HomeMy WebLinkAboutTR-298 TOWN OF SOUTHOLD
BOARD OF SOUTHOLD TOWN TRUSTEES
SOUTHOLD, NEW YORK
WETLANDS PERMIT
This-Wetlands Permit No. .. 298........... has been granted by the. Town Trustees according to
information furnished in Application No. ..381.. .... ...filed by-Applicant John Wesmantle for L.I L. s
. .... .. on . MaY...29, 19...$6... A map of the proposed work will be kept
on file in the Trustee Office under the application number given:
Permit granted to do the following work ..Approval to bury, trench and backf ill to install
69KV electric cable conduits at submarine crossing from Island View Lane
(Southold) to Rocky Shore (Shelter Island) .
.................................................................................................................................................................
Location of property on which work to be done ......Island,View.. ............................Lane ....................
. .......
.................................................................................................................................................................
Creek, Bay or Harbor fronting property .................................................................................................
..................................................................................................................................................I..............
Sizeof work: Length .............................................................................................................................
Width .............................................................................................................................
HeightAbove High Water ..............................................................................................
DepthBelow Low Water .................................................................................................
_Yards to be Excavated .....................................................................................................
Yardsto be Filled .........................................................................................................
Manner in which material is to be removed or deposited .........................................................................
.................................................................................................................................................................
Intendeduse of property .........................................................................................................................
.................................................................................................................................................................
Conditionsif any .....................................................................................................................................
.........................................................................................................................................................
Expiration Date a....................
Number of Inspections Required .?;Trustees..are to be,notified„uP.RR.. omR7elian..of..tJae....
work.Inspection Fees ........ %.0 .P.ad
.........................................................................................................
Liability Policies in the Amount of .........................................................................................................
The validity of this permit is or may be subject to the approval of other governmental or municipal
authorities. The Town accepts no responsibility in applying for or obtaining such approval. In the
event that such approval is necessary, the holder of this permit shall not commence operations here-
under until such approval has been obtained in writing. The failure to obtain such other approval when
required shall subject this permit to immediate revocation by the Trustees upon recejpt by the
1 Trustees- of written notice from such other governmental or municipal authorities of its refusal or
�1 disapproval.
J
TRUSTEES SCOTT L. 14APRIS
Supervisor
ft M. Brederneyer, 111, President d Henry P_ Smith, Vice President
Albert J. Krupski, Jr: ® Town Ha} Bo95 Main Road
P.O0 Box 1179
i John L. Bednoski, Jr.
� John B. Tuthill Southold, New York 11971
BOARD OF TOWN TRUSTEES Fax (516) 765-1823
Telephone (516) 765-1892 TOWN OF SOUT14OLD Telephone(516) 765-1800
March 23, 1990
MauriceIP. Fitzgerald
Manager, Permit Division
Long Island Lighting Co.
1660 Walt Whitman Road
Melville, NY 11747
RE: Wetlands Permit #298
i
Dear Mr. Fitzgerald:
The following action was taken by the Southold Town Board of
{ Trustees on Thursday, March 22, 1990:
RESOLVED that the Southold Town Board of Trustees extend Permit
#298 from December 31, 1989 to March 9, 1993.
Enclosed please find a check in the amount of $115 .00, which
represents the difference of the wetlands application fee of
$150.00 which you paid and the renewal fee of $35.
If you have any questions, please do not hesitate to contact
this office.
Ve truly yours,
n . Bred. yer, III
resident, Board of Trustees
JMB: jmt
enc.
a �3
TELEPHONT
(5.16)765-1892 -
BOARD OF TOWN TRUSTEES
TOWN OF SOUTHOLD
Town Hall, 53095 Main Road
P.O. Box-728
Southold, New York 11971
` APPLICATION IS HEREBY MADE TO THE TOWN TRUSTEES OF. 'THE: TOWN OF
SOUTHOLD, SUFFOLK COUNTY, NEW YORK FOR THE ISSUANCE OF APERMIT
PURSUANT. TO: THE. LAWS , ORDINANCES AND REGULATIONS GOVERNING THE
COASTAL AND INTERIOR WETLANDS, FLOOD PLAINS AND DRAINAGE AREAS .
-OF. THE TOWN OF: SOUTHOLD, AND. THE -ISSUANCE OF PERMITS PURSUANT'
TO CHAPTER. 32 OF THE CODES OF THE TOWN OF SOUTHOLD. .
APPLICATION NO..,�U _DATE OF APPLICATION
IDENTITY OF . APPLICANT. Long Island Lighting.Co. fff ---PHONE NO
ADDRESS OF APPLICANT 1660 Walt Whitman Road
Melville, NY 11747
TAX. MAP. NO. 1000-057-02 - N/A (public Street).
