HomeMy WebLinkAbout01/2018 SOUTHOLD PLANNING BOARD
Monthly Report — January 2018
Summary
Planning Board Applications
Currently Processing
Subdivisions: 19
Site Plans: 14
New this Month
Subdivisions: 3
Site Plans: 1
Application Fees Collected: $2,000.00
Site Plan and Subdivision Application Concept Meetings: 3
Site Plan and Subdivision Application Pre-submission Meetings: 4
Counter Visits: 24
Phone Calls: 154
Actions Taken at Public Meeting
Public Hearings: 1
Site Plan Decisions: 3
Subdivision Decisions: 5
Referrals for Comments from Other Boards
Town Board Local Laws & Other Issues: 1 Completed
LWRP Consistency Reviews: 25
Comprehensive Plan Update
1. Updated the Comprehensive Plan website
2. Submitted Status Report to New York Department of State regarding the grant to
complete the Comprehensive Plan update: One chapter left to complete (10 completed to
date)
Planning Board Monthly Report - Subdivisions
Hamlet Project Name Tax Map# Type Zone Status Submitted Recent Activity Next Step/Comment
Cutchogue
Baxter, William J., Jr. 102.-5-9.4 STANDARD HB CONDITIONAL 12/31/2007 9/11/17 Waiting for Final Plat
SUBDIVISION PRELIMINARY Appl to be submitted
APPROVAL
SU BDIV
Big Bing & Little Bing 95.-1-7.2 CONSERVATION AC R- CONDITIONAL 9/10/2015 2/22/2018 Referral review
SUBDIVISION 80 SKETCH pending
APPROVAL
SU BDIV
Hazard Subdivision 103.-2-1 STANDARD R-80 CONDITIONAL 8/18/2016 2/5/18 Waiting for conditions
SUBDIVISION FINAL to be met
APPROVAL
SU BDIV
Krupski & Zachariadis 97.-8-31.2 RESUBDIVISION R-80 FINAL PLAT 4/8/2016 2/5/2018 Waiting on applicant
(LOT LINE APPROVAL to submit filed deeds.
MODIFICATION) SUBDIV
Ovsianik Lot Line 97.-2-16.5 RESUBDIVISION R-80 PENDING 3/13/2015 2/5/18 In process of
(LOT LINE addressing public
MODIFICATION)
hearing comments
RCC Sacred Heart 96.-5-12.2 STANDARD AC CONDITIONAL 8/2/2017 1/8/18 Waiting for conditions
SUBDIVISION FINAL to be met
APPROVAL
SU BDIV
Fishers
Island
Kernan and Our Lady of Grace 10.-8-12 RESUBDIVISION R-80 PENDING 1/17/2018 2/6/2018 Applic. incomplete
Church (LOT LINE
MODIFICATION)
Greenport
Chloem, Patterson and Tuccio 56.-4-22 RESUBDIVISION MII PENDING 2/22/2018
Lot Line (LOT LINE
MODIFICATION)
Friday,February 23,2018 Page 1 of 3
Hamlet Project Name Tax Map# Type Zone Status Submitted RecentActivity Next Step/Comment
Mattituck
Estates at Royalton 113.-7-19.23 STANDARD AC FINAL PLAT 6/11/2015 2/22/18 Waiting for filed maps
SUBDIVISION APPROVAL to be submitted
SU BDIV
Harold R. Reeve & Sons 140.-1-6 STANDARD B CONDITIONAL 2/18/2014 2/15/18 SEQRA
SUBDIVISION SKETCH
APPROVAL
SU BDIV
Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL 4/6/2012 8/14/17 Waiting for applicant
Partnership SUBDIVISION PRELIMINARY to fulfill conditions
APPROVAL
SU BDIV
Noone, Margaret 143.-1-4.1 STANDARD B and FINAL PLAT 1/8/2010 1/22/2018 Waiting on maps to
SUBDIVISION R-40 APPROVAL be filed.
