TO OF SOUTHOLD LANDFILL CLOLSURE
Attendees:
Name
J. Brnichuck
T. Maher
R. Terry
MINUTES OF FEBRUARY 24, 2003
PROGRESS MEETING
Affiliation
Town. of Southold
Dvirka and Bartilucci Consulting Engineers
Terry Contracting & Materials, Inc.
1. Lclxnrnenis orl Minutes of previousJanaa><y 29, :?003'1 Ivieetin
Bob Terry and Jim Bunchuck stated that they had no comments on the January 29,
2003, Progress Meeting minutes.
2. Status of Installation of Replacement Water Supply Well
Jinn Bunchuck stated that the construction contract :had been signed, but no work
has been performed.
Status of Construction on 17 -acre Parcel
The Town will remove the remaining sand and gravel.
4. Status of Completion and Testing of Gas Monitoring Wells
and Completion of Cmoundwater I_ onitgj:,Li ells
Bob Terry staffed that he will request Casolki to check all of the wells to ensure that
they are complete, except for the concrete pads which will be installed in the Spring, Tom
Maher provided Bob with a list identifying the work that had to be completed for each weal
based on D B's last inspection.
01.114M.10301(R51)
1
Z 004!00
03 05!2003 WEIR 05:25 FAX
5. Status of New Access Road to Cox. Lane
Jiro Bunchuck stated that the Suffolk Colmty Department of ]Health Services has
approved the site investigation results and that remediation is not necessary if an asphalt
road Is constructer. The Town needs to speak with Coraazini to complete the land swap.
6. Costs for Additiowil SurveYs
Worn Maher stated that befora he can approve any additional survey costs, he will
need a detailed breakdown of the costs for each survey activity. This required cost
information also was provided in a letter to Bob Terry, Bob stated that he understood the
requirement and will work with Chris Dwyer of L.K. MULean Associates to get the
infonnation to Tota.
7. protection of Erosion Control Blanket
Bob Terry stated that the rolls of erosion control blanket on the landfill have been
moved and fully covered, and that the erosion control blanket stored by the office trailer
also has been fully coveted.
$. &e llacernent of Concrete Blocks Along Road to 17 -Acre Parcel
Bob Terry stated that no blocks have been placed since the last progress Meelbig
due to the weather..
9. Easertlwnt Te;rminw6on
Will wait until transition areas are graded.
0 1'4141rO301301(RD 1) 2
2005/007
03/05/2003 WED 08:26 FAX
1 C. Retaining WalllEasement Along McBride PropertylReloeation of Road
Tom Maher stated that based on a survey performed by D&B, it appears that the
road can be relocated away from the property line without significantly affecting the
swales. When the weather improves, Tom and Bob Terry will stake out the relocation of
the road to ensure that it will work.
11. Grading of Trsiti�a
Torn Maher stated that based on a survey performed by D&B, it appears that the
transition grades between the maintenance road and the property line to the preconstruction
elevations can be achieved with a maximum 2'/2:1 slope, except for a few locations along
the Corazzini property, where, according to Jim Btuichuck, Corazzini has agreed to allow
the extension of the transition area on to his property. Tom's inspector will work with Bob
Terry's operator during the transition area grading.
12. Proposal for Gates
Bob Terry stated that he will provide a proposal to Ain Bunchuck today.
13. Removal ofFluger Material
This will wait until the transition area grading is to be performed.
14, Town Power Requirements
Jim Bunchuck stated that he will get this information to Bob Terry this week.
013141r0303301(RO1) 3
2006/007
02/05/2003 NVED 08:26 FAX
15. CoMpleti In of All RqmgLw:1rgHQIL%
Bob Terry stated that he will provide this infonnation/schedule for completion to
Tom MaheT and Jim Bunchuck- next week.
1.6. Schedule of Work for Next Tvko Weeks
See heir N15,
17. Alternate Headwall for Recharge Basin No. 3
Bob Terry stated that he would like (v prepost a sLnipler and less costly headwall
for this recharge basin. Tom Maher indicated that he would consider an alternate after the
details are providf.-d by Bob. Bob stated that he would provide a proposal for review.
18. M,-mufacture of Topsoil
Jim Bunchuck. stated that he is continuing to produce. compost and it is being moved
into the Borrow Pit Where it can be used to mani):Chcrure topsoil by Bob Terry beginning in
mid March.
19. QQ pletion of Submittals
Torn Maher provided Bob Terry )Aith a letter documenting the remaining
subipltialslit,,vised submittals that need to be provided.