AGENT__John- A _WeiSmaxitle�_�z,P __---_--(516)-420-613'0--_—_—__—`---PHONE NO .---
PERM IT REQUESTED TO Trench, bury and backfill to install 69KV electric cable
conduits at submarine crossing.
LOCAT ION OF PROPERTY FOR WH I CH. PERM I T WANTED From Island View Vane
(Southold) to Rocky Shore Road (Shelter Island) .
--------------
HOME ADDRESS OF PERMIT APPLICANT IF DIFFERENT FROM AFORESAID LOCATION___
N/A
CREEK, BAY OR. HARBOR FRONT IMG PROPERTY Conkling Point - Crescent Beach
S I zE OF PROPOSED WORK__Approximately 13,600 sq_ft. l crossing)_____ '
LENGTH_^ 3400' - (total ten h--Of crossing)__--
_�--- — -----------------------_.
WIDTH approximately 4'
HEIGHT ABOVE HIGH WATER - N/A
DEPTH BELOW LOW WATER--Ran es from 0' at shoreline t0 -85 '
YARDS TO BE EXCAVATED_: approx_ 2000 yd5 (t0tal croS.2ing) ______________
YARDS TO BE F I u ED apgrox. 2000^"'yds_ (backfill trench with excavated material)
WIDTH OF CANAL , CREEK OR BAY FRONTING PROPERTY 3400'
DEPTH AT LOW- TIDE 0'-85'
AVERAGE RISE IN SIDE 2.3'
.DISTANCE TO THE NEAREST CHANNEL_NA-____FT.
DISTANCE. PROJECT EXTENDS BEYOND SIMILAR PROJECTS IN. THE AREA NA FT.
IS THIS FOR PRIVATE OR BUSINESS USE.? Business
AREA ZONING-- Residential
MANNER IN WHICH MATERIAL WILL BE REMOVED OR DEPOSITED Probably either
jetting and/or clam shell dredge
INTENDED USE OF PROPERTY improve. reliability of electric. service
DESCRIBE ANY KNOWN PRIOR OPERATIONS CONDUCTED ON THE PREMISE
Previous cable laid between Conkling Point & Crescent Beach about 20'years ago.
-----------------------
AND WHETHER ANY PRIOR LICENSE OR PERMITS HAVE BEEN ISSUED TO' ERRECT
STRUCTURES OR TO DREDGE OR DEPOSIT FILL ON SAID PREMISES AND WHETHER
. ANY PERMITS OR LICENSES. WERE EVER. SUSPENDED OR . REVOKED BY A GOVERNMENTAL
AGENCY
---------------- ------------ I
None known
DES.CRI.BE FULLY THE REHABILITATION AND PROPOSED. CONDITION OF THE
PREMISES AFTER THE WORK. IS COMPLETED. INCLUDE. AN ADDITIONAL SURVEY OF
THE PROJECT . SITE IF NECESSARY
Excavated material will be used as backfill over the buried cable.
-----------------------------------------------------------------
------------------ j
WRITTEN 'CONSENT OF THE OWNER OF THE PROPERTY, IF NOT THE SAME. AS THE
APPLICANT. Highway work permit to be issued by Town.
ARE THERE . ANY COVENANTS OR RESTRICTIONS IN YOUR DEED THAT WOULD
PROHIBIT THIS PROJECT? NA
BOARD OF TOWN TRUSTEES
fj
TOWN OF SOUTHOLD
SHORT ENVIRONMENTAL ASSFSSMENT FORM
Project information(To be completed by Applicant or Project sponsor) -
1 APPhcautlsponsor 2. Project Name
—LonQ Island Lid-iting do. Buell to Southold Underground round C able System
3. Project location. Southold,_ Shelter Island, Southampton, North.Haven Sag Harbor, East
Municipality Hamton County Suffolk.
4. Is prro}�pjosed action:
g New..., .❑ Expansion E.Modificationfalteration
5 Describe project briefly: -
Installation of 69kV pipe-type cable system (underground) from
Southold to Buell Substations, making 3 sLkm rine crossings. The route follows
existing roads. (See attached Project Siml for additional details) .
6. Precise location(road intersections,prominent landmarks,etc.or provide map)
See attached Project Sumiu:y
7. Amount of land affected
Initially acres Ultimately aces
a. Will proposed action comply with existing zoning or other existing land use restrictions?
KI Yes ❑ No If No,describe briefly -
9. What is present land use in vicinity of project?
Z Residential ❑ Industrial ❑ Commercial ❑ Agriculture ❑ Parklandlopen space ❑ Other
Describe:.
10. Does action involve a permitlapproval,or funding,now or ultimately,from any other governmental.agency(Federal,state or local)?
