HomeMy WebLinkAbout04/12/200204/18/2002 TUE 11:07 FAX
Attendees:
Name
J. Buil buck
J. llomanelli
T. Wickham
T. Maher
C. Morris
R, Ferry
T, Howell
TOWN OF SOUTHOLD
LANWILL CLOSILR E
MINUTES OF APRIL 12, 2002
PROGRESS MEETING
Affiliation
Town of Southold
Town of Southold
Town of Southold
Dvirka and Bartilucci Consulting Engineers
Dvirka and Bartilucci Consulting Engineers
Tent' Contracting & Materials
Terry Contracting & Materials
Minutes of Previous !A ril g. 2002) Meeting
Tom Maher disaveed with Bob's claim, in item #2, that the gest side of the
landfill was done without a grading plan, and stated that there was a ,grading plan for the
west side. Bob replied that they did not build the west side according to the plan as a
result of the additional material placed on the west side, and reiterated his claim that the it
was completed without a grading plan. Tom stated that the reason for change in grading
as compared to the plan provided was due to the fact that the subgrade was less than
required minimum 4% grade in a few areas.
2. Status of. Surveying and Staking of Eastern Portion of Landfill by_McLean
Tom Maher asked the status of the staking the eastern portion of the landfill. Bob
Terry replied that the eastern drainage system has been staked out. Tont asked if the
property line on The east side has been staked. Bob answered yes. Torn asked Bob if he
had received the revised grading plan for the east side. Bob said yes and added that
McLean is working on the plan and is scheduled to stake the east side on Monday.
G1314/Cd415203
1
1004/008
04/18/2002 TUE 11:09 FAX
3. Nonyotable Well — Fire Department Plan, to Install
Tom Maher asked the status of thy; well installation. Jim Bunchuck responded
that he was supposed to hear from Sandy Freeman. of the Cutchogue Fire District this-
week,
hisweek, but has not as of this point. Tom Wickham asked what the cost of the well is now
expected to be. Jim replied approximately $16,000. Tom Maher stated that the price
does not include the electrical work and other equipment such as the pump. Jim agreed
and added that they are consulting with an electrician on the price for the work needed.
4. West Half of Landfill — Status ani Plan for Completion
Bob Terry said that he has spoken with Chenango about the additional cost for the
extra liner work associated with construction of the permanent road and the removal of
the temporary road, and is expecting to have their response today. Bob added that he has
done so in order to make everyone aware up front of the costs. Tom Maher stated that it
is important that Terry ruake the permanent road usable as soon as possible. Bob replied
that he is aware of that and that he is working towards it. Bob continued to say that
Cherango may be here to install liner In the area the week after neat. Tom stated that it is
important to discuss the sequence of the upcoming work in order to avoid delays and
suggested completing the east side in sections to avoid surveying delays. Bob replied
that Tom's plan may be a good idea. John Romaanelli said that anyway to move the work
along quicker is desirable.
5. Status of Submittals
Tim Howell stated that he -has sent all of the geomernbrane roll certifications to
Tom Maher. Tom suggested that Terry review the schedule of submittals to avoid any
delays.
6 1314fr0415203 2
R005/008
'At
04/16/2002 TUE 11:10 FAX
6. Vegetative Cover Mix — Agronomist Certification/
Revised Report and Testing by University of Massachusetts
Tom Maher asked the status of the University of Massachusetts report. Jim
Bunchuck said he is expecting to receive something from them today.
7. Status of Sand Screening and Testing
Tom Maher asked if the sand screening process is ongoikg, Bob Terry answered
yes, and stated that the screening process will have to stop early next week, as they are
quickly running out of available area. Bob added that screening cannot continue until the
permanent pad is constructed on the 17 -acre property, which likely will not be for another
week. Tom asked Bob if he believes there is anything that will delay Terry from
screening sufficient sand to complete the job by the revised substantial completion date.
Bob answered that he does not believe so.
S. - Soil Test Results
Tim Howell stated that he still needs to collect a few samples of the gas venting
layer.
