Attached is a summary of use of material from the 17 -acre parcel. As discussed, after use of
sand from the 17 -acre parcel, approximately 40,000 cy of the remaining 80,000 cy of stockpiled
sand in the Borrow Pit will be required to complete the landfill cap.
TFM/tam
Attachment
1314/TFM02LTR. do c-06 (RO 1)
SUMMARY OF USE OF 17 -ACRE MATERIAL
As of January 2002
H2M estimate of sand and stone on 17 -acre parcel 160,000 cy
Material initially screened at $2.50/cy based on volume of screened sand
(20,000 sand, 2,500 gravel and 2,500 stone - cost 25,000*
= 20,000 x $2.50 = $50,000 - sand used for gas venting
layer (GVL) (17,000 cy) on western portion of landfill
and Town Highway Department (3,000 cy)
i.s:),Uuu
Contour grading material and 6" final subbase used to date on western portion of
landfill 30,000
105,000
Contour grading material and 6" final subbase to complete western portion
of landfill 3,000
102,000
GVL to complete western portion of landfill (8,000 cy*) 10,000
92,000
Barrier protection layer (BPL) for western portion of landfill (28,000 cy*) 35,000
Needed from Borrow Pit stockpiled material to complete cap 40,000
*Screened sand
0 1314/1'0109205 (R05 )
D /,UUU
Waste Excavation Area #1 backfill
2,000
55,000
Waste Excavation Area 92 backfill
3,000
52,000
Waste Excavation Area #3 backfill
2,000
50,000
Waste Excavation Area #4 backfill
500
49,000
Contour grading material and 6" final subbase on eastern portion of landfill
17,000
32,000
Backfill Recharge Basin #4
12,000
Remaining unscreened material
20,000
= Remaining screened sand
16,000
GVL for eastern portion of the landfill (28,000 cy)
(28,000)
12,000
BPL for eastern portion of the landfill (28,000 cy)
(28,000)
Needed from Borrow Pit stockpiled material to complete cap 40,000
*Screened sand
0 1314/1'0109205 (R05 )
`-r
Dvirka
d!
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-3649890 ■ 718-460-3634 ■ Fax: 5.16-364-9045
e-mail: db-eng@worldnet.att.net
Prineipala January 25, 2002
Nicholas J. Bartilucci, P.E.
President
Henry J. Chlupsa, P.E.
Ese hw Vice President
Thomas F. Maher, P.E.
Vice President
Anthony J. Cava, P.E.
Anthony
Robert T. Burns, P.E.
Vice President
Regional Solid and Hazardous Materials Engineer
Richard M. Walka
Vice President
New York State Department of
Steven A. Fangma"", P. E.
Vice President
Environmental Conservation - Region 1
SUNY - Building 40
Senior Aaaodatea
Stony Brook, NY 11790-2356
Anthony 0. Conetta, P.E.
Dennis F. Koehler, P.E.
Re: Southold Landfill Closure
Joseph H. Marturano
Kenneth J. Pritchard, P.E. D&B 1314
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E. Dear Mr. Cava:
Aaaoalatea As a follow-up to my letter of October 15, 2001, which provided a conceptual
Garrett M. Byrnes, P.E. plan for a new drainage system along the eastern boundary of the landfill,
Rudolph F. Cannavale enclosed are design drawings for review and approval.
Joseph A. Fiorafiso, P.E.
David S. Glass, P.E. The main change from the conceptual plan is that drainage pipe will no longer run
Gould, Gerald CPG
WilD. n, P.E. through waste to discharge to Recharge Basin #3, but will be outside the limits of
liamMichael Neuberger, P.E. waste'
Richard P. Russell, P.E.
Charles J. Wachsmuth, P.E. We are in the process of preparing the details for the catch basins, manholes and
Kenneth P. Wenz, Jr., CPG head wall, and redesign of Recharge Basin #3 to accommodate additional flow.
These drawings will be provided to you when they are complete. The catch
basins will be waterproofed since they are over (Catch Basin #1) and adjacent to
(Catch Basin #2) waste.
Since we would like to install this drainage system as soon as possible, we would
appreciate your comments/approval by mid-February.
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
r.
Dvirka and Bartilucci
CONSULTING ENGINEERS
Anthony J. Cava, P.E. Page Two
Regional Solid and Hazardous Materials Engineer
New York State Department of Environmental Conservation
January 25, 2002
If you have any questions or require additional information, please do not hesitate to call me at
(516) 364-9890.
Very truly yours,
Thomas F. Maher
Vice President
TFM/tam
Enclosures
cc: Robert Phaneuf, NYSDEC
Igor Sikiric, NYSDEC
James Bunchuck, Town of Southold
Chris Morris, D&B
Peter Sutherland, TEC
0131VITNI02MR.doc-28
i
r-
.�l
C
50
40
30
20
10
I DATUM ELEV
0.00 0+00
1+00
2+00
3+00 4+00 5+00 6+00 7+00
DRAINAGE PROFILES
HW1 TO CB2
SCALES: HORIZ: 1 "=40'
VERT: 1"=4'
8+00
9+00
10+00
11+00
12+00
50
�o
30 6
20 5
10 40
DATUM ELEV
30.00 0+00
L=30'
S=1.00%
DIA. CHDPE
DRAINAGE PROFILES
C61 TO MI -15
SCALES: HORIZ: 1"=40'
VERT: 1"=4'
PROJECT NO. DRAWING NO.
N0. DATE REVISION INT. TOWN OF SOUTHOLD
UNAUTHORIZED ALTERATION OR ADDITION
TO THIS DOCUMENT IS A VIOLATION OF SUFFOLK COUNTY, NEW YORK 1314
a SECTION 7209 OF THE NEW YORK STATE
EDUCATION LAW. SOUTHOLD LANDFILL CLOSURE DATE:
DRAINAGE PROFILES DECEMBER 2001
PROJECT ENGINEER: DRAWN BY:
T.F.M. J.E.Z. DVIRKA AND eARTiLUCCi GENERAL CONSTRUCTION SCALE: L
z DESIGNED BY: CHECKED BY: CONSULTING ENGINEERS
AS NOTED
E.P. E.P. A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
V)
V3
0
C�n
Ld
00
6
�O
�N
04
O
M
Lrj 00tn
O0
OQ�
Lr) OOrM
MO�
C4C)n
.0�
JcpF-
} 04 AZO
CC)
rr�cZ0
+C6ZO
0)
+ozo (—f)O�Z
OM
Zp
-N
04
NWZ
�q—
.-
"'—
.-�--
_<
�(n�--
_��>>
ZZ �(nQ'--
MQ
ZZ 21—
�Np_ZZ
�Q�>>
SF--
�V)
Lr)Q
SF--
�0EK
J» tOQmi>
=F--
KZ �cr)E
NQJ>
mF-
Z (-)
1+00
2+00
3+00 4+00 5+00 6+00 7+00
DRAINAGE PROFILES
HW1 TO CB2
SCALES: HORIZ: 1 "=40'
VERT: 1"=4'
8+00
9+00
10+00
11+00
12+00
50
�o
30 6
20 5
10 40
DATUM ELEV
30.00 0+00
L=30'
S=1.00%
DIA. CHDPE
DRAINAGE PROFILES
C61 TO MI -15
SCALES: HORIZ: 1"=40'
VERT: 1"=4'
PROJECT NO. DRAWING NO.