SU BDIV
Quantuck Properties 107.-10-8 CONSERVATION AC CONDITIONAL 2/24/2017 1/11/18 Final Plat Applic
SUBDIVISION SKETCH Completeness Review
APPROVAL
SU BDIV
Orient
Droskoski and Sepenoski 18.-4-7.4 RESUBDIVISION R-80 FINAL PLAT 1/26/2011 1/8/18 Waiting for filed
(LOT LINE APPROVAL deeds to be submitted
MODIFICATION) SUBDIV
Gonzalez Standard 27.-1-9 STANDARD R-80 PENDING 12/1/2017 2/5/2018 Conditional Sketch
Subdivision 2 SUBDIVISION decision 3/13/18
Mazzoni, 500 Soundview 13.-2-8.2 STANDARD CONDITIONAL 3/12/2014 1/22/2018 Prelim Plat Applic
Drive, LLC SUBDIVISION SKETCH incomplete
APPROVAL
SU BDIV
Tuthill Conservation 17.-4-16 CONSERVATION R-80, PENDING 7/2/2014 4/4/16 Waiting on DEIS
Subdivision SUBDIVISION R-200
Peconic
Friday,February 23,2018 Page 2 of 3
Hamlet Project Name Tax Map# Type Zone Status Submitted RecentActivity Next Step/Comment
Brantuk & Pearson 75.-6-7.2 RESUBDIVISION A-C PENDING 4/27/2011 2/1/18 Agent given an
(LOT LINE additional copy of
MODIFICATION)
required materials
Southold
Sutton, Alexander &Tracy 78.-9-54 STANDARD CONDITIONAL 5/20/2008 1/8/18 Waiting for applicant
SUBDIVISION FINAL to fulfill conditions
APPROVAL
SU BDIV
Friday,February 23,2018 Page 3 of 3
Planning Board Monthly Report - Site Plans
Hamlet Project Name Tax Map# Type Zone Status Submitted Next Step, Comment
Cutchogue
Chris Mohr Lawncare Shed 96.-1-20.1 SITE PLAN LI PENDING 2/13/2017 Amended application found
Amended incomplete at PB's 3/13/17
work session; PB required
additional information and
revised site plan; not
submitted as of 2/23/18
North Fork Recycling (NF 83.-3-4.7 SITE PLAN LI PENDING 3/30/2017 Complete SEQRA/Referral
Sanitation) review - 3/2018
Laurel
Northside Beverage 122.-7-6.7 SITE PLAN B PENDING 6/20/2017 Public hearing held and
closed; revisions to site plan
required, SCDHS approval
outstanding
Mattituck
870 Love Lane Professional 140.-2-17 SITE PLAN RO PENDING 5/31/2017 SEAR Neg Dec 1/8/18;
Office & Apartment revisions required to site
plan; SCDHS
Verizon Wireless at Laurel 122.-6-35.4 SITE PLAN B PENDING 8/24/2017 Incomplete application
Stone 2/23/18
Orient
Tenedios Agricultural Barn 19.-1-1.4 SITE PLAN R-200 PENDING 6/28/2017 Public hearing 9/11/17
adjourned w/out date
pending information to be
submitted
Verizon Wireless at MGH 15.-9-8.1 SITE PLAN MII PENDING 6/2/2016 Approved with conditions
Enterprises WIRELESS 4/10/17 - proof of C&R filing
required prior to Chairman
endorsing site plan
Friday,February 23,2018 Page 1 of 2
Hamlet Project Name Tax Map# Type Zone Status Submitted Next Step, Comment
Peconic
Berry & Berry, LLC 75.-5-13 SITE PLAN B PENDING 12/2/2014 Referral review conducted
7/6/15; SCDHS approval
obtained 6/15/17; NYSDOT
approval and plans to be
submitted to PB for final
review before determination
Pindar Storage Building 85.-2-9.2 SITE PLAN AC PENDING 1/26/2018 Public Hearing 3/12/18
Southold
First Universalist Church 63.-6-6.1 SITE PLAN RO PENDING 10/12/2017 Application incomplete
11/7/17; Waiting on required
information
Purita Wine Production 51.-3-5.1 AMENDED SITE AC PENDING 12/20/2017 Set the Public Hearing
Building PLAN
Southold Gas Station & 55.-5-2.2 SITE PLAN B PENDING 3/31/2015 Applicant preparing FEIS for
Convenience Store SEQRA
Surrey Lane Vineyard 69.-5-18.1 SITE PLAN AC PENDING 8/29/2016 Traffic Safety Evaluation
required at PBs 6/26/17 work
session and not submitted as
of 1/11/18
The Enclaves Hotel 63.-3-15 SITE PLAN HB PENDING 1/31/2017 ZBA Special exception/SEQRA
in process
Friday,February 23,2018 Page 2 of 2