® Yes ❑ No If yes,list agency(s).and permit/approvals
Corps of Engineers - Construction
NYS Dept. of Environmental Conservation - Wetlands
11. Does any aspect of the action have a currently valid permit or approval?
❑ Yes 12 No If yes,list agency name and permitiapproval type
12. As result of proposed action will existing permit/approval require modification? -
❑. Yes ® No
CERTIFY THAT THE INFORMATION PROVIDED ABOVE IS TRUE TO THE.BEST OF MY KNOWLEDGE
Applicantfsponsor name: John A. Weismantle, V.P. Date:
Signature
PART II Environmental Assessment(To be completed by Agency) _
A. Does action exceed any Type I threshold in 6 NYCRR,Part 617.12? If yes,coordinate the review process and use the FULL,'LONG FORM EAF.
❑ Yes ❑ No
B. Will action receive coordinated review as provided for Unlisted Actions in 6 NYCRR,Part 617.7? If No,a negative declaration may be superceded by anothe
involved action.
❑ Yes ❑ No
C. Could action result in ANY adverse effects on,to,or arising from the following:(Answers may be handwritten, if legible)
Cl. Existing air quality,surface or groundwater quality or quantity,noise levels,existing traffic patterns,solid waste production or disposal,potential for erosior
drainage or flooding problems? Explain briefly:
C2. Historic,archeological,visual or aesthetic,or other natural or cultural resources;agricultural districts;or community or neighborhood character?Explain brie
C3. Vegetation or fauna,movement of fish or wildlife species,significant habitats,or threatened or endangered species? Explain briefly:
C4. A community's existing plans or goals as officially adopted,or a change in use or intensity of use of land or other natural resources? Explain briefly.
C5. Growth.subsequent development,or related activities likely to be induced by the proposed action? Explain briefly.
06. Secondary,cumulative,or other effects not identified in Cl-C6? Explain briefly.
C7. A change in use of either quantity or type of energy? Explain briefly.
PART III Determination of Significance(To be completed by Agency)
INSTRUCTIONS: For each adverse effect identified above, determine whether it is substantial, large, important or otherwise
significant. Each effect should be assessed in connection with its(a)setting(i.e. urban or rural);(b) probability of occurring;
(c)duration;(d) irreversibility;(e).geographic scope; and(f)magnitude. If necessary, add attachments or reference supporting
materials. Ensure that explanations contain sufficient detail to show that all relevant adverse impacts have been identified
and adequately addressed
❑ .Check this box if you have identified one or more potentially large or significant adverse impacts which.MAY occur. Then
proceed directly to the FULL/LONG FORM.EAF andlor prepare appositive declaration. '
❑ Check this box if you have determined, based on the information and analysis above and any supporting documentation,
that the proposed action WILL NOT result in any significant adverse.environmental impacts AND provide here, and on
attachments as necessary, the reasons supportng this determination: i
Agency Name Agency Preparers Name
P1epa1e1 Date
COUNTY OF SUFFOLK )
STATE OF NEW YORK ) SS:
John A. Weismantle BEING DULY SWORN DEPOSES
AND SAYS THAT HE IS THE APPLICANT FOR THE ABOVE DESCRIBED PERMITS,
AND THAT ALL STATEMENTS CONTAINED HEREIN ARE TRUE TO THE 'BEST.. -
. OF HIS KNOWLEDGE ANDBELIEF, THAT THE. WORK WILL BE DONE `IN THE
MANNER SET FORTH .. IN THIS APPLICATION AND AS MAY BE APPROVED BY
THE TOWN BOARD OF THE TOWN OF SOUTHOLD. THE APPLICANT 'AGREES' TO
HOLD . THE TOWN OF ,.SOUTHOLD AND .THE. TOWN TRUSTEES HARMLESS AND
FREE. FROM ANY AND. ALL DAMAGES ' AND CLAIMS ARISING UNDER OR BY
VIRTUE OF SAID 'PERMIT, IF GRANTED.
IIGNARE OF APPLICANT
.SWORN TO BEFORE ME THIS
DAY OF ✓ / 191
Et1ZASf-: ; A, LRIP DY
Notary:Pub;, . ",-1,,? of New York
No. 30-4506M
't—!,in Nassau county
/ NOTARY UBL6 C Commission expires`Mtar. 30, 19.-Z/
EXAMINED /
APPROVED "WETLANDS" PERMIT (CHAPTER 97)
APPROVED "BOAT, DOCKS , WHARVES" PERMIT (CHAPTER 32)
DISAPPROVED "WETLANDS PERMIT" (CHAPTER 97)
DISAPPROVED " BOATS ,DOCKS , WHARVES" PERMIT (CHAPTER 32)
CONDITIONS, IF ANY
EXAMINING BODY
SIGNATURE OF CHAIRMAN
COMPUTATION OF FEES
Approved 2127/85
Table of Contents
Page
1.0 Introduction 1
2.0 Purpose and Necessity 1
3.0 Location of Project 2
4 . 0 Project,Design 3
5 . 0 Construction Program 3
6.0 Key Environmental Factors 5
6. 1 Cable Fluid 5
6.2 Aquatic and Land Use Features 6
6.2. 1 Aquatic Crossings 6
6 .2.2 Land Use 7
7 . 0 Alternatives 8
7 . 1 Overhead Transmission 8
7 .2 Solid Dielectric Underground Cable 8
8 .0 Summary and Conclusion 8
9.0 Appendices
Appendix A - Route Map
Appendix B References
Appendix C - List of Agencies Receiving Project
Summary/Environmental Permits Required
1 .0 introduction
This Project Summary Report for the installation of the
Buell-Southold`underground pipe-type cable system has been
prepared in support of applications for the various
environmental permits necessary ,for the construction and
implementation of the proposed project. Because the cable
is designed to operate at 69kV (69' thousand volts) it is
not subject to regulations< stemming from Article VII of New
York State Public Service Law; those regulations have a
100kV threshold.