N0. DATE REVISION INT. TOWN OF SOUTHOLD
UNAUTHORIZED ALTERATION OR ADDITION
TO THIS DOCUMENT IS A VIOLATION OF SUFFOLK COUNTY, NEW YORK 1314
a SECTION 7209 OF THE NEW YORK STATE
EDUCATION LAW. SOUTHOLD LANDFILL CLOSURE DATE:
DRAINAGE PROFILES DECEMBER 2001
PROJECT ENGINEER: DRAWN BY:
T.F.M. J.E.Z. DVIRKA AND eARTiLUCCi GENERAL CONSTRUCTION SCALE: L
z DESIGNED BY: CHECKED BY: CONSULTING ENGINEERS
AS NOTED
E.P. E.P. A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
I
I
I
36" DIA. CHD
E
L-162'
S=1.00
"CHDPE
L-158' S=1
00 •
L=g
'7::r
�736"
L=27'
DIA. CH
PE
5=1.0
%
24" DIA.
S=1.00%
CHDPE
36" DIA. CH
PE
5=1.00
L=400'
36 DIA.
CHDPE
36" DIA. CHDPE
L= 215'
5=1.00
O
O
CV
00
G,ZO
+_
0 0
N Z
0,
5�
,
I
I
1+00
2+00
3+00 4+00 5+00 6+00 7+00
DRAINAGE PROFILES
HW1 TO CB2
SCALES: HORIZ: 1 "=40'
VERT: 1"=4'
8+00
9+00
10+00
11+00
12+00
50
�o
30 6
20 5
10 40
DATUM ELEV
30.00 0+00
L=30'
S=1.00%
DIA. CHDPE
DRAINAGE PROFILES
C61 TO MI -15
SCALES: HORIZ: 1"=40'
VERT: 1"=4'
PROJECT NO. DRAWING NO.
N0. DATE REVISION INT. TOWN OF SOUTHOLD
UNAUTHORIZED ALTERATION OR ADDITION
TO THIS DOCUMENT IS A VIOLATION OF SUFFOLK COUNTY, NEW YORK 1314
a SECTION 7209 OF THE NEW YORK STATE
EDUCATION LAW. SOUTHOLD LANDFILL CLOSURE DATE:
DRAINAGE PROFILES DECEMBER 2001
PROJECT ENGINEER: DRAWN BY:
T.F.M. J.E.Z. DVIRKA AND eARTiLUCCi GENERAL CONSTRUCTION SCALE: L
z DESIGNED BY: CHECKED BY: CONSULTING ENGINEERS
AS NOTED
E.P. E.P. A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvi rka
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 - 718-460-3634 • Fax: 516-364-9045
e-mail db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucci, P E
President
Henry J. Chlupsa. P.E.
Executive Vice President
Thomas F Maher. P.E.
Vice President
Rbben T. Burns, P.E.
Vice President
Richard M. Walka
Vice President
Steven A. Fangmann, P. E.
Vice President
Senior Associates
Anthony 0. Conetta. P.E.
Dennis F. Koehler. P.E.
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
Associates
Garrett M. Byrnes, P.E.
Rudolph F. Cannavale
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
Gerald Gould, CPG
William D. Merklin, P.E.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. wachsmuth, P.E.
Kenneth P. Wenz, Jr., CPG
January 25, 2002
Mr. Robert G. Terry
Terry Contracting & Materials, Inc.
840 West Main Street
Riverhead, NY 11901
Re: Southold Landfill Closure
D&B No. 1314
Dear Mr. Terry:
We have reviewed your letter dated January 24, 2002, requesting that the
geocomposite maximum exposure period be extended from the contract required
period of 14 days to 30 days based on the recommendation of the manufacturer
(Engineered Synthetic Products, Inc.).
Although the' manufacturer's letter refers to no "noticeable" degradation, to
confirm: this -=we need to review the manufacturer's data on degradation of
properties with time.
Also, as discussed, if we find the extension of time acceptable, we will require a
statement from both the manufacturer and Terry Contracting & Materials, that the
increased' exposure period will not affect the warrantee of the material or the
overall closure project.
If you have any questions, please do not hesitate to call me. -
TFM/tam
cc: J.. Bunchuck"
I.-Sikiric
C. Morris . P. Sutherland
'01314lrFM02LTR.doc-27 -
V 1y yo ,
Thomas F. Maher, P.E.
Vice President
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
PDD 00 02 12.15 PROM. ID.:10004007n PAGO 2"T
DV i rka
and
0 Bartilucci
cnrv.wr-u..TlrJo rtuTvir-r nn
330 Crossways Park Drive, Woodbury, New York,. 11797-2015
516-364-9890 - 718.460-3634 - Fax; 516-364-9045
e-mail: db eng@worldnet.alt.net
Ffln"jo-Als
NrchoWs J. Gon;luccl, P E
'
Hatay J. Chl*!:4 P E.
Thomas F. Mahw. P F
ROW T oome, PF
Richard M 1M *4
816va(,A Fangmann, RE
James Bunchuck
niwAaµQcialu
Solid Waste Coordinator
Anrhony o. Comm). P E
Town Southold
Nrois F Koohlor, PE
of
JOsoo H (Aun rano
Town Hatl
Kennoth J Pnrchnrd, P.E.
lheoloroS Pyllar Jr.
P.O. Box 1 179
53095 Main Road
RudolpnF. Cann)valo
Southold, NY 11971
JosaphA. Floralizo PC
oawrl s Gia:.;; P E.
