TOWN OF SOUTHOLD 1LANDFILL CLOSURE
Attendees:
Name
J. Bunuhuck
T. Maher
R. Terry
MINUTES OF JULY 2, 2003
PROGRESS MEETING
Affiliation
Town of Southold
Dvizka and Bartilucci Consulting Engineers
Terry Contracting & Materials, Inc.
].. Commentfi on Minutes of Previous (June 19, 2003) Meeting
Bob Tcrry stated that he had no continents on the previous (June 19, 2003) meeting
minutes.
2. Status or installation of Replacement Water Say)& Wel1
Tom Maher suggested that, consistent with the original design, the replacement
water supply well should be located as close to Route 48/upgradient of the landfill as
possible. Jinn Runchuck stated that he will amominodate this suggestion to the degree
possible and inform NYSDEC of the revised location.
3. Status of Testing of Gas Monitoring Wells
and Completion of Groundwater Monitoring Well
Torn Maher stated that the groundwater monitoring wells still need bollards, or
other agreed upon methods of protection, and pads.
4. Replacement of Concrete Blocks Along Road to 17 -Acre Parcel
Bob Terry stated that the concrete blocks will not be replaced until the Town
decides whether to inial pave the asphalt roads.
G 13 i4/rO71 "01
Z004/007
07/16/2003 WED 13:49 FAX
5. Fasement Termination
Jim Bunchuck stated that the construction easement terrnination letters are being
mailed next week,
6. Placement o `Topsoil and Erosion Control Blanket
Bob Terry stated that all placement of topsoil, seeding and erosion control blanket,
except for Recharge Basin No. 1, is complete.
7. Installation o f Fenein and Sound Barrier
Jinn Bunchuck stated that further installation of fencing and consrruction of the
sound barrier depend on Finalization of quantities and determination of monies remaining
within the original contract amount.
�. ColnPletion of Submittals
Bob Terry stated that he tried to contact Maria Wright of D&B this week regarding
resolution of final submittals, but has not been able to speak with her. Torsi Maher
explained that she is on vacation, but that Bob should be able to reach her next week (July
7, 2003),
9. Com-oletion of Recharge Basins
Bob Terry stated that all recharge basins are completed except for Recharge Basin
No. 1 (see item 6 above). Because it is unlik=ely that the asphalt roads will receive final
paving, Tone Maher asked Bob Terry to contact Corazzini to install a curb by Recharge
Basin No. I in order to complete construction of the basin. Bob Terry stated that he will
contact Corazzini this: week.
Q IIVI 0715301
X1005/007
07;16f2003 WED 13:50 FAX
10. Completion of Paving
Jim Bunehuck stated that there is no final decision with regard to final paving, but
relative WOO remaining work, Bob Terry should proceed with completion of work.
11. Punch List Items and Schedule of Work
Tom Maher reviewed the punch list items with Bob Terry and Bob reported on. the
actions as listed on the attachment for the Mimites of the June 19, 2003, Progress Meeting
(Item 12).
Items Status
1) Complete grading of transition area and place topsoil, seed and Completz
erosion control blanket by Coraz7lni.
2)
Clean out catch basins and cover or remove exposed textile.
?
3)
Check grouting in mz-alholes,
?
4)
Move temporary fence around wells along eastern landfill
Completed
boundaiy.
5)
Clean up along eastern landfill boundary :aid access road to Cox
Completed
Lane.
G)
Complete clearing of access road to Cox Lane.
?
7)
Place stone around manhole by Recharge Basin No. 3.
Completed
8)
Extend rip rap by hea0wall in Recharge Basin No. 3.
Needs to be
Completed
9)
Straighten gas trench vent pipe ae long east side.
Completed
10)
Install split rail fence by Collection Center.
Needs to be
Completed
l I)
Move concrete blocks to edge of Recbarge Basin No. 2.
Completed
0 131VO715301 3
Z 006/007
07/16/2007 WED 13:50 FAX
12) Put 4' rings around wells by Recharge Basin No. 2 with concrete Needs to be
pad inside tapering from the well to bottom of first slot. Completed
13) Remove sand bags and geocomposite by Recharge Basin No. 2. Completed
14) Smooth west central maintenance road. Completed
15) Remove silt from Recharge Basin No. 1. Completed
16) Complete replacernent of concrete blocks along road to Compost Needs to be
Facility and topsoil and erosion control blanket along north face of Completed
Recharge Basin No, 1.
17) Remove sand bags in swalti along road to Compost Facility. Completed
18) Coin ,plete topsoil wid erosion control blanket in Recharge Basin Needs to be
No_ 1. Completed
a> 914,TO71s30 i 4
2007/007
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11
SOUTHOLD LANDFILL CLOSURE
AGENDA ITEMS FOR
JULY 2, 2003, PROGRESS MEETING
Comments on Minutes of Previous (June 19, 2003) Meeting IZZM jocvk- 110
Status of Installation of Replacement Water Supply Well
Status of Testing of Gas Monitoring Wells and Completion of Groundwater
Monitoring Wells
Replacement of Concrete Blocks Along Road to 17 -Acre Parcel
Easement Termination
Placement of Topsoil and Erosion Control Blanket
Installation of Fencing and Sound Barrier
Completion of Submittals
Completion of Recharge Basins
Completion of Paving
Punch List Items and Schedule of Work
4-0 S 'rL-07 Su, -1-4-Y 51e
P eztA
a L--vO 13, —