Loading...
HomeMy WebLinkAbout06/2017 SOUTHOLD PLANNING BOARD Monthly Report June 2017 Summary Planning Board Applications Currently Processing Subdivisions: 19 Site Plans: 24 Application Fees Collected: $2,290.20 Park & Playground Fees Collected: $7,000 Admin./Inspection Fees Collected: $4,000 Site Plan and Subdivision Application Concept Meetings: 1 Site Plan and Subdivision Application Pre-submission Meetings: 6 Counter Visits: 56 Phone Calls: 186 Actions Taken at Public Meeting Public Hearings: 3 Site Plan Decisions: 6 Subdivision Decisions: 5 Referrals for Comments from Other Boards ZBA: 1 Received, 4 Completed LWRP Consistency Reviews: 20 Planning Board Monthly Report - Subdivisions IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ /ǒƷĭŷƚŭǒĻ Baxter, William J., Jr. 102.-5-9.4 STANDARD HB CONDITIONAL ЊЋΉЌЊΉЋЉЉААΉЊЊΉЊА Requested new FEAF SUBDIVISIONSKETCH conducting SEQR APPROVAL review SUBDIV Big Bing & Little Bing95.-1-7.2 CONSERVATION AC R-PENDING ВΉЊЉΉЋЉЊЎЋΉЋАΉЊА Waiting on County SUBDIVISION 80 PDR STANDARD R-80 CONDITIONAL БΉЊБΉЋЉЊЏАΉЊЉΉЊА Hazard Subdivision103.-2-1Revised plans under SUBDIVISIONSKETCH review APPROVAL SUBDIV Joint Industry Board & 83.-2-17.1 RESUBDIVISION AC PENDING ЋΉЊЋΉЋЉЊЏЍΉАΉЊА Waiting on new design (LOT LINE McBride MODIFICATION) Krupski & Zachariadis 97.-8-31.2 RESUBDIVISION R-80 PENDING ЍΉБΉЋЉЊЏЍΉЊЉΉЊА Waiting on applicant (LOT LINE to submit Access MODIFICATION) Easement STANDARD R-40 CONDITIONAL ЍΉЋЋΉЋЉЊЎЍΉЊЊΉЊА Martz, Theodore C., Jr.104.-12-6.1Waiting on applicant SUBDIVISIONFINAL to fulfill conditions APPROVAL SUBDIV CźƭŷĻƩƭ LƭƌğƓķ Miller & Brinckerhoff8.-1-6.5 RESUBDIVISION R-120 PENDING ЊΉЊБΉЋЉЊААΉЊЉΉЊА Public Hearing held & (LOT LINE closed MODIFICATION) STANDARD R-80 CONDITIONAL ЊЋΉЋЌΉЋЉЊЌЍΉЊЊΉЊА Ridgway, EPR F.I. Trust II 6.-1-3Waiting on applicant SUBDIVISIONFINAL to fulfill conditions APPROVAL SUBDIV ağƷƷźƷǒĭƉ Thursday, July 27, 2017Page 1 of 3 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ Estates at Royalton113.-7-19.23 STANDARD AC CONDITIONAL ЏΉЊЊΉЋЉЊЎАΉЋЉΉЊА Waiting on applicant SUBDIVISIONFINAL to fulfill conditions APPROVAL SUBDIV Harold R. Reeve & Sons140.-1-6 STANDARD B CONDITIONAL ЋΉЊБΉЋЉЊЍАΉЋЉΉЊА Waiting for applicant SUBDIVISIONSKETCH to submit requested APPROVAL info SUBDIV Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL ЍΉЏΉЋЉЊЋЍΉЊБΉЊА Reviewing revised SUBDIVISIONSKETCH Partnershipmaps & SEQRA APPROVAL SUBDIV Noone, Margaret143.-1-4.1 STANDARD B and CONDITIONAL ЊΉБΉЋЉЊЉЍΉЋЍΉЊА Waiting on applicant SUBDIVISION R-40 FINAL to fulfill conditions APPROVAL SUBDIV Quantuck Properties107.-10-8 CONSERVATION AC PENDING ЋΉЋЍΉЋЉЊАЍΉЊЉΉЊА Waiting for applicant SUBDIVISION to submit viewshed analysis requested by Planning Board hƩźĻƓƷ Mazzoni, 500 Soundview 13.-2-8.2 STANDARD PENDING ЌΉЊЋΉЋЉЊЍАΉЊЉΉЊА Reviewing revised SUBDIVISION Drive, LLCplans and application completeness, public hearing to be set for September Orient Acres14.-2-25 STANDARD R-80 PENDING ЎΉЊАΉЋЉЊЏЏΉЏΉЊЏ Applic. incomplete SUBDIVISION Tuthill Conservation 17.-4-16 CONSERVATION R-80, PENDING АΉЋΉЋЉЊЍЍΉЍΉЊЏ Waiting on DEIS SUBDIVISION R-200 Subdivision tĻĭƚƓźĭ Thursday, July 27, 2017Page 2 of 3 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ Beninati, Lee & Marie74.-3-15 STANDARD RO CONDITIONAL ЎΉЊЌΉЋЉЊЍЌΉЋЊΉЊЏ Waiting for requested SUBDIVISIONSKETCH items to be APPROVAL submitted. SUBDIV {ƚǒƷŷƚƌķ Stanton, Phil & Jennifer64.-1-29 STANDARD R-40 CONDITIONAL ЊΉЊБΉЋЉЊЋЎΉБΉЊА Final Plat Approval SUBDIVISIONFINAL expired before map APPROVAL filed with County. SUBDIV Seeking re-issue of Final Approval Sutton, Alexander & Tracy78.-9-54 STANDARD CONDITIONAL ЎΉЋЉΉЋЉЉБЊΉЌЉΉЊА Awaiting applicant's SUBDIVISIONPRELIMINARY SCDHS approval APPROVAL SUBDIV Thursday, July 27, 2017Page 3 of 3 Planning Board Monthly Report - Site Plans IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ /ǒƷĭŷƚŭǒĻ Chris Mohr Lawncare Shed 96.-1-20.1 SITE PLAN LI PENDING 2/13/2017Amended application found Amendedincomplete at PB's 3/13/17 work session; PB required additional information and revised site plan E. Lopez Nursery97.