WdLam 0 MoMlin, PE
Re: Southold Landfill
M cnael Nooboraor, P E
Mori M Vedh, a E
D&B No. 1314 (67)
Charles J. Nbchsmulh F E
Dear Mr, Bunchuck:
January 24, 2002
Please find enclosed an invoice in the amount of $88,838.84 for our services for the
period commencing December 1, 2001 through December 28, 2001. This invoice
includes the following:
Task h3 - Construction Observation
1. Provide full-time construction inspection services.
2 Coordinate, attend and record weekly progress meetings.
3. Review and comment on contractor's submittals.
4. Review contractor's progress and schedules.
5, Review application for payment.
6. Review and evaluate contractor's proposal for changes to design,
7, Obtain NYSDEC approval for design changes.
8, Prepare change orders.
A DIVISION OF WILLIAM F COSLIUCH ASSOCIATES. P.C.
®vi rka
and
Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 • 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucca, P.E.
President
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F. Maher. P.E.
January 23, 2002
Vice President
Robert T. Burns. P.E.
Y'e President
Mr. Robert O. Terry.
Richard M. Walka
Vice President
Terry Contracting & Materials, Inc.
Steven Fangmann, P.E.
Yx:e Resident
i
840 West Main Street
Riverhead, NY 11901
Senior Associates
Anthony O. Conaria, P.E.
Re: Southold Landfill Closure
Dennis F. Koehler. P.E.
D&B No. 1314
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Dear Mr. Terry:
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
This is in response to your letter dated
January 21, 2002, requesting a time
Associates
extension for work performed in Waste Excavation Areas 2 and 3. Please be
Garrett M. Byrnes, P.E.
aware that this time extension previously was provided to you as part of Change
Rudolph F. Cannavale
Order No. 4, which was fully executed on November 8, 2001.
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
Ve/ry^d truly yours,
Gerald Gould, CPG
G
William D. Merklin, P.E.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. Wachsmuth, P.E.
Thomas F. Maher, P.E.
Kenneth P. Wenz, Jr., CPG
Vice President
TFM/tam
cc: J. Bunchuck
I. Sikiric
C. Morris
01314/rFM02LTR.doc-24
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvi rka
and
O Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 - 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucci, P.E.
Resident
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F. Maher, P.E. January 23, 2002
Vwe Resident
Robert T. Bums, P.E.
Vice Resident
Rwalks• Robert G. Terry
Richard M.
Vw President Terry Contracting & Materials; Inc.
Steven A. Fangmann, P. E.
Ywe President 840 West Main Street
Riverhead, NY 11901
Senior Associates
Anthony O. Conetta, P.E.
Re: Southold Landfill Closure
Dennis F. Koehler, P.E.
Joseph H. Marturano D&B No. 1314
Kenneth J. Pritchard, P. E.
Theodore S. Pytlar, Jr. Dear Mr. Terry:
Brian M. Veith, P.E.
As discussed, please provide a cost estimate for testing of the 17 -acre material for
Associates use on the landfill. This cost estimate should provide the type of test, unit price,
Garrett M. Byrnes, P.E. estimated quantity and total costs. As also discussed, please provide this cost
Rudolph F. Cannavale estimate to me at the January 24, 2002, Progress Meeting.
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
GVery truly yours,
Gerald Gould, CPG
William D. Merklin, RE.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. Mchsmuth, P.E. Thomas F. Maher, P.E.
Kenneth P. wenz, Jr., CPG Vice President
TFM/tam
cc: J. Bunchuck
I. Sikiric
C. Morris
01314/PFM02LTR.doc-21
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvi rka
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 - Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucci, P E
President
Henry J. Chlupsa. P.E.
Execuh� Vice President
Thomas F. Maher. P.E.
Vice Resident
RobertT Burns, P. E.
Vice Resident
Richard M. M-lka
Vice President
Steven A. Fangmann, P. E.
bice Resident
Senior Associates
Anthony 0. Conetta, P.E.
Dennis F. Koehler. P.E.
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
Associates
Garrett M. Byrnes, P.E.
Rudolph F. Cannavale
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
Gerald Gould, CPG
William D. Merklin, P.E.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. Wachsmuth, P.E.
Kenneth P. Wenz, Jr., CPG
January 22, 2002
Mr. Robert G. Terry
Terry Contracting & Materials, Inc.
840 West Main Street
Riverhead, NY. 11901
Re: Southold Landfill Closure
D&B No. 1314
Dear Mr. Terry:
At the January 17, 2002, meeting, in reviewing costs for compost facility
construction, you indicated that approximately 110,000 cy of sand is to be
screened at $3.65/cy.
As stated 'iri �rry letter to you dated December 31, 2001, unscreened sand shall be
used as final 6 -inch subgrade layer on the eastern portion of the landfill. You are
responsible for ensuring that 20,000 cubic yards of unscreened sand remains from
development of the 17 -acre parcel unless directed otherwise by the Town. There
shall be no payment for screening of sand which results in less than 20,000 cubic
yards of unscreened sand remaining on the 17 -acre parcel.
If you have any questions, please call me.
Very truly yours,
J
Thomas F. Maher, P.E.
Vice President
TFM/tam ;
Cc: J. Bunchuck:.
C. Morris
01314/TFM02LTR.doc-16(R01)
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
3
Dvirka
and
Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 - Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
January 22, 2002
Principals
Nicholas J. Bartilucci, RE
President
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F. Maher, P.E.
Vice President
Robert T. Burns, P. E.
Vice President
Richard M. Walka
Vice President
James Bunchuck
Solid Waste Coordinator
Town of Southold
53095 Main Road
Southold, NY 11971
Steven A. Fangmann, P. E.
Vice President
Re: Southold Landfill Closure and
Senior Associates Compost Facility Construction
Anthony o. Conetta, P.E. D&B No. 1314
Dennis F. Koehler, P.E.
Joseph H. Marturano
Kenneth J. Pritchard, P.E. Dear Mr. Bunchuck:
Theodore §. Pytlar, Jr.
Brian M. veith, P.E. Based on comments received at the January 17, 2002, Progress Meeting on my
analysis of landfill closure savings and additional costs, and compost facility
Associates construction costs, I have revised the cost analysis, which is enclosed with this
Garrett M. Byrnes, P.E. letter. Please review the enclosure and provide me with any additional comments
Rudolph F Cannavale at the January 24 Progress Meeting, in particular as it relates to allocation of costs
Joseph A. Fioraliso, P.E.
to either the closure or compost facility project.
