HomeMy WebLinkAbout05/2017 SOUTHOLD PLANNING BOARD Monthly Report May 2017 Summary Planning Board Applications Currently Processing Subdivisions: 18 Site Plans: 22 Application Fees Collected: $4,796 Admin./Inspection Fees Collected: $4,000 Tree Fund Fees Collected: $500 Site Plan and Subdivision Application Concept Meetings: 1 Site Plan and Subdivision Application Pre-submission Meetings: 2 Counter Visits: 64 Phone Calls: 214 Actions Taken at Public Meeting Public Hearings: 3 Site Plan Decisions: 8 Subdivision Decisions: 1 Referrals for Comments from Other Boards ZBA: 2 Received LWRP Consistency Reviews: 11 Planning Board Monthly Report - Subdivisions IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ /ǒƷĭŷƚŭǒĻ Big Bing & Little Bing95.-1-7.2 CONSERVATION AC R-PENDING ВΉЊЉΉЋЉЊЎЋΉЋАΉЊА Waiting on County SUBDIVISION 80 PDR & revised plans Hazard Subdivision103.-2-1 STANDARD R-80 CONDITIONAL БΉЊБΉЋЉЊЏЌΉЊЌΉЊА Waiting on revised SUBDIVISIONSKETCH plans APPROVAL SUBDIV RESUBDIVISION AC PENDING ЋΉЊЋΉЋЉЊЏЍΉАΉЊА Joint Industry Board & 83.-2-17.1Waiting on new design (LOT LINE McBride MODIFICATION) Krupski & Zachariadis 97.-8-31.2 RESUBDIVISION R-80 PENDING ЍΉБΉЋЉЊЏЍΉЊЉΉЊА Waiting on applicant (LOT LINE to submit info MODIFICATION) Martz, Theodore C., Jr.104.-12-6.1 STANDARD R-40 CONDITIONAL ЍΉЋЋΉЋЉЊЎЍΉЊЊΉЊА Granted Conditional SUBDIVISIONPRELIMINARY Final Approval APPROVAL SUBDIV CźƭŷĻƩƭ LƭƌğƓķ Miller & Brinckerhoff8.-1-6.5 RESUBDIVISION R-120 PENDING ЊΉЊБΉЋЉЊАЋΉЊАΉЊА June 5, 2017 Planning (LOT LINE Board set Public MODIFICATION) Hearing Ridgway, EPR F.I. Trust II 6.-1-3 STANDARD R-80 CONDITIONAL ЊЋΉЋЌΉЋЉЊЌЍΉЊЊΉЊА Conditional SUBDIVISIONPRELIMINARY Preliminary Plat APPROVAL Approval extension SUBDIV ağƷƷźƷǒĭƉ Friday, June 16, 2017Page 1 of 3 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ Estates at Royalton113.-7-19.23 STANDARD AC CONDITIONAL ЏΉЊЊΉЋЉЊЎЍΉЊЊΉЊА Granted Conditional SUBDIVISIONFINAL Final Approval - APPROVAL Granted Special SUBDIV Request to Proceed with road and drainage. Harold R. Reeve & Sons140.-1-6 STANDARD B CONDITIONAL ЋΉЊБΉЋЉЊЍЊΉЋЌΉЊА SEQR review for SUBDIVISIONSKETCH subdivision and APPROVAL change of zone in SUBDIV process. Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL ЍΉЏΉЋЉЊЋЍΉЊБΉЊА Reviewing revised SUBDIVISIONSKETCH Partnershipmaps & SEQRA APPROVAL SUBDIV Noone, Margaret143.-1-4.1 STANDARD B and CONDITIONAL ЊΉБΉЋЉЊЉЍΉЋЍΉЊА Checking Final Plat SUBDIVISION R-40 PRELIMINARY Application for APPROVAL completeness SUBDIV Quantuck Properties107.-10-8 CONSERVATION AC PENDING ЋΉЋЍΉЋЉЊАЍΉЊЉΉЊА Waiting for applicant SUBDIVISION to submit complete application hƩźĻƓƷ Mazzoni, 500 Soundview 13.-2-8.2 STANDARD PENDING ЌΉЊЋΉЋЉЊЍЋΉЏΉЊА Reviewed Report on SUBDIVISION Drive, LLCWater quality from applicant Orient Acres14.-2-25 STANDARD R-80 PENDING ЎΉЊАΉЋЉЊЏЏΉЏΉЊЏ Applic. incomplete SUBDIVISION Tuthill Conservation 17.-4-16 CONSERVATION R-80, PENDING АΉЋΉЋЉЊЍЍΉЍΉЊЏ Waiting on DEIS SUBDIVISION R-200 Subdivision tĻĭƚƓźĭ Friday, June 16, 2017Page 2 of 3 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ œƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ Beninati, Lee & Marie74.-3-15 STANDARD RO CONDITIONAL ЎΉЊЌΉЋЉЊЍЌΉЋЊΉЊЏ Waiting for requested SUBDIVISIONSKETCH items to be APPROVAL submitted. SUBDIV {ƚǒƷŷƚƌķ Stanton, Phil & Jennifer64.-1-29 STANDARD R-40 CONDITIONAL ЊΉЊБΉЋЉЊЋЎΉБΉЊА Final Plat Approved. SUBDIVISIONFINAL Waiting for Proof of APPROVAL Filing SUBDIV STANDARD CONDITIONAL ЎΉЋЉΉЋЉЉБЊΉЌЉΉЊА Sutton, Alexander & Tracy78.-9-54Awaiting applicant's SUBDIVISIONPRELIMINARY SCDHS approval APPROVAL SUBDIV Friday, June 16, 2017Page 3 of 3 Planning Board Monthly Report - Site Plans IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ /ǒƷĭŷƚŭǒĻ Chris Mohr Lawncare Shed 96.-1-20.1 SITE PLAN LI PENDING 2/13/2017Amended application found Amendedincomplete at PB's 3/13/17 work session; PB required additional information and revised site plan E. Lopez Nursery97.-3-3.1 SITE PLAN LB PENDING 6/23/2016Referral review conducted 10/24/16; NYSDOT permit needs to be obtained; PB required revisions to site plan and have not been submitted as of 6/15/17 East End Tick & Mosquito 97.