9. Status of Backfill of Recharge Basin 04
_and Construction of Eastern D_tai= a S. vstem
Tom Maher stated that the new grades for the area of Recharge Basin .44 are
included on the new revised grading plan for the east side of the landfill and asked Bob
Terry to review the plan. Tom continued to say that a dry well may have to be added at
the base of the loading ramp should drainage problems occur.
Tom asked the status of the eastern drainage system construction. Bob replied that
construction should begin next week and that regarding of the Shroder area should begin
early next week.
013141TO415203 3
121006/008
4`1
04/18/2002 TUE 11:12 FAX
10. Status of As -Built Drawing -ft Southwest Drainage System
Tom Maher asked Bob Terry the status of the as -built for the southwcst drainage
system.. Bob stated that they could possibly get the as -built to Tom today. Tom then
suggested that Terry provide a copy of the as -built to him before completing work in the
area in order to rectify any problems with the system while it is still partially exposed.
Tim Howell said that he needs to speak with M- cLean and have the drawing labeled
properly before providing it to Tam.
11. Rop-arding Area of Shroder P -m =
See item #9.
12. - Schedule to Manufacture To soil
Tom Maher asked Bob Terry what is preventing him from starting the
manufacturing process. Bob replied that the Town is still screening compost in the
borrow pit, therefore, he does not have ample room. Tom asked how long it will take to
screen the necessary amount of topsoil to complete the job. Bob said that they can
produce 500-800 cubic yards of topsoil a day at best. Tom said that he believes 34,000
cubic yards of topsoil are needed, meaning it will take 50-80 days to produce the
necessary amount of topsoil. Tom then said it is critical that the work begin soon. Bob
agreed and said he hoped to begin by the middle of next week. Jim Bunchuck sated that
the Town is scheduled to stop screening compost Sunday. Bob replied that the Town will
need a few extra days to haul out the screened waste once the screening work is stopped,
and added that he now believes they have screened enough compost to complete the.
project. Tom stated that we still need the results from the University of Massachusetts
report before topsoil production can begin. Bob responded that the soil testing is Terry's
responsibility and that he hoped to receive his results from Cornell shortly.
01314/ro415203 4
0007/008
04/18/2002 TUE 11:13 FAX
13. Schedule of Work for N xt WE
Bob Terry said they will complete the schedule today and provide a copy to Chris
Morris.
14. Revised Construction Schedule to Complete project
Tim Howell provided copies of the revised construction schedule to all attendees
which now list the substantial completion date as October 10, 2002. John Romanelli
stated that he was not aware that the Town Board was responsible for causing a major
delay to the project by not promptly deciding on the driving range plan, Tom Wickham
agreed with John's statement. Jim Bunchuck said that the Town Board only caused
delays after January 1, 2002, after the new Board was in place. Jun added that Terry slid
not file any delay claims because he was able to focus his efforts on other tasks; however,
as of January I' he had to scale back his work force. Bob Terry stated that he cut his
work force at a much earlier date. Tom Malier informed John. and Toren Wickham that
discussions on the driving range began in October and continued until finally being
resolved in February. Tom also said that in addition to the driving range other delays
were caused as a result of the necessity to coordinate the landfill closure with the project
on the 17 -acre property. Bob added that delays were also caused as a result of extra
material being added to the landfill to accommodate the Town, such as the Greenport
pond material and C&D, as well as other factors including the eastern drainage system
and the necessity of keeping the 17 -acre property active. John and Tom Wickham
echoed their concern that they were not aware the Town Board was causing any delays.'
Jim said he believed the issue was put on hold until the new Board took office in January,
and stated at that point he did matte the Hoard aware that a decision was critical. Tom
Maher said that he believes the job may finish before Terry's proposed new substantial
completion date, and unformed Bob that he still needs to file a formal request for the
extension and to provide au explanation for the extension. Bob replied that he is aware of
it
01314fr0413203 - 5
X1008/008