David S. Glass, P.E.
Gerald Gould, CPG ,
William D. Gould,
C n, P, E. These are a few items on which I need clarification:
Michael Neuberger, P.E. 1
Richard P. Russell, P.E. 1. Should removal/hauling of unscreened sand from the 17 -acre parcel
Charles J. Wachsmuth, P.E. and placement at the landfill as contour grading/subbase material
Kenneth P. Wenz, Jr., CPG ($3/cy) be charged to the closure or compost project?
2. Should removal/hauling of screened sand from the 17 -acre parcel and
placement at the landfill as gas venting and barrier protection material
($3/cy) be charged to the closure or compost project?
3. Should the screening of sand from the 17 -acre parcel ($2.50/cy and
$3.65 cy) be charged to the closure or compost project?
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvirka and Bartilucci
CONSULTING ENGINEERS
James Bunchuck Page Two
Solid Waste Coordinator
Town of Southold
January 22, 2002
4. Should the testing of the screened and unscreened sand from the 17 -acre parcel be
charged to the closure or compost project?
By copy of this letter, I am requesting that John Romanelli and Bob Terry also review and
provide comments on this letter and the enclosures, including review of the quantities by Bob
Terry.
Ve ruly your -sem
Thomas F. Maher
Vice President
TFM/tam
Enclosure
cc/encl: John Romanelli
Bob Terry
0 13141FFM02LTR.doc-18
SOUTHOLD LANDFILL CLOSURE
SAVINGS/ADDITIONAL COST ANALYSIS
AS OF JANUARY 15, 2002
SAVINGS
Item No. Description Unit Price Estimated Actual Savings
3 Reduction in clearing and $1,200/acre 50 acres 12 acres $45,600
grubbing.
7 Elimination of Geotextile $2/sy 166,000 sy 0 $332,000
Type I between final 6"
subgrade and gas venting layer
30 Elimination of sand pit $3/cy 73,000 cy 0 $219,000
regrading
21 Elimination of southwest $8.75/sy 1,030 sy $9,000
maintenance road
13B Elimination of contingency $13.80/cy 18,000 cy 0 $248,400
off-site topsoil
13A
Manufacture of additional on-
$7/cy
18,000 cy
0
(126,000)
site vegetative growth medium
0
$122,400
22
Elimination of asphalt for a
$42.50/sy
3,400 sy
0
$144,500
portion of Main Access Road
1,020 ft. x 30 ft. = 30,600 sf
9
21
Replacement with 12"
$8.75/sy
3,400 sy
0
29,750)
recycled concrete aggregate
0
$114,800
Elimination of waterproofing
manholes along southwestern
drainage system
$1,700
26
Reduction of depth of
southwestern drainage system
19A
Elimination of fencing along
$18.75 If
1,2601f
$23,600
western boundary
0 1314/T0115202(ROS)
SOUTHOLD LANDFILL CLOSURE
SAVINGS/ADDITIONAL COST ANALYSIS
AS OF JANUARY 15, 2002
ADDITIONAL COSTS
Item No.
Description
Unit Price
Estimated
Actual
Cost
32
Test pit excavation to
$1,200/day
0
9 days
$10,800
determine limits of waste
33
Placement of waste after
$25/ton
0
2,575 tons
$64,375
baseline topographic survey
(10,000 cy)
5D
Excavation of waste from
$6.78/cy*
0
7,138 cy*
$48,396
Area 2
5E
Excavation of waste from
$6.78/cy*
0
6,911 cy*
$46,857
Area 3
10
Additional gas vents due to
$1,184/vent
39 vents
51 vents
$14,200
placement of loam on west
side and test vents on east
side
(Charge
Spreading of Greenport
$21,000 LS
8,400 cy
$21,000
to DOT?)
Pond material
5A
Additional excavation of
$6.78/cy*
2,000 cy
2,010 cy*
$68
waste from area 1
5C
Pull back and backfilling of
$3/cy
0
3,000 cy
$9,000
waste in Waste Excavation
Area 2
Excavation of waste from
$6.78/cy*
493 cy
$3,313
Area 4
(Charge to
Compost
Facility?) Testing of 17 -acre soil
3 Pull back and relandfilling of $5/cy 0 395 cy $1,975
waste in Waste Excavation
Area 3
0 1314/T0115202(R05)
A
ADDITIONAL COSTS (continued)
Item No. Description Unit Price Estimated Actual Cost
6 Additional contour grading $3/cy 36,000 cy —80,000 cy $132,000
material
11 Additional geocomposite $4.20/cy 39,000 sy 59,000 sy $84,000
28 Modified water supply well
New drainage system on east
side, including enlarged
Recharge Basin 3
6 Backfilling of Recharge $3/cy 0 12,300 cy $36,900
Basin 4
*In-place
01314/T0115202(R05)
COMPOST FACILITY CONSTRUCTION
Description
Clearing and grubbing
Windrowing of topsoil and loam
Removal and stockpiling of topsoil in borrow
pit
Removal and placement of topsoil on landfill
Removal and placement of loam on landfill
Removal and placement of loam in borrow pit
Excavation and screening of initial 25,000 cy
of sand
Excavation and screening of remaining sand
? Removal and placement of unscreened
sand on landfill as contour grading
material and 6" subbase on west side
? Removal and placement of screened sand
on landfill as gas venting layer and
barrier protection layer
Temporary access road to 17 -acre parcel
Relocate temporary access road
Permanent access road to 17 -acre parcel
Widening of the northwest road from 17 -acre
parcel to the borrow pit
Modification to southwest drainage system*
Additional guide rail*
01314/f0115202(R05)
Unit Price
Ouanti
Cost
$1,200/acre
17 acres
$20,400
$2/cy
32,565 cy
$65,130
$5/cy
12,877 cy
$64,385
$3/cy
4,321 cy
$12,963
$3/cy
42,833 cy
$128,499
$3/cy
50,523 cy
$151,569
$2.50/cy
20,000 cy
$50,000
$3.65 60,000 cy $219,000
$3/cy —53,000 cy —$159,000
$3/cy —60,000 —$180,000
$36,250 LS 1 $36,250
$42.50/sy 2,270 sy $96,500
$8.75/sy 680 sy $5,950
Description
Relocation of brush*
Temporary 1 -acre pad*
Sound barrier and vegetation along permanent
access road*
*To be determined
0 13141 0115202(805)
Unit Price Quantily Cost
Dvi rka
d!