2.0 Purpose and Necessity
The Long Island Lighting Company is proposing to build a
69kV transmission line from Southold to East Hampton in
order to meet the existing electric load and to increase
the reliability of the electric system on the easternend
of Long Island, as this load continues to grow.
Average system load growth has been 1-2% over the last few
years. However, east end electric load growth of 7%
annually during the past five years has severely strained
the ability of the existing transmission system to supply
the area' s peak loads , particularly in the Town of East
Hampton. LILCO has compensated for this load growth to the
maximum degree possible by running expensive distillate
oil-fired peaking generation at Buell (East Hampton) and
Montauk for extended periods.
Nevertheless, during hours of heavy electric use on about
60 days during the year, a single line outage on the 69kV
supply between LILCO` s Tiana and Buell Substations could
result in line damage on the remaining circuit and a local
blackout of significant duration.
Delays in implementing improvements for the area will
compound the existing operating problems because the
experienced load growth rate is expected to continue for at
least the next few years.
Actual construction is scheduled to begin in February 1987
following completion of preliminary engineering and
procurement, which have been initiated. The projected
completion date is April 1989 in order for the system to be
available to help meet the peak summer electrical loads'.
_ 1 _
3 .0 Location of Project
The proposed underground transmission line between Buell
Substation in East Hampton and Southold Substation rear
Greenport runs generally north and south and follows state
Route 114 for most of the route (See Appendix A for Route
Maps) . The total approximate length of this cable will be
sixteen and a half miles , including three submarine '
crossings.
Beginning from Buell Substation, the cable heads northwest
on Route 114 approximately four and a half miles to the
Village of Sag Harbor. In the village, the route bypasses
the business district by heading north on Hempstead Street
and north again on Bay Street to the first submarine
crossing at Sag Harbor Cove. The distance within the
village is approximately one and a half miles . Following
the &00 foot submarine crossing east of the bridge, the
cable continues north on Route 114 , here known as Ferry
Road, through North Haven, a distance of three miles, to
the terminal for the south ferry to Shelter Island.
A 2 ,000 foot submarine crossing of Shelter Island Sound,
east of the south ferry route, brings the cable to Shelter
Island. On the island the cable' continues to follow Route
114 north to the intersection of Ferry Road and Ram Head
Road. While Route 114 turns west, the cable continues
north on Ram Island Road, also known as St, Mary' s Road,
until the third intersection where it, too, turns west,
onto Manwaring Road. The cable heads west on this road,
which changes names from Manwaring' Road to Ferry Road, to
Crescent Beach and the final submarine crossing. The
distance on Shelter Island is four and a third miles .
This third crossing, from Crescent Beach, Shelter Island
to -Conkling Point , Southold, is 3,400 feet long and
generally parallels the route of the existing, distribution
cable crossing; The cable comes ashore at Island View Lane
and immediately turns north onto Bay Shore Road which
continues onto Kerwin Boulevard, passing under the LIRR
street level crossing, to Route 25. This distance is
approximately a mile and a half. On Route 25 the cable
heads east approximately a quarter mile to the Southold
Substation just west of Chapel Lane.
2 _
4.0 Project Design
The proposed underground transmission cable between Buell
and Southold will be `1500 kmil, 69, kV standard,pipe-type
cable. On land, the system will consist of three single
conductor cables in one 6 5/8" diameter by 1/4" wall steel
pipe coated for cathodic protection. Two pipes (one a
spare) with 1 1/2" thick concrete coatings will be
installed at the submarine crossings. Spare pipe has been
included in the submarine sections of the route to expedite
restoration in the event of failure at one of the three
cable crossings On land, the pipe will be buried with
about 3 feet of cover. At the submarine crossings, the
pipe will be buried at a depth of approximately 5 feet.
