SOUTHOLD PLANNING BOARD
Monthly Report Summary, July, 2016
Planning Board Applications
Currently Processing
Subdivisions: 20
Site Plans: 24
New this Month
Site Plans: 2
Application Fees Collected: $1,544.00
Site Plan and Subdivision Application Concept Meetings: 1
Site Plan and Subdivision Application Pre-submission Meetings: 2
Counter Visits: 33
Actions Taken at Public Meeting
Public Hearings: 2
Site Plan Decisions: 3
Subdivision Decisions: 4
LWRP Consistency Reviews: 15
Referrals for Comments from Other Boards
SEQRA Reviews for Town Board: 1
Planning Board Monthly Report - Subdivisions
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
/ǒƷĭŷƚŭǒĻ
Big Bing & Little Bing95.-1-7.2 CONSERVATION AC R-PENDING 9/10/2015 The Board is waiting for
SUBDIVISION 80
correction to the application
as per the Planning Board
letter dated 11/2/15.
Joint Industry Board & 83.-2-17.1 RESUBDIVISION AC PENDING 2/12/2016The Planning Board reviewed
(LOT LINE
McBridethe application at their
MODIFICATION)
7/11/16 work session and
required that the applicant
meet with Planning Staff to
discuss design of the
property further.
Krupski & Zachariadis 97.-8-31.2 RESUBDIVISION R-80 PENDING 4/8/2016The Board is waiting for the
(LOT LINE
applicant to submit
MODIFICATION)
corrections to the
application. A ZBA variance is
also required to continue to
process the application.
STANDARD R-40 CONDITIONAL
Martz, Theodore C., Jr.104.-12-6.14/22/2015The Planning Board on
SUBDIVISIONPRELIMINARY
6/20/16 has requested that
APPROVAL SUBDIV
Town Engineer review the
submitted road and drainage
plan and respond with
comments to the Planning
Board.
9ğƭƷ
ağƩźƚƓ
Thursday, August 18, 2016Page 1 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Philippou & Vallas31.-2-7 RESUBDIVISION R-40 PENDING 12/14/2015Planning Staff reviewed the
(LOT LINE
application and sent a letter
MODIFICATION)
to the agent on 12/22/15
requiring that corrections be
made to the application
before it can be processed
further by the Planning
Board.
CźƭŷĻƩƭ
LƭƌğƓķ
STANDARD R-80 CONDITIONAL
Ridgway6.-1-312/23/2013 The Planning Board at their
SUBDIVISIONPRELIMINARY
6/6/16 public meeting
APPROVAL SUBDIV
granted conditional
preliminary plat approval.
ağƷƷźƷǒĭƉ
Estates at Royalton113.-7-19.23 STANDARD AC CONDITIONAL 6/11/2015The Planning Board held and
SUBDIVISIONPRELIMINARY
closed the final public
APPROVAL SUBDIV
hearing at their 8/8/16 public
meeting. The Board will
review all comments from
the hearing at their 8/22/16
work session.
Harold R. Reeve & Sons140.-1-6 STANDARD B CONDITIONAL 2/18/2014The Planning Board is
SUBDIVISIONSKETCH APPROVAL
conducting a SEQR review for
SUBDIV
both the subdivision
application and the change
of zone.
Thursday, August 18, 2016Page 2 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
James Creek Landing122.-3-1.4 STANDARD R-80, B CONDITIONAL FINAL 8/25/2005The Planning Board at their
SUBDIVISIONAPPROVAL SUBDIV
5/2/16 Public Meeting
granted Conditional Final Plat
Approval. The Board is
waiting for the applicant to
fulfill the conditions of
Conditional Final Plat
Approval.
James Neumann107.-1-1.3 STANDARD R-80 CONDITIONAL 7/9/2008Planning staff is working on
SUBDIVISIONPRELIMINARY
addressing the applicant's
APPROVAL SUBDIV
concerns regarding the draft
drainage easement.
Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL 4/6/2012The Planning Board reviewed
SUBDIVISIONSKETCH APPROVAL
Partnershipthe application at their
SUBDIV
8/8/16 work session the
applicant requested
additional time to evaluate
and research requested
design changes.
STANDARD B and CONDITIONAL
Noone, Margaret143.-1-4.11/8/2010The Planning Board at their
SUBDIVISION R-40 PRELIMINARY
4/4/16 public meeting
APPROVAL SUBDIV
granted Conditional
Preliminary Plat Approval.