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
January 22, 2002
Principals
Nicholas J. Bartilucci, RE
President
Henry J. Chlupsa, P.E.
James Bunchuck
Executive Vice President
Garrett M. Byrnes, P.E.
Thomas F. Maher, P.E.
�+ !�
Solid Waste Coordinator
Vice President
Town of Southold
Robert Burns, P.E.
David S. Glass, P.E.
Vice President
53095 Main Road
Richard M. Wake
Vice President
Southold, NY 11971
Steven A. Fangmann, P.E.
William D. Merklin, P.E.
Vice President
Vice President
Michael Neuberger, P.E.
Re: Southold Landfill Closure
Senior Associates
D&B No. 1314.
Anthony O. Conetta, P.E.
Dennis F. Koehler, P.E.
Dear Mr. Bunchuck:
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr. Enclosed please find a copy of the letter to Terry Contracting & Materials
Brian M. Veith, P.E. regarding a request for a credit for sewing rather than heat seaming the geotextile
end of the geocomposite, which I inadvertently neglected to copy you.
Associates
Garrett M. Byrnes, P.E.
Very truly yours,
Rudolph F. Cannavale
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
Gerald Gould, CPG
Thomas F. Maher, P.E.
William D. Merklin, P.E.
Vice President
Michael Neuberger, P.E.
T /
TFM tam
Richard P. Russell, P.E.
Enclosure
Charles J. Wachsmuth, P.E.
Kenneth P. Wenz, Jr., CPG
cc: I. S1k1nc
R. Terry
T. Howell
P. Sutherland
C. Morris
01314lrFM02LTRAoc-20
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvirka
d!
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@woddnet.att.net
January 18, 2002
Principals Mr. Robert G. Terry
Nicholas J. Bartilucci, P.E.
.President Terry Contracting & Materials, Inc.
Henry J. Chlupsa, RE. 840 West Main Street
Executive Vice President
Thomas F Maher, P.E. Riverhead, NY 11901
vice President
Robert T. Bums, P.E.
Vice Presaent Re: Southold Landfill Closure
Richard M. walks
Vxe President D&B No. 1314
Steven A. Fangmann, P.E.
vw President
Dear Mr. Terry:
Senior Associates
Anthony O. Conetta, P.E.
We have reviewed Chenango Contracting, Inc., s request, dated January 17, 2002,
Dennis F. Koehler, P.E.
Joseph H. Marturano to stitch the loose edge of the geotextile around the exposed edge of the
Kenneth J. Pritchard, P.E. geocomposite as it terminates outside the storm water channels, and approve this
Theodore S. Pytlar, Jr. method provided the stitch is a double thread lock stitch, Type 401, with a flat or
Brian M. Veith, P.E. prayer seam.
Associates Since the stitching method is faster than the heat seam geotextile wrap as
Garrett M. Byrnes, P.E. specified in the Contract Documents, the Town of Southold expects a credit based
Rudolph F. Cannavale
on this change. Please provide me with the amount of the credit.
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
- If you have any questions, please call me.
Gerald Gadd, CPG
William D. Merklin, RE.
Very truly yours,
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. Wachsmuth, P.E.
Kenneth P. Wenz, Jr., CPG
Thomas F. Maher, P.E.
Vice President
TFM/tam
01314/PFM02LTR.doc-15
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
01/22/2002 TUE 16:36 FAX 002/OO�J
a_
Ovirka
and
Bartiiucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
51&364-9894 • 718.460-3634 . Fax: 518.364-9045
e-mail. db-enq@worldnet.attnet
January 22, 2002
PrInCIPRIB
Nicholas J. Dadgueei, P E
emmw
HQM J. Chlu4ps r, P.E. James Bunchuck
D,eaci,e u+w -+wJ,ier
Thomas F. MOW, P.E.
Solid Waste Coordinator
wa {1YvAo
Town of Southold
kamen� ns, P.E.
wo
53095 Main Road
gieherd M. YUhlke
V" preAmnr
Southold, NY 11971
Slievenk Fanpmem, P.E.
*V %vsM-*
Re: Southold Landfill Closure and
Senior A**otlstes
Compost Facility Construction
ArO=y O. Caropa, RE
D&B No. 1314
Dems F. Koehler, P.C.
Jo seph K MvAur=
n 7'
Dear MT, Bunchuck:
Kemain J. Pmenara, PE.
Themore 6. PpWr, Jr
Wan NL Mwlh, re,
Based on comments received at the January 17, 2002, Progress Meeting on my
analysis of landfill closure savings, and additional costs, and compost facility
Aeaedl.kts
construction costs,- 1 have revised the cost analysis, which is enclosed with this
Nrrattk 9ymos, RE
letter. Please review the enclosure and provide me with any additional comments
`umw F• cmnaveie
at the January 24 Progress Meeting, in particular as it relates to allocation of costs
Joseph Fmraiiso, P.E...
to either the closure or compost facility project.
David $. Glass, P.E.
Gerald OOWtl, CFO
These are a few items on which I need clarification:
welled U. Meech, P.E
Michael NeuEugee,, P.E.
Richard P Paseo. PE.
1. Should removal/trauling of unscreened sand from the 17 -acre parcel
Cherlae J. Vachamurh. PE and placement at the landfill as contour grading/subbase inaterial
ldnnSM P. wean, A. cPa ($31cy) be charged to the closure or compost project?
2. Should removaUhauling of screened sand from the 17 -acre parcel and
placement at the landfill as gas venting and barrier protection material
($3/cy) be charged to the closure or compost project?
3. Should the screening of sand from the 17 -acre parcel ($2.50/cy and
$3.65 cy) be charged to the closure or compost project?
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, PC, -
01/22/2002'TUE 16:37 FAX
y
®virka and Bartilucci
CONSULTING ENGINEERS
Z 003/008.
James Bunchuck Page Two
Solid Waste Coordinator
Town of Southold
January 22, 2002
4. Should the testing of the screened and unscreened sand from the 17 -acre parcel be
charged to the closure or compost project?
By copy of this letter, I am requesting that John Romanelli and Bob Terry also review and
provide comments on this letter and the enclosures, including review of the quantities by Bob
Terry.
.