Manholes will be spaced about 3 ,000 - 4 ,0`00 'apart, a
distance dictated by the reel size that can be accommodated
by available cable reel trailers and by the permissible
cable pulling tensions:
The cable' s pipe will be filled with insulating fluid at a
nominal pressure of 200 psi, maintained by a pumping plant
with a reservoir at each end of the circuit in the
substations . Leaks in such installations are extremely '
rare and the use of an environmentally benign insulating
fluid will ensure a minimal environmental impact should a
significant leak occur. (See Section 6.1 for additional
information on the characteristics of the proposed
fluids . ) LILCOts construction forces have installed
several similar transmission: lines on land and three
domestic manufacturers are capable of supplying the cable.
The submarine crossing conduits will be installed by a
marine contractor.
5. 0 Construction Program
Construction is accomplished in four sequential phases:
o Manhole and Pipe Installation (Land and Marine)
o Cable Pulling
o Splicing
o Filling Line with Insulating Fluid
Manholes and pipe installation on the land sections will
be in conformance with all permit requirements and
generally accepted installation practices . Typical
installation practice would involve such construction
equipment as backhoes , truck mounted cranes, hydraulic
cranes, front end loaders , dump and flat bodied trucks to
install the pipe in a nominal 3 foot wide by 4 foot deep
trench generally located in the shoulder area of the roads
3 -
along the route. Work will be progressed in a safe and ,
expeditious manner with regard to; traffic control and
safety to the general public and scheduled so as to avoid
the peak traffic periods associated with summer
recreation. Work period for this portion of the project is
expected to span 12 to 15 months.
Marine installation of the cable will involve
pre-excavation of a nominal foot deep trench along the
bottom of each water crossing on the route by, clamshell or
drag line bucket, operated from a 'crane mounted on a
barge. Excavated material will be sidecast for later use
as back fill over the cable. Pipe may be installed from a
lay barge or pre-staged on shore and floated or' pulled
across to the opposite shore into the prepared'trench.
After pipe installation, backfilling will be accomplished
in similar fashion to excavation. The sidecasa materials
will be used to restore the trench to the original bottom
contour. A final decision on specific methods of marine
installation will be dependent on preference of the
successful bidding contractor. Marine work will conform to
all permit requirements and all U.S. Coast Guard
regulations and will be progressed in a mannetr to minimize
imidct on boating and recreational activity ilp the
designated areas. It is estimated that the marine portion
of pipe installation will have a duration of 9 to 12
months
Cable pulling will be accomplished by positioning a reel
trailer at one manhole and setting up a winch at an
adjacent' manhole about 3 ,000 feet away. Although each pull
duration is _expected to be one day, a three month window is
allowed in the project' s schedule to cover inclement
weather and set up time for each pull (about ;30 in all) .
After the cables are pulled, splicing proceeds in each
manhole to connect adjacent cable sections. Splicing is a
continuous around-the-clock operation spanning three days
per splice. It requires a trailer outfitted with tools and
equipment to be positioned over each manhole to support the
splice crews in this operation. All splicing is expected
to be completed in 10 to 12 weeks following cable pulling.
Cable filling with insulating fluid generally requires
four or 'five days of continuous activity, mostly
concentrated at the cable terminals and several manhole
locations along the route. Both the splicing and filling
operation are planned to minimize impact on the lifestyle
of the residents and traffic conditions and to insure
general 'safety of the public.
4 -
6.0 Key Environmental Factors
6.1 Cable Insulating Fluids
The cable insulating fluid for the proposed Buell
Southold Project is specified to be either Low
Viscosity Polybutene (LVP) , or Dichevrol 100 (DO
100) . Both have undergone bioassay testing and have
been found to be environmentally safe.
LVP is a colorless , odorless liquid with a slightly
oily feel; It is relatively ;insoluble in water, has
low vapor pressure, and a quite-high flash point of
265°F. LVP is classified as a Class IIIB combustible
liquid under the Rules and Regulations of the Federal
Occupational Safety and Health Administration and by
the National Fire Protection Association,`_and is
excluded from special handling and 'storage
requirements of lower flash point combustible and
flammable liquids.
LVP has undergone extensive environmental assessment
by Federal and New York State regulatory agencies and
was approved for use in the Dunwoodie-Glenwood
underground- underwater transmission line. (See
Appendix B, References. ) Toxicity tests conducted on
several- animal species have indicated that LVP
produces no discernible effects on these organisms
when the material is ingested. LVP is biodegradable
in the aquatic environment; therefore , in the unlikely
event of a pipe leak, there would be no long term
serious degradation of environmental quality. None of
the deterious effects: of residues generally associated
with spills of petroleum products would be found, as
LVP is very similar to clean mineral oil. The absence
of animal toxicity, combined with the compound' s known
chemical identity and purity, permit the conclusion
that LVP is as safe as ordinary white mineral 'oil,
which it closely resembles. It is approved by the
Food and Drug Administration for use as a lubricant in
food processing machines.