The Board is waiting for the
applicant to submit a Final
Plat application.
hƩźĻƓƷ
Thursday, August 18, 2016Page 3 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Mazzoni, 500 Soundview 13.-2-8.2 STANDARD CONDITIONAL 3/12/2014The agent has requested on
SUBDIVISIONSKETCH APPROVAL
Drive, LLC2/1/16 that the Planning
SUBDIV
Board stop processing the
application until further
notice, as the agent would
like to submit addition
information pertaining to
environmental constraints on
the property.
STANDARD R-80 PENDING
Orient Acres14.-2-255/17/2016The Planning Board reviewed
SUBDIVISION
the Sketch Plan Application
at their 6/6/16 work session
and found the application
incomplete with items to be
submitted.
The Orchards27.-1-3 STANDARD R-80 CONDITIONAL 7/1/2013The Planning Board at their
SUBDIVISIONSKETCH APPROVAL
7/6/15 Public Meeting issued
SUBDIV
a Positive Declaration. The
applicant is working on the
Environmental Impact
Statement.
CONSERVATION R-80, PENDING
Tuthill Conservation 17.-4-167/2/2014The Planning Board at their
SUBDIVISION R-200
Subdivision4/4/16 work session
reviewed the submitted
Environmental Impact
Statement (EIS) for adequacy
and found the EIS
inadequate for public
tĻĭƚƓźĭ
STANDARD RO CONDITIONAL
Beninati, Lee & Marie74.-3-155/13/2014The Planning Board reviewed
SUBDIVISIONSKETCH APPROVAL
the application at the
SUBDIV
3/21/16 work session and
requested items to be
submitted.
Thursday, August 18, 2016Page 4 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻ ƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Robertson and Johnson67.-3-10 RESUBDIVISION R-40 PENDING 11/7/2012The Planning Board at their
(LOT LINE
3/21/16 work session
MODIFICATION)
required that the applicant
submit a draft C&R template
for Board review.
{ƚǒƷŷƚƌķ
Stanton, Phil & Jennifer64.-1-29 STANDARD R-40 CONDITIONAL 1/18/2012The Planning Board at their
SUBDIVISIONPRELIMINARY
5/2/16 work session agreed
APPROVAL SUBDIV
to waive the final plat public
hearing. The applicant must
submit revised C&Rs for
Board review and approval.
Sutton, Alexander & Tracy78.-9-54 STANDARD CONDITIONAL 5/20/2008The Planning Board at their
SUBDIVISIONPRELIMINARY
4/4/16 public meeting
APPROVAL SUBDIV
granted Conditional
Preliminary Plat Approval.
The Board is waiting for the
applicant to submit a Final
Plat application.
Thursday, August 18, 2016Page 5 of 5
Planning Board Monthly Report - Site Plans
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
/ǒƷĭŷƚŭǒĻ
Commercial Solar Energy 96.-1-17.5 SITE PLAN LI PENDING 8/5/2015Public hearing closed
Production System at 11/2/15; referral review
Southold Town Landfillconducted on 11/16/15;
revisions and additional
information required and
outstanding as of 7/20/16
Cutchogue Business Center 83.-3-4.6 AMENDED SITE LI PENDING 2/15/2013PB reviewed the revised site
PLAN
Site Planplan at their 6/16/14 work
session, all site plan elements
have been met. Site plan
approval is contingent on the
concurrent subdivision.
E. Lopez Nursery97.-3-3.1 SITE PLAN LB PENDING 6/23/2016Accepted as complete for
review at PB's 8/22/16 work
session; public hearing to be
set for 10/3/16
SITE PLAN LB PENDING
East End Tick & Mosquito 97.-3-23/30/2015Referral review continued
Pest Control8/8/16 regarding emergency
access concerns by the Fire
Marshall to rear of property
(less than 15'); applicant to
pursue alternatives in order
to provide at least 15'
Heritage at Cutchogue 2015102.-1-33.3 SITE PLAN HD PENDING 1/2/2015Working on completion of
RESIDENTIAL
Final Environmental Impact
Statement as of 8/17/16
SITE PLAN AC PENDING
McCall Wine Production 109.-1-389/23/2015Revised site plan to be
Facilityreviewed at PB's 8/22/16
work session
Thursday, August 18, 2016Page 1 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
N & L Properties, LP73.-2-4 AMENDED SITE AC R-PENDING 10/27/2014Waiting on related
PLAN 80
subdivision (The Vines)
Sannino Winery & Tasting 101.-1-14.4 SITE PLAN AC PENDING 8/25/2015Application found
