HomeMy WebLinkAbout02/2017
SOUTHOLD PLANNING BOARD
Monthly Report Summary, February, 2017
Planning Board Applications
Currently Processing
Subdivisions: 19
Site Plans: 22
New this Month
Subdivisions: 2
Site Plans: 2
Application Fees Collected: $3,327.50
Site Plan and Subdivision Application Concept Meetings: 1
Counter Visits: 38
Phone Calls: 130
Actions Taken at Public Meeting
Public Hearings: 1
Subdivision Decisions: 2
Site Plan Decisions: 4
Referrals for Comments from Other Boards
ZBA: 0 completed, 4 received
LWRP Consistency Reviews: 19
Comprehensive Plan Update:
Final revisions to the draft Land Use Chapter
Updated Introduction Chapter with newer demographics
Planning Board Monthly Report - Subdivisions
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ
/ǒƷĭŷƚŭǒĻ
Big Bing & Little Bing95.-1-7.2 CONSERVATION AC R-PENDING ВΉЊЉΉЋЉЊЎЋΉЋАΉЊА Work session
SUBDIVISION 80
discussion re: road
design & location
Hazard Subdivision103.-2-1 STANDARD R-80 PENDING БΉЊБΉЋЉЊЏЋΉЊАΉЊА Review for
SUBDIVISION
completeness
Joint Industry Board & 83.-2-17.1 RESUBDIVISION AC PENDING ЋΉЊЋΉЋЉЊЏАΉЊЊΉЊЏ Waiting on new design
(LOT LINE
McBride
MODIFICATION)
Krupski & Zachariadis 97.-8-31.2 RESUBDIVISION R-80 PENDING ЍΉБΉЋЉЊЏЎΉЋΉЊЏ Waiting on applic
(LOT LINE
revisions & ZBA
MODIFICATION)
Martz, Theodore C., Jr.104.-12-6.1 STANDARD R-40 CONDITIONAL ЍΉЋЋΉЋЉЊЎЋΉЊАΉЊА Responded to
SUBDIVISIONPRELIMINARY
applicant's requests
APPROVAL
re: drainage
SUBDIV
installation &
performance
guarantee
9ğƭƷ
ağƩźƚƓ
Philippou & Vallas31.-2-7 RESUBDIVISION R-40 PENDING ЊЋΉЊЍΉЋЉЊЎЊΉВΉЋЉЊА Set hearing for Feb.
(LOT LINE
MODIFICATION)
CźƭŷĻƩƭ
LƭƌğƓķ
Miller & Brinckerhoff8.-1-4.16 RESUBDIVISION R-120 PENDING ЊΉЊБΉЋЉЊАЋΉЊАΉЊА Reviewing for
(LOT LINE
completeness
MODIFICATION)
Monday, March 27, 2017Page 1 of 3
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ
Ridgway6.-1-3 STANDARD R-80 CONDITIONAL ЊЋΉЋЌΉЋЉЊЌЏΉЏΉЊЏ Waiting for applic to
SUBDIVISIONPRELIMINARY
submit Final Plat
APPROVAL
Applic.
SUBDIV
ağƷƷźƷǒĭƉ
Estates at Royalton113.-7-19.23 STANDARD AC CONDITIONAL ЏΉЊЊΉЋЉЊЎЋΉЋЊΉЊА Waiting for revised
SUBDIVISIONFINAL
Final Plat
APPROVAL
SUBDIV
STANDARD B CONDITIONAL ЋΉЊБΉЋЉЊЍЊΉЋЌΉЊА
Harold R. Reeve & Sons140.-1-6SEQR review for
SUBDIVISIONSKETCH
subdivision and
APPROVAL
change of zone in
SUBDIV
process.
Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL ЍΉЏΉЋЉЊЋБΉБΉЊЏ Waiting for applic to
SUBDIVISIONSKETCH
Partnershiprespond to required
APPROVAL
map changes
SUBDIV
Noone, Margaret143.-1-4.1 STANDARD B and CONDITIONAL ЊΉБΉЋЉЊЉЊЉΉЊΉЊЏ Waiting for applic to
SUBDIVISION R-40 PRELIMINARY
submit Final Plat
APPROVAL
Applic
SUBDIV
Quantuck Properties107.-10-8 CONSERVATION AC PENDING ЋΉЋЍΉЋЉЊА
SUBDIVISION
hƩźĻƓƷ
Mazzoni, 500 Soundview 13.-2-8.2 STANDARD PENDING ЌΉЊЋΉЋЉЊЍЋΉЏΉЊА Reviewed Report on
SUBDIVISION
Drive, LLCWater quality from
applicant
Orient Acres14.-2-25 STANDARD R-80 PENDING ЎΉЊАΉЋЉЊЏЏΉЏΉЊЏ Applic. incomplete
SUBDIVISION
Tuthill Conservation 17.-4-16 CONSERVATION R-80, PENDING АΉЋΉЋЉЊЍЍΉЍΉЊЏ Waiting on DEIS
SUBDIVISION R-200
Subdivision
tĻĭƚƓźĭ
Monday, March 27, 2017Page 2 of 3
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ SubmittedRecent Activity/ƚƒƒĻƓƷƭ
Beninati, Lee & Marie74.-3-15 STANDARD RO CONDITIONAL ЎΉЊЌΉЋЉЊЍЌΉЋЊΉЊЏ Waiting for requested
SUBDIVISIONSKETCH
items to be
APPROVAL
submitted.
SUBDIV
{ƚǒƷŷƚƌķ
Stanton, Phil & Jennifer64.-1-29 STANDARD R-40 CONDITIONAL ЊΉЊБΉЋЉЊЋЊЉΉЌΉЊЏ Waiting on applicant
SUBDIVISIONFINAL
to fulfill conditions.
APPROVAL
SUBDIV
STANDARD CONDITIONAL ЎΉЋЉΉЋЉЉБЍΉЍΉЊЏ
Sutton, Alexander & Tracy78.-9-54Waiting for applic to
SUBDIVISIONPRELIMINARY
submit Final Plat
APPROVAL
Applic
SUBDIV
Monday, March 27, 2017Page 3 of 3
Planning Board Monthly Report - Site Plans
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
/ǒƷĭŷƚŭǒĻ
Ackermann Agricultural Barn 102.-4-6.1 SITE PLAN AC PENDING 8/29/2016Public hearing 10/3/16 held
AGRICULTURAL
open to 11/7/16 and
extended for written
comment to 11/21/16 then
closed. PB sent ZBA a request
to interpret the proposed
use of the barn 12/2/16
Chris Mohr Lawncare Shed 96.-1-20.1 SITE PLAN LI PENDING 2/13/2017Amended application to be
Amendedreviewed for completeness
at PB's 3/13/17 work session
E. Lopez Nursery97.-3-3.1 SITE PLAN LB PENDING 6/23/2016Referral review conducted
10/24/16; NYSDOT permit
needs to be obtained; PB
required revisions to site
plan and have not been
submitted as of 3/27/17
SITE PLAN LB PENDING
East End Tick & Mosquito 97.-3-23/30/2015Revised plans reviewed by PB
Pest Control12/19/16; revisions
required
Heritage at Cutchogue 2015102.-1-33.3 SITE PLAN HD PENDING 1/2/2015Approved with 43 conditions
RESIDENTIAL
11/7/16; Conditions must be
met before the Chairman can
endorse the site plan
Monday, March 27, 2017Page 1 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Sannino Winery & Tasting 101.-1-14.4 SITE PLAN AC PENDING 8/25/2015Revised site plan has been
Roomsubmitted addressing the
two primary concerns about
potential impacts regarding
proposed building/parking
location and traffic safety.