-3-3.1 SITE PLAN LB PENDING 6/23/2016Referral review conducted 10/24/16; NYSDOT permit needs to be obtained; PB required revisions to site plan and have not been submitted as of 7/26/17 East End Tick & Mosquito 97.-3-2 SITE PLAN LB PENDING 3/30/2015Waiting on ZBA variances Pest Controlrequired Heritage at Cutchogue 2015102.-1-33.3 SITE PLAN HD PENDING 1/2/2015Conditional Approval RESIDENTIAL 11/7/16. Preliminary approval for site work to begin 7/10/17. SITE PLAN LI PENDING North Fork Recycling (NF 83.-3-4.73/30/2017Public hearing held/closed; Sanitation)referral review to be conducted at 8/14/17 work session Sannino Winery & Tasting 101.-1-14.4 SITE PLAN AC PENDING 8/25/2015PB granted conditional Roomapproval 6/5/17; applicant must successfully meet all conditions prior to the Chairman endorsing a site plan CźƭŷĻƩƭ LƭƌğƓķ Thursday, July 27, 2017Page 1 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ Fox Lane Residences12.-1-1.2 SITE PLAN AHD PENDING 2/1/2016SCDHS approval outstanding as of 7/26/17 DƩĻĻƓƦƚƩƷ Front Street Offices45.-7-5.3 SITE PLAN R-40 PENDING 6/9/2017Application accepted as complete for review; public hearing to be set for 9/11/17; referrals distributed \[ğǒƩĻƌ Bennett Properties122.-6-29.4 SITE PLAN B PENDING 5/31/2017New site plan application found incomplete for review at PB's 4/24/17 work session; revisions and additional information required Country Car Wash Additions125.-1-19.5 SITE PLAN B PENDING 6/17/2016Amended site plan application requires special exception and an area variances as per the revised notice of disapproval issued 11/16/16; Northside Beverage122.-7-6.7 SITE PLAN B PENDING 6/20/2017Application found incomplete 7/10/17 hƩźĻƓƷ Tenedios Agricultural Barn19.-1-1.4 SITE PLAN R-200 PENDING 6/28/2017Accepted as complete for review 7/24/17; public hearing to be set for 9/11/17; referrals distributed Verizon Wireless at MGH 15.-9-8.1 SITE PLAN MII PENDING 6/2/2016Approved with conditions WIRELESS Enterprises4/10/17 - proof of C&R filing required prior to Chairman endorsing site plan tĻĭƚƓźĭ Thursday, July 27, 2017Page 2 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ Berry & Berry, LLC75.-5-13 SITE PLAN B PENDING 12/2/2014Public hearing held and closed 6/1/15; referral review conducted 7/6/15; SCDHS approval obtained 6/15/17; final information and plans to be submitted to PB for final review {ƚǒƷŷƚƌķ Jemcap Gas Station & 55.-5-9.1 SITE PLAN B PENDING 4/18/2017New site plan application Conveinence Store found incomplete at PB's 5/22/17 work session; revised site plan and additional information required Lucas Ford59.-3-32.1 AMENDED SITE B PENDING 12/10/2014Applicant working on new PLAN design with Ford Company after preliminary (positive) review with ARC North Fork SurgiCenter63.-3-2 SITE PLAN LI PENDING 5/16/2017referrals distributed; public hearing held open 7/10/17; to be continued 8/14/17 North Fork United Methodist 63.-1-15 SITE PLAN LB PENDING 2/10/2016referral review conducted ChurchMay 2017; requiring: SCDHS approval, revisions to site plan and supplemental plans; staff has been working with applicant to provide all necessary information on site plan as of 7/26/17 Thursday, July 27, 2017Page 3 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ North Fork Woodworks61.-1-15.3 SITE PLAN HB PENDING 3/9/2016Application found incomplete at PB's 3/21/16 work session; revisions and additional information required and not submitted as of 7/26/17 One Woman Vineyard Ag 51.-3-4.14 SITE PLAN AC PENDING 4/11/2017Public hearing held/closed Storage Barn6/5/17; referral review conducted at 6/26/17 work session; revisions required SITE PLAN AC PENDING Purita Winery51.-3-58/2/2016Approved 5/8/17 with conditions to be met prior to the Chairman endorsing the site plan Southold Gas Station & 55.-5-2.2 SITE PLAN B PENDING 3/31/2015DEIS found adequate for Convenience Storepublic review on 7/10/17 and has been distributed appropriately for public comment; Surrey Lane Vineyard69.-5-18.1 SITE PLAN AC PENDING 8/29/2016Traffic Safety Evaluation required at PBs 6/26/17 work session and not submitted as of 7/26/17 The Enclaves Hotel63.-3-15 SITE PLAN HB PENDING 1/31/2017New site plan application requires special exception from ZBA; ZBA to take lead agency for SEQR Thursday, July 27, 2017Page 4 of 4