Roomincomplete; revised materials
not submitted as of 8/17/16
Terp Retail102.-5-4 SITE PLAN HB PENDING 5/23/2016public hearing held and
closed 8/8/16; ARC meeting
to review application set for
8/18/16
SITE PLAN LI PENDING
Threes Brewing East83.-3-4.67/29/2016Accepted as complete for
review at PB's 8/8/16 work
session; public hearing set
for 9/12/16
CźƭŷĻƩƭ
LƭƌğƓķ
Fishers Island Club Additions4.-6-9 SITE PLAN R-120 PENDING 5/2/2016Referral review conducted
8/8/16; revisions to site plan
required; SCDHS approval
outstanding
Fox Lane Residences12.-1-1.2 SITE PLAN AHD PENDING 2/1/2016Application was found
complete for review; public
hearing held and closed
7/11/16; applicant working
on revised design to
decrease size of buildings
\[ğǒƩĻƌ
Country Car Wash Additions125.-1-19.5 SITE PLAN B PENDING 6/17/2016Accepted as complete for
review at PB's 8/8/16 work
session; public hearing set
for 9/12/16
ağƷƷźƷǒĭƉ
Thursday, August 18, 2016Page 2 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
13400 Main Road Corp.114.-11-9.6 SITE PLAN HB PENDING 11/10/2015The application was found
incomplete for review at the
PB's 12/7/15 work session;
revised site plan required,
not submitted as of 8/17/16
Hudson City Amended122.-3-17.1 AMENDED SITE R-40 PENDING 7/7/2016Amended site plan
PLAN
application accepted as
complete for review 8/22/16;
public hearing to be set for
10/3/16
SITE PLAN HB PENDING
Olde Colonial Place, LLC140.-2-212/5/2015Referral conducted at PB
work session 10/19/15; Staff
met with applicant on
1/12/16 to discuss and
explain outstanding
requirements; revised site
plans submitted 8/16/16; to
be reviewed
hƩźĻƓƷ
SITE PLAN MII PENDING
Verizon Wireless at MGH 15.-9-8.16/2/2016Public hearing set for 8/8/16;
WIRELESS
EnterprisesZBA area variance required
and Special Exception by PB
for a co-location extension of
20'
tĻĭƚƓźĭ
Berry & Berry, LLC75.-5-13 SITE PLAN B PENDING 12/2/2014Public hearing held and
closed 6/1/15; referral
review conducted 7/6/15;
SCDHS approval outstanding
as of 8/17/16
{ƚǒƷŷƚƌķ
Thursday, August 18, 2016Page 3 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
Filipkowski Air, Inc.59.-10-5 SITE PLAN LB PENDING 4/15/2014Revised site plan reviewed by
ZBA and PB (preliminary);
special exception and
multiple area variances
required for the proposed
project; applicant met with
PB staff to discuss alternative
options instead of 34'x100'
building on this severely
nonconforming lot; applicant
to attempt a revised site plan
to include a smaller building
and more landscaping;
applicant to stake building on
site (not completed as of
8/17/16)
Lucas Ford59.-3-32.1 AMENDED SITE B PENDING 12/10/2014Public hearing held and
PLAN
closed 5/4/15; referral
review conducted 6/15/15
and PB required revisions to
the site plan, in addition to
requirements listed in PB
letter dated 5/7/15; revised
site plan not submitted as of
8/17/16 (applicant just hired
new architect and is working
on new building design to
meet ARC criteria)
North Fork United Methodist 63.-1-15 SITE PLAN LB PENDING 2/10/2016Application found
Churchincomplete for review
3/21/16; revised application
not submitted as of 8/17/16
Thursday, August 18, 2016Page 4 of 5
IğƒƌĻƷtƩƚƆĻĭƷ bğƒĻğǣ ağƦ ϔǤƦĻƚƓĻ{ƷğƷǒƭ{ǒĬƒźƷƷĻķbĻǣƷ {ƷĻƦƭͲ /ƚƒƒĻƓƷƭ
North Fork Woodworks61.-1-15.3 SITE PLAN HB PENDING 3/9/2016Application found
incomplete at PB's 3/21/16
work session; revisions and
additional information
required and not submitted
as of 8/17/16
Purita Winery51.-3-5 SITE PLAN AC PENDING 8/2/2016New site plan application to
be reviewed for
completeness at 9/12/16
work session
SITE PLAN B PENDING
Southold Gas Station & 55.-5-2.23/31/2015Public hearing held and
Convenience Storeadjourned 8/3/15 until
completion of SEQR review
with the aid of AKRF and
traffic impacts; Positive
Declaration issued by PB at
11/2/15 public meeting; DEIS
submitted by applicant
7/14/16 and found in need of
revision and additional
information at PB's 8/8/16
work session
Thursday, August 18, 2016Page 5 of 5