Vemlruly ypyxs�
Thomas F. Maher
Vice President
TFM/tam
Enclosure
cc/encI: John Romanelli
Bob Terry
01314MM0MTA.doo-18
13
01/22/2002 TUE 18:38 FAX
SOUTHOLD LANDFILL CLOSURE
SAVINGWADDITIONAL COST ANAL Y•SB
AS OF JANUARY 15, 2002
SAVINGS'
Item No. " Description Unit Price Estimated - Actual
3 Reduction in clearing and - $1,200/acre 50 aeres 12 acres
4004/008
Savings
$45,600
7
Elimination of Gcotextile
$21st'
166,000 sy
0
$332,000
Type, I between final 6"
subgrade and gas venting layer
30
Elimination of sand pit
$3/cy
73,000 cy
0
$219;000.
regrading
21
Elimination of southwest
$8.75/sy
1,030 sy
$9,000
maintenance road
13E
Elimination of contingency
$13.80/cy
18,000 cy
0
$248,400
off-site topsoil
13A
Manufacture of additional on-
$7/cy
18,000 cy
0
(126,U00)
site vegetative growth medium
A
$122,400
22
Elimination of asphalt for a
$42.50/sy
3,400 sy
0
$144,500
portion of Main Access Road
1,020 ft, x 30 ft. m
9
21
Replacement with 12"
58.75/sy
3,400 sy
0
29,7 0
recycled concrete aggregate
A
$114,802
Elimination of waterproofing
manholes along southwestern
drainage system
$1,700
26
Reduction of depth of
southwestern drainage system
19A
Elimination of fencing along
$18.?51f
1,260 If
$23,600
western boundary
01314(r0x15=(R05) /
01/22/2002 TUE 18:38 FAX
0005/008
. SOMHOLD 1LANDFML CLOSURE -
SAVINOS/ADDITIONAL COST ANALYSIS -
AS OF JANUARY 15, 2002
ADDITIONAL COSTS
item No. Description
32 Test pit excavation to
detcrmine limits of waste
Unit Price Estimated Actual Cost
$1,200/day 0 9 days $10,800
33 Placement of waste after $25/ton 0 2,575 tons $64,375
baseline topographic survey (-10,000 cy)
5D Excavation of waste from $6.78/cy* 0 7,138 cy* $48,396
Area 2
5E Excavation of waste from $5.78/cy* 0, 6,911 cy* $46,857
Area 3
10 Additional gas vents due to $1,184/vent 39 vents 51 vents $14,200
placement of loam on west
side and test vents on cast
side
(Charge Spreading of Greenport $21,000 LS 8,400 cy $21,000
to DOT?) Pond material
5A Additional excavation of $6.78/4* 2,000 cy 2,010 cy* $68
waste from area 1
5C Pull back and backfilling of $3/cy 0 3,000 cy S9,000
waste in Waste Excavation
Area 2
Excavation of waste from $6.78/cy* 493 cy $3,313
.Area 4
(Charge to
Compost
Facility?) Testing of 17 -acre soil
3 Pull back and relandflling of $5/cy 0 395 cy $1,975
waste in Waste Excavation
Area 3
013141TO115202(R45)
01/22/2002 TUE 16:39 FAX R006/008
ADDITIONAL COSTS (continued)
Item No. Description . - Unit Price Estimated - Actual - -C4,st
6 Additional contour grading $3/cy 36,000 cy —80,000 cy $132,000
material
I l Additional geocornposite $4.20/cy 39,000 sy 59,000 sy$84,000
28 ---Modified water supply wellNew drainage system on east
side, including enlarged
Recharge Basin 3
6 Backfilling of Recharge $3/cy 0 ---12,300 cy $36,900
Basin 4
*In-place
01314rr0115202(ROS)
#q�a��s�
sa 1,1' w s �gl g vo-
co,
01/22/2002 TUE 16:39 FAX
Y
COMPOST FACILITY CONSTRUCTION `
Description
Clearing and grubbing
Windrowing of topsoil and loarn
Removal and stockpiling of topsoil in borrow -
pit
Removal and placement of topsoil on landfill
Removal and placement of loam on landfill
Removal and placement of loam in borrow pit
Excavation and screening of initial 25,000 cy
of sand
Excavation and screening of remaining sand
? Removal and placement of unscreened
sand on landfill as contour grading
material and 6" subbase on west side
? Removal and placement of screened sand
on landfill as gas venting layer and
barrier protection layer
Temporary access mad to 17 -acre parcel
Relocate temporary access road
Permanent access road to 17 -acre parcel '
Widening of the northwest road from 17 -acre
parcel to the borrow pit
Modification to southwest drainage system*
Additional guide rail*
0 13141TOI15202(R05)
Z007/006
Un nt ri a
Quantity
os --
S1,200/acre
17 acres
$20,400
$2/cy
32,565 cy
$65,134
$5/0y
12,877 cy
$64,385
$31cy
4,321 cy
$12,963
$3/cy
42,833 cy
$128,49.9
$3icy
50,523 ey
$151,569
$2.50/cy
20.000 cy
$50,000
$3.65 60,000 cy $219,000
$3/cy —53,000 ey —$159,000
$31cy
—60,000
-✓$1.80,000
$36,2.50 ]J$
1
$36,250
.$42.50/sy
2,270 sy
$96,500
$8.75/sy
680 sy
$5,950
01/22/2002 TUB 16:40 FAX
Desedption
Relocation of brush*
Temporary 1 nacre pad*
Sound barrier and vegetation along permanent
access road*
*To be determined
0 1314/C0115202(R05)
Unit Price Ouantity - Cost
X1008/006
DVIRKA AND BARTILUCCI
CONSULTING ENGINEERS
330 CROSSWAYS PARK DRIVE
WOODBURY NY 11797-2015
PHONE: (516)364-9890
FAX: (516) 364 - 9045
TO: Terry Contracting & Materials, Inc.