The Planning Board has set
April 10, 2017 to re-open the
public hearing to give
adjacent property owners
and general public the
opportunity to provide
comment on the revisions to
the site plan.
Terp Retail102.-5-4 SITE PLAN HB PENDING 5/23/2016Visual impact analysis
required by PB not yet
submitted as of 3/27/17.
Threes Brewing East83.-3-4.9 SITE PLAN LI PENDING 7/29/2016SCDHS approval outstanding
and applicant needs to
provide proof of filing C&R's
as of 3/27/17
CźƭŷĻƩƭ
LƭƌğƓķ
Fox Lane Residences12.-1-1.2 SITE PLAN AHD PENDING 2/1/2016SCDHS approval outstanding
as of 3/27/17
DƩĻĻƓƦƚƩƷ
Matchbook Distillery48.-2-44.3 SITE PLAN LI PENDING 9/23/2016PB to review revised site
plan, SCDHS approval and
revised photometric plan at
3/27/17 work session
\[ğǒƩĻƌ
Monday, March 27, 2017Page 2 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Country Car Wash Additions125.-1-19.5 SITE PLAN B PENDING 6/17/2016Amended site plan
application requires special
exception and an area
variances as per the revised
notice of disapproval issued
11/16/16;
ağƷƷźƷǒĭƉ
13400 Main Road Corp.114.-11-9.6 SITE PLAN HB PENDING 11/10/2015PB conducted referral review
1/23/17 and required
revisions to the site plan.
Applicant to attend 3/27/17
work session to discuss
certain requirements with PB;
hƩźĻƓƷ
Verizon Wireless at MGH 15.-9-8.1 SITE PLAN MII PENDING 6/2/2016Public hearing held and
WIRELESS
Enterprisesclosed 9/12/16; referral
review forthcoming; ZBA
area variance required and
Special Exception by PB for a
co-location extension of 20';
tĻĭƚƓźĭ
Berry & Berry, LLC75.-5-13 SITE PLAN B PENDING 12/2/2014Public hearing held and
closed 6/1/15; referral
review conducted 7/6/15;
SCDHS approval outstanding
as of 3/27/17
{ƚǒƷŷƚƌķ
AMENDED SITE B PENDING
Lucas Ford59.-3-32.112/10/2014Applicant working on new
PLAN
design with Ford Company
after preliminary (positive)
review with ARC
Monday, March 27, 2017Page 3 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
North Fork United Methodist 63.-1-15 SITE PLAN LB PENDING 2/10/2016Application accepted as
Churchcomplete for review; public
hearing set for 4/10/17
North Fork Woodworks61.-1-15.3 SITE PLAN HB PENDING 3/9/2016Application found
incomplete at PB's 3/21/16
work session; revisions and
additional information
required and not submitted
as of 3/27/17
SITE PLAN R-80 PENDING
Polak Agricultural Barn55.-6-342/17/2017Application accepted as
complete for review;
referrals distributed and
public hearing set for 4/10/17
Purita Winery51.-3-5 SITE PLAN AC PENDING 8/2/2016Referral review conducted
1/9/17; a revised site plan
has provided all information
as required by PB and Code;
approval from SCDHS
remains outstanding as of
3/27/17
Southold Gas Station & 55.-5-2.2 SITE PLAN B PENDING 3/31/2015DEIS found inadequate for
Convenience Storepublic review on 10/24/16
and for a second time on
1/23/17; required
information (including visual
impact analysis) not
submitted as of 3/27/17
Surrey Lane Vineyard69.-5-18.1 SITE PLAN AC PENDING 8/29/2016Public hearing adjourned
12/5/16 and request sent by
PB to ZBA for code
interpretation on winery &
tasting room
Monday, March 27, 2017Page 4 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
The Enclaves63.-3-15 SITE PLAN HB PENDING 1/31/2017New site plan application
requires special exception
from ZBA; ZBA to take lead
agency for SEQR with
support help from Planning
Board/staff who would also
manage (possible) consultant
3/27/17