TOWN OF SOUTHOLD
LANDFILL CLOSURE
MINUTES OF JUNE 12, 2002
PROGRESS MEETING
Affiliation
Town of Southold
Town of Southold
Dvirka and Bartilucci Consulting Engineers
Dvirka and Bartilucci Consulting Engineers
'ferry Contracting & Materials, Inc.
Terry Contracting & ]Materials, Inc.
1. - Minutes of Previous (May 31, 2002) Meeting
No comments on the minutes.
2. Status of Surveying of Eastern Drainage System and
Manhole 93 (Southwest Drainage._System) by McLegn
01003/007
McLean has surveyed both but Torn Maher said he has not received the information as
yet. Bob Terry said he will have McLean send the information by the end of today.
3. Cost for Fire Department to Install the N=otable Supply Well
Tom Maher has received the cost front Jim Bunchuck, which is $2$,000 including the
electrical work.
~}1314rr0613201(A61) 1
06/18/2002 TUE 12:26 FAX
a
4. Status. of Submittals
Q004/007
Tim Howell handed to Torn Maher submittals on the liner certification and eastern
drainage system. Torn again requested that, in the future, Terry send one copy of all submittals
regarding geosynthetics and soils data directly to Tectonic Engineering.
5. Test Results of Vegetative Cover Infix by the Town and Terri
Bob Term expressed concem over the minimum 5 percent organic content required in the
final blended mixture of 3 parts compost, 2 parts topsoil and 1 part sand. Tom. Maher asked Jim
Mulligan to take the required samples, as per the specifications, on the final blended mix, which
will then determine what action might be necessary, if any. It is expected that the blended mix
will be ready in about 2 to 3 weeks.
b. Status of Completion of Permanent lead for 17-gc Parcel
Jim Bunchuck expressed concern on the slow progress in creating the permanent RCA
pad. Torn Maher suggested getting Janie Richter of the Town more involved to work out
problems together with Jiro and Bob Terry. Jim also has not been. ,able to get H2M to provide
assistance on the berm design. John Romanelli said he will call both Jamie Richter and H2M to
help Jim out. Bob Terry said. there may come a time when he will have a problem with
manpower doing toroth the landfall and compost facility work; however, based on the existing
situation, Bob did not foresee any delays in completing the landfill closure. Tom Maher said that
he would not recommend to the Town any further contract extension beyond that recently
approved for completion of the landfill project, and that it is Bob's responsibility to provide
adequate equipment and manpower to complete both projects according to schedule.
7. Status of Sand Screening and Testin
No sand screening is being done at the present time.
0 1314/r0613201(RUl) 2
00/18/2002 TUE 12:27 FAX
g. Status of Soil Test Results
0005/007
All required soil testing has been completed and the results are satisfactory according to
Tim. Howell.
9. Status of Further Regradiney Area of shroder Property
The regrading by the Sbroder property is neat complete and Bob Terry said this will be
completed after fuiisMag 'work on the east half of the landfill.
10. Schedule to Manufacture Topsoil
Approximately 3,000 cy of vegetative cover mix has been made to date with a goal to
make 39,000 cy total.
It. Dai1y Schedule of Work fur Next Two alecks
Tim Howell said he will have the schedule to Jim MulUgan by this afternoon.
12. _Status of Request for Time Extension
Terry's request for the time extension has been approved by the Town and Bob Terry has
been given the Change Order by Tom Maher.
13. Schedule for Construction of Permanent Road
Tom Maher pointed out that Terry's June 6, 2002, project schedule calls for ' the
permanent road construction to begin during the first week of July, Tom wvilI have a road
construction inspcetor from D&B on-site at that time.
01310061320i(RO) 3
06/16/2002 TUE 12:27 FAX
14. Revised Construction S.QhIi
Bob Terry has submitted the new schedule dated Janne 6, 2002.
15. ch,dule for Installation of Gas Monitoring_ Wells along Southwestern B4undaTI
0006/007
Bob Terry said his subcontractor, Cassola Well Drilling, will be on-site by next
Wednesday (June 19, 2002) to begin installing the four gas monitoring wells along the
southwestein boundary.
16. Responses Due
Stilling Basin Shop —Drawing Information — Bob Terry said he will have this by the
next progress meeting.
- Revised Chenango Cost Bgd2W for phased Liner Installation of West Side — Tim
Howell said he will call Chenango to submit a more refined cost breakdown (man-
hours, etc.) than that contained in their previous letter.
i��V'
Jim Bunchuck said that Terry can no longer fall his water tanker at the recycling center
well due to interference with Town operations. Bob Terry said he will have the electrical work
completed by this Monday at the fire well on Cox Lane so that his tanker can then be filled from
that location as previously requested.
Tom Matter instiucted Bob Terry to install geocomposite up higher (than shown on the
plans) on the northern and eastern slopes of the east half of the landfill, because of the need to
increase the grades due to landfilling of more waste than originally planned.
oasivrrc� 3201(Roi) 4
V - V
SOUTHOLD LANDFILL CLOSURE
G
�3
AGENDA ITEMS FOR
JUNE 12, 2002, PROGRESS MEETING
1. Minutes of Previous (May 31, 2002) Meeting
2. Status of Surveying of Eastern Drainage System and Manhole #3 by McLean
3. Cost for Fire Department to Install the Nonpotable Supply Well
4. Status of Submittals
,8
5. Test Results of Vegetative Cover Mix by the Town and Terry
6. Status of Completion of Permanent Pad for 17 -acre Parcel
7. Status of Sand Screening and 'testing
8. Status of Soil "i est Results
9. Status of Further Regrading Area of Shroder Property
1�1/ 35�'�
10. Schedule to.Manufacture Topsoil V �Al-
11. Daily Schedule of Work for Next 2 Weeks
12. Status of Request for Time Extension L,-,' 4
13. Schedule for Construction of Permanent Road
14. Revised Construction Schedule 14
15. Schedule for Installation of Gas Monitoring Wells along Southwestern Boundary
16. Responses due: - Stilling Basin Shop Drawing Information
- Revised Chenango Cost Backup for Phased Liner Installation