840 West Main Street
Riverhead, NY 11901
WE ARE SENDING YOU:
Shop Drawings
Copy of Letter
LETTER OF TRANSMITTAL
Date: 17 -Jan -02 JJob No. 1314-F3
Attention: Robert Terry
Re: General Construction
Contract No. 2000
Southold Landfill Closure
0
Attached
F -I Under Separate Cover Via.
the following items:
For your use
Prints
❑ Plans ❑ Samples
❑ Specifications
Q
Change Order
❑
TRANSMITTAL
COPIES No. Received Returned
DESCRIPTION
1 30b 01/17/2002 01/17/2002
Geocomposite Roll Certifications - Resubmit 2
For your use
Return corrected prints
As requested
E-1 Other
For review and comment
THESE ARE TRANSMITTED as checked below
❑
For approval
F—] Submit copies for distribution
For your use
Return corrected prints
As requested
E-1 Other
For review and comment
I Iff . .�
0 Approved as submitted (A)
= Resubmit copies for approval
Approved as noted (AAN)
F—] Submit copies for distribution
aDisapproved (D)
Return corrected prints
Rejected (R)
E-1 Other
Copies to: J. Bunchuck T. Howell Signed:
'Nax�-
T. Maher P. Sutherland rAaria Wright, P.E.
6 AI -Mau — I. Sikiric
• MDIrnS If enclosures are not as noted, kindly notify us at once
30btransmit.x1s
Dvirka
anand
o Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 - 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucci, RE
President
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F Maher, R.E.
Vice President
Robert T. Burns, P.E.
Vice President
Richard M. Walka
Vice President
Steven A: Fangmann. P.E.
Vwe President
Senior Associates
Anthony 0. Conetta, P.E.
Dennis F. Koehler, P.E.
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
Associates
Garrett M. Byrnes, RE.
Rudolph F. Cannavale
Joseph A. Fioraliso, P.E.
David S. Glass, P.E.
Gerald Gould, CPG
William D. Merklin, P.E.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. Wachsmuth, P.E.
Kenneth P. Wenz, Jr., CPG
January 16, 2002
Mr. Robert G. Terry
Terry Contracting & Materials, Inc.
840 West Main Street
Riverhead, NX 11901
Re: Southold Landfill Closure
Pre -Cast Concrete Waterproofing
D&B No. 1314
Dear Mr. Terry:
We are_ in receipt- of, your letter dated January 15, 2002, with regard to approval
for elimination..of the waterproof coating for all precast manhole structures. As
noted in y_.our.:letter, approval for elimination of the waterproofing is only
provided for:.precast concrete structures located outside the limits of waste. The
credit of $1,700 for elimination of the waterproofing on the manhole structures as
part of the southwestern drainage system is acceptable.
Please do not hesitate to contact me at (516) 364-9890 if you have any questions.
Very truly yours,
Thomas F. Maher, P.E.
Vice President
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvirka
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
January 16, 2002
Principals Mr. Robert G. Terry
Nicholas J. Bartilucci, P.E.
President
Terry Contracting & Materials, Inc.
Henry J. Chlupsa, P. E.
p
840 West Main Street
Executive Vice. President
Thomas F. Maher, P.E.
Riverhead, NY 11901
Vice President
Robert T. Bums, P.E.
trice President
Re: Southold Landfill Closure
Richard M. walks
like Resident
Submittal 27b
Steven A. Fangmann, P.E.
D&B No. 1314
Vice President
Senior Associates . Dear Mr. Terry:
Anthony O. Conetta, P.E.
Dennis F. Koehler, P.E.
Joseph H. Marturano As you are aware, we have reviewed Submittal 27b - Pre -Cast Concrete
Kenneth J. Pritchard, P.E. 'Specifications - Manholes and Stilling Basin - Resubmit No. 2 received in our
Theodore S. Pytlar, Jr. office on January 10, 2002, and submitted comments on the submittal on January
Brian M. Veith, P.E. 14, 2002. In addition to the comments provided in our letter dated January 14,
2002, we also require the following:
Associates
Garrett M. Byrnes, P.E. 1. The Standard Manhole Drill Sheet for Manhole #3, must correspond with the
Rudolph F. Cannavale Contract Drawings. Specifically, it appears as if the two 42 -inch holes in the
Joseph A. Fioraliso, P.E. manhole are not orientated as required by the Contract Drawings.
David S. Glass, P.E.
Gerald Gould, CPG Please include a modified Standard Manhole Drill Sheet for Manhole #3 with
William D. Merklin, PE.
Mikael Neugerger, RE. your resubmittal that incorporates all comments provided to you previously on
Richard R Russell, P.E. this submittal. Please do not hesitate to contact me at (516) 364-9890 if you have
-Charles J. Wachsmuth, P.E. any questions.
Kenneth P. Wenz, Jr., CPG
Very truly yours
Thomas F. Maher, P.E.
Vice President
TFM/MW(t)/tam
cc: J. Bunchuck
I. Sikiric
T. Howell
C. Morris
0 1314/rFM02LTR.doc-12
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
L
d1Dv i rka
and
0 Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 • 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Principals
Nicholas J. Bartilucci, P.E.
President January 15, 2001
'
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F. Maher, P.E.
. Re: Southold Landfill Closure
V"' President
,T_
M • Robert G. Terry
Robert T. Bums, P.E.
Vice President
Terry Contracting & Materials, Inc.
Richard M. Walka
Vim President
840 West Main Street
Vxe Prean; "9ma"", P.E.
Riverhead, NY 11901
Brian M. Veith, P.E.
We have reviewed your letter dated January 11, 2002, requesting additional
Senior Associates
. Re: Southold Landfill Closure
Anthony O. Conetta, P.E.
D&B No. 1314
Dennis F. Koehler, P.E.
Joseph H. Marturano
Dear Mr. Terry'
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
We have reviewed your letter dated January 11, 2002, requesting additional
payment associated with redesign of the drainage system along the southwestern
Associates
boundary of the landfill.
Garrett M. Byrnes, P.E.
Rudolph F. Cannavale
Please be aware that while additional pipe and an additional manhole are required
Joseph A. Fioraliso, P.E.
as a result of the redesign, the depth of excavation and placement of the pipe is
David S. Glass, P.E.
substantially less (average of 6 feet over a distance of 320 feet) and depths of the
Gerald Gould, CPG
manholes are less (manhole #1 is 6 feet less and manhole #2 is 1.5 feet less) as
William D. Merklin, RE.
Mikael Neuberger P.E.
compared to the original design. Please provide a credit (with computation) for
Richard P. Russell, P.E.
the reduction in the depth of the drainage system. Also, your price of $4,125 for
Charles J. Wachsmuth, P.E.
the additional manhole appears high, as compared to the costs provided to us for
Kenneth P. Wenz, Jr, CPG
construction of the new drainage system along the eastern boundary of the landfill
which was $2,500 for a 15 -foot (average) manhole.