Dichevrol 100 (DO 100) , a branched alkylbenzene, is
similar in many properties to LVP. DO 100 is a water
white, viscous liquid with an oily feel. It is
insoluble in water, has a low vapor pressure and a
somewhat higher flash point of 310°F. Like LVP, DO
100 has exhibited no animal toxicity in bioassays with
aquatic organisms. It, too, should be as safe as
ordinary white mineral oil, which it also resembles.
- 5 -
The selection of either LVP or DO 100 as the cable
fluid of choice will depend on availability and cost
when the purchase is made.
6 .2 Aquatic and Land Use Feature
6 .2 .1 Aquatic Crossings
The proposed cable route makes three submarine
crossingswhich total about 6,200 feet in
length. The southern crossing, Sag; Harbor
Cove , is an 800 foot run across Sag Harbor Cove
on the northeast side of the existing bridge.
The maximum water depth is approximately" 12 '
(MLW) The bottom is largely coarse sand with
occasional isolated pockets of finer sands
along with smaller amounts of silt and clay.
Percent composition of the three fractions
average: sand - 90% ; silt - 5% ; clay 5%. Grab
samples taken in January 1986 indicated
isolated patches of heavy concentrations of
empty shell debris. Live organisms are limited
to a few mud crabs , chitons , 'starfish, slipper
shells, near nut shells and anemones. No
concentrations of clams , oysters or scallops
were found. Tidal currents are estimated at
about 1 1/2 knots at strength of tide.
Shorelines on both sides of the crossing are
sandy beaches or rip-rapped bridge structures .
The only wetlands vegetation present is a small
stand of 'Spa_r_t- a alterniflora which is located
at the sout- Beast corneaol ttFie bridge. It will
be bypassed by the proposed crossing route.
The middle crossing, between North Haven
Peninsula and Shelter Island, is a 2,000 foot
run proposed to be located along a line
approximately 100 ' feet to the east of the South
Ferry Company' s terminals. Maximum water
depths of approximately 42 feet occupy the
center one-third of the crossing. Currents are
quite strong, running, at better than 22 knots
at strength of tide, preventing the
accumulation of fine sediments or dense
organism communities. The bottom is composed
of coarse materials whose nature required
sampling by dredge rather than by grab.
Samples showed as much as 90 `,percent of the
bottom to be stones up to 6 inches in
diameter. Smaller fractions were found in the
- 6 -
proportions: , sand - 89 .9% , silt - 7 .2% , clay
2.8% . Live organisms , found in very low
densities, were; limited to a few slipper shells
and paper spoon shells No commercial
shellfish were found. Both landfalls are across
sandy beaches with no wetland vegetation
present:
The north crossing runs 3 ,400 feet from
Crescent Beach on Shelter Island to Conkling
Point in. Southold. It follows an existing
submarine cable :crossing route which is
indicated on NOS navigation chart No. 12358 .
Maximum depths are approximately 85 feet at the
middle and southern part of the crossing,
shallowing to about 30 feet and less at the
northern end. As with the middle` crossing,
currents 'sun at better than 22 knots , and the
bottom is composed of` coarse" materials
dominated by stones (about 50%) . 'Finer
materials, where present, are in the
proportions: sand - 84.3%, silt 9.5%, clay
6.3%. The benthic community at this crossing
was a bit more diverse and populous than at the
other two, but was still limited by high
currents and hard substrate. Organisms found
in ;.greatest abundance were slipper shells, near
nut shells and mud crabs.
6. 2 .2 Land Use
The proposed transmission line willbe located
entirely underground, either within existing
roadways or along the shoulder of these roads.
There will be no visible, above ground
structures with the exception of the two oil
Bumping stations and reservoirs which will be
located entirely within the electric
substations . There are both mapped and
unmapped freshwater wetlands adjacent to some
of the roadway used as the cable route. The
location of the cable within the roadway or
shoulder will avoid any impact on these
wetlands.
- 7 -
I_.
7 .0 Alternatives
7. 1 Overhead Transmission
An overhead transmission line has been ruled out
because the Town of Shelter Island and the Village of
North Haven have ordinances which prohibit new
overhead electric transmission construction. In
addition, in response to .the Company' s inquiry, the
Towns of East Hampton and Southampton, and the Village
of Sag Harbor have informed the Company that they are
opposed to overhead construction for this line.
7 .2 Solid Dielectric Underground Cable
The Company has conducted an engineering and economic
analysis of solid dielectric vs, pipe-type cable.
That analysis showed a very small economic advantage
for the solid dielectric cable that was easily`
outweighed by the superior reliability of the
pipe-type cable. Environmentally, the construction of
the pipe-type cable involves considerably less
disturbance because of the smaller (width) trench
required for installation. In terms of operational
environmental impacts; the only difference is the
small potential for a leak of the dielectric fluid
from the pipe-type cable. This is mitigated by the
choice of insulating fluids , which are considered
"environmentally safe" on the basis of extensive
environmental 'assessment including animal toxicity
tests.