-3-2 SITE PLAN LB PENDING 3/30/2015PB re-opened the public Pest Controlhearing on 5/8/17 to give adjacent property owners and general public the opportunity to comment on the revised site plan; PB reviewed revised plans and public hearing comments; ZBA variances still need to be obtained Heritage at Cutchogue 2015102.-1-33.3 SITE PLAN HD PENDING 1/2/2015Approved with 43 conditions RESIDENTIAL 11/7/16; Conditions must be met before the Chairman can endorse the site plan SITE PLAN LI PENDING North Fork Recycling (NF 83.-3-4.73/30/2017Public hearing held/closed Sanitation)6/5/17; referral review to be conducted at 6/26/17 work session Friday, June 16, 2017Page 1 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ Sannino Winery & Tasting 101.-1-14.4 SITE PLAN AC PENDING 8/25/2015PB granted conditional Roomapproval 6/5/17; applicant must successfully meet all conditions prior to the Chariman endorsing a site plan CźƭŷĻƩƭ LƭƌğƓķ Fox Lane Residences12.-1-1.2 SITE PLAN AHD PENDING 2/1/2016SCDHS approval outstanding as of 6/15/17 DƩĻĻƓƦƚƩƷ Schriever Front Street Offices45.-7-5.3 SITE PLAN R-40 PENDING 6/9/2017 \[ğǒƩĻƌ Bennett Properties122.-6-29.4 SITE PLAN B PENDING 5/31/2017New site plan application found incomplete for review at PB's 4/24/17 work session; revisions and additional information required Country Car Wash Additions125.-1-19.5 SITE PLAN B PENDING 6/17/2016Amended site plan application requires special exception and an area variances as per the revised notice of disapproval issued 11/16/16; hƩźĻƓƷ Verizon Wireless at MGH 15.-9-8.1 SITE PLAN MII PENDING 6/2/2016Approved with conditions WIRELESS Enterprises4/10/17 - proof of C&R filing required prior to Chairman endorsing site plan tĻĭƚƓźĭ Friday, June 16, 2017Page 2 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ Berry & Berry, LLC75.-5-13 SITE PLAN B PENDING 12/2/2014Public hearing held and closed 6/1/15; referral review conducted 7/6/15; SCDHS approval outstanding as of 6/15/17 {ƚǒƷŷƚƌķ Jemcap Gas Station & 55.-5-9.1 SITE PLAN B PENDING 4/18/2017New site plan application Conveinence Store found incomplete at PB's 5/22/17 work session; revised site plan and additional information required Lucas Ford59.-3-32.1 AMENDED SITE B PENDING 12/10/2014Applicant working on new PLAN design with Ford Company after preliminary (positive) review with ARC North Fork SurgiCenter63.-3-2 SITE PLAN LI PENDING 5/16/2017Application found complete at PBs 6/5/17 work session; referrals distributed and public hearing set for 7/10/17 SITE PLAN LB PENDING North Fork United Methodist 63.-1-152/10/2016Application accepted as Churchcomplete for review; public hearing held 4/10/17 & 5/8/17; referral review conducted 5/8/17 with revisions required to the site plan North Fork Woodworks61.-1-15.3 SITE PLAN HB PENDING 3/9/2016Application found incomplete at PB's 3/21/16 work session; revisions and additional information required and not submitted as of 6/15/17 Friday, June 16, 2017Page 3 of 4 IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦϜƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ One Woman Vineyard Ag 51.-3-4.14 SITE PLAN AC PENDING 4/11/2017Public hearing held/closed Storage Barn6/5/17; referral review to be conducted at 6/26/17 work session Purita Winery51.-3-5 SITE PLAN AC PENDING 8/2/2016Approved 5/8/17 with conditions to be met prior to the Chairman endorsing the site plan Southold Gas Station & 55.-5-2.2 SITE PLAN B PENDING 3/31/2015DEIS found inadequate for Convenience Storepublic review on 10/24/16 and for a second time on 1/23/17; required information (including visual impact analysis) has been submitted and to be reviewed for adequacy at PBs 6/26/17 work session Surrey Lane Vineyard69.-5-18.1 SITE PLAN AC PENDING 8/29/2016Public hearing re-opened and closed 6/5/17; referral review to be conducted at PBs 6/26/17 work session The Enclaves Hotel63.-3-15 SITE PLAN HB PENDING 1/31/2017New site plan application requires special exception from ZBA; ZBA to take lead agency for SEQR Friday, June 16, 2017Page 4 of 4