Also based on your Schedule of Values, the average cost for an 18 -foot (average)
6 -foot diameter manhole is $3,400 while the requested increase in cost of $4,125
is for a 9 -foot, 4 -foot diameter manhole. Therefore, it appears that the cost for the
additional manhole should not be greater than $2,000.
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvirka and Bartilucci
CONSULTING ENGINEERS
Mr. Robert G. Terry
Terry Contracting & Materials, Inc.
January 15, 2002
Page Two
Please revise your letter of January 11 based on the above comments. If you have any questions,
please call me.
Very truly yours,
Thomas F. Maher, P.E.
Vice President
TFM/tam
cc: J. Bunchuck
I. Sikiric
C. Morris
M. Wright..
O 1314/rFM0MM.doc-10
Principals
Nicholas J. Bartilucci, P.E.
President
Henry J. Chlupsa, P.E.
Executive Vim President
Thomas F. Maher, P.E.
Vice President
Robert T. Bums, P.E.
✓ice President
Richard M. W'alka
✓Am President
Steven A. Fangmann, P. E.
Uwe President
Senior Associates
Anthony O. Conetta, P.E.
Dennis F. Koehler, P.E.
Joseph H. Marturano
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
Associates
Garrett M. Byrnes, P.E.
Rudolph F. Cannavale
Joseph A. Fioraliso, P. E.
David S. Glass, P.E.
Gerald Gould, CPG
William D. Merklin, P.E.
Michael Neuberger, P.E.
Richard P. Russell, P.E.
Charles J. wachsmuth, P.E.
Kenneth P. wenz, Jr., CPG
Dvirka
and
Bartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ° 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
January 14, 2002
Mr. Robert G. Terry
Terry Contracting & Materials, Inc.
840 West Main Street
Riverhead, NY 11901
Re: Southold Landfill Closure
Submittal 34
D&B No. 1314
Dear Mr. Terry:
We have reviewed Submittal 34 - Corrugated High Density Polyethylene Drain
Pipe Specifications received in our office on January 10, 2002. We have
reviewed the submittal with respect to the requirements of the Specifications for
the above -referenced project. Our comments are as follows:
1. The pipe shall bear the class of pipe and trademark of the
manufacturer.
The submittal has been stamped "approved as noted." Please do not hesitate to
contact me at (516) 364-9890 if you have any questions.
Very truly yours,
Thomas F. Maher, P.E.
Vice President
TFM/MDWt/.cmc
cc: J. Bunchuck
I. Sikiric
T. Howell
C. Morris
P. Sutherland
M. Wright
♦ 1314\TFM02LTR-09.DOC
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
J
Dvi rka
and
Dartilucci
CONSULTING ENGINEERS
330 Crossways Park Drive, Woodbury, New York, 11797-2015
516-364-9890 ■ 718-460-3634 ■ Fax: 516-364-9045
e-mail: db-eng@worldnet.att.net
Kenneth P. Wenz, Jr., CPG 1. The concrete mix design for the stilling basin must be provided.
2. The shop drawing for the stilling basin shall indicate that the precast
concrete will meet the requirements of ASTM C478.
3. The contract drawings indicate the stilling basin base has.concrete fill.
4. Remove reference to 60 mil HDPE liner on stilling basin shop drawing
and indicate stilling basin is to be installed in accordance with the
contract drawings and specifications.
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
January 14, 2002
Principals
Nicholas J. Bartilucci, P.E.
President
Henry J. Chlupsa, P.E.
Executive Vice President
Thomas F. Maher, P.E.
Mr. Robert G. Terry
We President
Terry Contracting & Materials, Inc.
RobertT Bums, P.E.
Vice President
840 West Main Street
Richard M. Walka
Vice President
Riverhead, NY 11901
Steven A. Fangmann, P.E.
Yice President ,
Re: Southold Landfill Closure
Senior Associates
Submittal 27b
Anthony O. Conetta, P.E.
D&B No. 1314
Dennis F. Koehler, P.E.
Joseph H. Marturano
i_
Dear Mr. Terry:
Kenneth J. Pritchard, P.E.
Theodore S. Pytlar, Jr.
Brian M. Veith, P.E.
We have reviewed Submittal 27b - Pre -Cast Concrete Specifications - Manholes
and Stilling Basin - Resubmit No. 2 received in our office on January 10, 2002.
Associates
We have reviewed the submittal with respect to the requirements of the Contract
Garrett M. Byrnes, P.E.
Specifications for the above -referenced project, and, there are a number of
Rudolph F Cannavale
omissions and inconsistencies between this Submittal and the Specifications.
Joseph A. Fioraliso, P.E.
Based on a telephone conversation with Mr. Timothy Howell of your office, we
David S. Glass, P.E.
understand that the head wall shop drawing will be submitted with the cast -in -
Gerald Gould, CPG
Gould,C
submittals and the cast iron covers also will be a separate submittal.
William D. n, RE.place
Michael Neuberger, P.E.
Based on this review, we have the following comments:
Richard R Russell, P.E.
Charles J. Wachsmuth, P. E.
Kenneth P. Wenz, Jr., CPG 1. The concrete mix design for the stilling basin must be provided.
2. The shop drawing for the stilling basin shall indicate that the precast
concrete will meet the requirements of ASTM C478.
3. The contract drawings indicate the stilling basin base has.concrete fill.
4. Remove reference to 60 mil HDPE liner on stilling basin shop drawing
and indicate stilling basin is to be installed in accordance with the
contract drawings and specifications.
A DIVISION OF WILLIAM F. COSULICH ASSOCIATES, P.C.
Dvirka and Bartilucci
CONSULTING ENGINEERS
Mr. Robert G. Terry Page Two
Terry Contracting & Materials, Inc
January 14, 2002
In addition, it is our understanding that you are considering requesting approval for excluding the
use of Kop-Coat Bitumastic waterproofing on the precast structures. Please provide a formal
request with regard to this issue and modify the submittal accordingly. Please note that the Kop-
Coat Bitumastic waterproofing will be required on any precast structure to be placed within the
limits of waste.
The submittal has been stamped "revise and resubmit". Please do not hesitate to contact me at
(516) 364-9890 if you have any questions.
Ve. truly yours,,
Thomas F. Maher, P.E.
Vice President
TFM/MDW/jmy,tam
cc: J. Bunchuck
I. Sikiric
T. Howell
C. Morris
P. Sutherland
M. Wright
♦ 1314frFM02LTR-07.doc(ROI)