8 .0 Summary and Conclusion
In order to increase the reliability of electric service
to Long Island' s east end, the Long Island Lighting Company
proposes to construct a 69kV underground transmission line
to connect the Southold Substation on the north fork with
the Buell Substation in East Hampton on the south fork.
The 16-1/2 mile long route, which includes three submarine
crossings , follows existing roads and highways. It will be
buried along its entire length, including the submarine
crossings. The line will be a standard steel walled,
pipe-type cable filled with an insulating fluid selected
for its environmental compatibility. Construction is
proposed for the, period February 1987 to March 1989 , but
only a short length of roadway will be open at any one
time. Work will be scheduled to avoid disruption of land
and boat traffic during peak summer travel periods. 'Once
completed, the project will have no visual impact.
8 _
Potential for environmental impact during construction is
minimal because the line will be buried within existing
roadways or along their shoulders, thereby avoiding several
adjacent freshwater and tidal wetlands. Impacts at the
water crossings will likewise be minimal because of the
absence of vulnerable tidal wetlands at the crossing.
landfalls , and minimal benthic populations or commercial
shellfish along the proposed routes. New York State
Department of Environmental Conservation guidelines ;for
determining compatibility of projects with wetlands, find
that installation of underground electric utilities
involving restoration of existing ground'elevations is
generally compatible, and a (permit is required.- The nature
of this project will not substantially alter or impair
natural'conditions or functions of any tidal wetlands.
The project is fully consistent with the policies of New
York' s Coastal Zone Management Plan and proposed waterfront
revitalization plans of several local agencies. All
municipalities along the route and all regulatory agencies
having jurisdiction are being notified of the project. A
list of these agencies is included in Appendix C.
- 9 -
APPENDIX A
Route Maps
OAIMRrW.,VISIMIS OREENPDRf
?9Zd NEADOWCREST DR, SREEMPORT
YORKTOWN NE/GIITS, At Y- NAkSOR
O ADeLE A+.au6voeY
ENARZES F• armw f.INNINF PT.
Urrca./ri✓Are: eD.
_ -�� Jt!![T6C LSLAND, AI.Y. P/OIES N
Z \ ® TOWN OF,*A&rK Ind.AID _ever
$ IAI ,00 05,
NNI
nu.ro aEww. \� NNI CXatE AREA
('OWKUAlG \NZ�•'� ZOCA710N OF PRO)0054W PD/,VT ► \\ \ rJUBMIU E CONDUirS(2J
\\\'�osc ��o `C� St1ECTER
�� �a� \ CONKLIN6i ISLAND
f
MAUrleAC M/LES /It
f�p0� "� Ns" LOCATION MAP
�p� ```.r \\�r�'J from U.S.C. 6.5. CNART NQ 363
700 0 700 \
SCAL E IA!FEET
�E=T NECK
4
5AMITER
' ap. /SLAAID
as
s
IN.N.M/. t.3'
LAA1.W, E4E11.
400 0 400 2 ST6E[.C0400175 FOR ELEC,
CABLE 6 TG E S&R1Eo $,OFT
wwaoNTXL 5C4 LE /N FEET �� BE2ow NATURAL 80TTOM
40 0 40
YERTiCAL sGLE w mer_ peOF/LE
400KIA/6 EAST
APPLICATIOAI BY- PZOP0.5fD StIBMAelAYE_ CONOI17S
L OIVG ISL ANO t 161,1TW4 CO. CROSSING CHANNEL BETWEEN
A11CKSY14lE, NEW YOA?K COWLING Pj. '720MN OrSOUTNOlD
AND SyfLTER ISLAND, COUNTY
agrt OF SOFFOLK, NEW YORK
• ILo/0 cscco oar,. o t-/35-5
9NELTf? / .7r1�c7�¢
ISL.A.vo tSU D N
0
r v'
. ,i'011TN ` r.
FERRY
!{!LL{ I R LOCArtON Of `
PACROSEO
;OA/DOJTS(Zr�
{ 8
<tooD 2 io\ TYMOAL
N 'o pT
g6 ?•vw NOQTN NA YEN
4 �_ rat AlN/t/3t/L4
1Q0o 900 0 1800
0 WAUTJICAL MILES 1(Q
.9CAIL AV AFfr AXAr/aV M4P
i
�ip, AeaNu.S.C.EC,5. CYAeT'AV,563
64EASOA/
pT
NORTH NAVE" SOurH FERRY/NC.
40-FERRY RD,
SNELrER MAMD,N.Y.
PLAN O® LORRA/NE 2 ANDERSOAI
MOM AMA114W
SA6.4AR6OR,M y.
2 ST.EEt FONOurTS fO/C ELFC, - M.K.W2.3
C94LA9 TO BE 6✓R/EO S.O iT
biLOw ANTLRAL LdOTTOM -���,� ♦1,L•W. ELEV �+
Soo 0 yp0
MIORIZOMML "a AVAORT
40 0 do Y.`` . ,
YF?TICAL SCAa Av FEET '---"
- Moor rz
zoos/M` eAtsT
APPI-ICA770AI 8Y l'24POSEO SUBMARINE COMMrS
t ONG ISL AND L 14W 7711V6. CO, C QOSS11V 6 CRANNEC BFTWS CN
HICKSY144E, N46W YORK r11FL7ER /SLAND AMP NORP4
HAVEN 0 COUNTY OF SUFFOLK,
o.►�F NEW YORK
w0 42010 t/t CO DWO AO L-I36-5
N
O 3q'ATt VAA9W W"
230 usr 6s•S r1 PeNrzvsucA
P kAV& J "mow+iON&, V.V.
awAffr ac sw4p',r N
t}?fAVTY A�S[/fFOLx
' Q LOGI nU v aK
~ a15 PROpOSEO
JU6t*/L�N6
CONO/liiTS (2I
N •OG�
J46
NAN~ STAG NAROOR
QO✓t 1` `��J �\
3 0.J N- A(IrICAI. MILES Ile
po00 4 wET c �s . 40CAT/OAJ MAP
LAV p3 q/
SAG "AZ30,e
PLAN
600 goo o boo
CALL /4/FLET
,H.a..W. Z-5,
2 STBEL.GONDUATS foR FLFG,..
cga[.f To &A` Bury&o S•OET .�-
&SLOW �yA1ruR4L BOTTOM v_�_� �.
P,2 jo Egg
tooKiwy EaJr
too o 200
MORI7GNTAL SCALE AV KPJir
YfR7fcA1 4414F ,w FiET
ADPLICAT/ON 8Y P'20POSE0 XZ1,60 '/NE CONOv/TS
LONC1 1SL ANO Llq#r G CO CRO.u1N(, CHANNEL ,BEfWfF
N/CKSVIL ZE, NEW YORK NO!?TN HAVEN ANO S't4t? NQR802,
GOUNTY Of SUFFOLK,
oArs NEW YOR K •
Wo f20io liLCc DWla A0
APPENDIX B
REFERENCES
Alexander, J.E. , 1973. A Study of the Solubility of
LVP in Seawater. Prepared for theLong Island
Lighting Company. New York Ocean Science
Laboratory. Montauk, New York'
Biospherics Inc. 1984. The Acute Toxicity of
Dichevrol 100 to Rainbow Trout (Salmo
airdneri) , Prepared for Chevron Environmental
Heat Care Center, Inc. Richmond, California
Biospherics Inc. 1984 . The Acute Toxicity of
Dichevrol 100 to Sheepshead Minnow-(Cyprinodon
varie atus) . Prepared for Chevron Environmental
Heat are Center, Inc. Richmond, California
Cosden Oil and Chemical Company, 1986. Cosden
Polyvis Polybutenes, Technical Bulletin, Number
43 , Windsor, New Jersey
Food and Drug Research Laboratories , 1986 . Feeding
Studies with Polyvis - SH on Rats and Dogs .
Submitted to Cosden Oil and Chemical Company.
Maspeth, New York
Leibovitz , L, 1972. Toxicity Studies of Low
Viscosity Polybutene (LVP) in White Pekin
Ducks. Cornell University Duck Research
Laboratory. Eastport, L.I. , New York
Quirk, Lawler and Matusky Engineers , 1972 . Analysis
of Possible Toxic Effects of Low Viscosity
Polybutene (LVP) on Fundulus: heteroclitus and
Artemia Salina.
U.S. Army Engineer District, 1975. Final
Environmental Statement: Proposed Con Edison -
Long Island Lighting Company' s Power Transmission
Cable, New York, New York. (Dunwoodie -
Glenwood) .
APPENDIX C
AGENCIES RECEIVING PROJECT SUMMARY/ENVIRONIIENTAL PERMITS
EEjUIRED
U. S. Army Corps of Engineers - Permit Required
• New York State Department of Environmental
Conservation Wetlands and -Dewatering Permits
Required
• New York State Department of State - Statement of
Consistency with,Coastal Management Plan Required.
• Suffolk County Department of Health Services -
Permit required under Article 12 of Sanitary Code
(Oil 'Pumping Stations)
° Town of Southold - Wetlands Permit Required
° Town of Shelter Island - No Environmental Permit
Required
• Town of East Hampton - No Environmental Permit
Required
• Town of Southampton - No Environmental Permit
Required
• Village of North Haven - No Environmental Permit
Required
° Village of Sag Harbor - No Environmental Permit
Required