HomeMy WebLinkAbout08/22/200208'27/2002 TUE 08:54 FAX
Attendees:
J. Bunchuck
J. Mulligan
T. Howell
TOWN QF SOUTHOLD LANDFILL CLOSURE
MINUTES OF AUGUST 22, 2002
PROGRESS MEETING
Affiliation
Town of Southold
Dvirka and Bartilucci Consulting Engineers
Terry Contracting & Materials, Inc.
1. Minutes of Previous (August 15, 2002) Meeting
Not received in time for this meeting.
2. status of Submittals
.2003/008
Tim Howell said he is awaiting a response from D&B regarding his submittal on the
erosion control fabric.
3. Status of Stand scree ing and Testing
Sand screening continues on the 17 -acre parcel, although not for the past two days due to
a problen-A with the power screener.
4. Status of Soil Test Results and Resolution of Three Gas Vent Laver Saa'ales
All sampling is up to date according to Tim Howell. Tim recently has taken BPL and
VG -L samples and laboratory results should be received by next week.
0 1s14n092222e1 (P.01) I
08127,'2002 TUE 08;54 FAX Z004/008
5, Discussion with Ed Wankel Regarding Seed_Mixtwe
The seed mix of 60% rescue and 40% Perennial Rye, submitted to D&B by Terry, has
been approved verbally by Prank DeVita. A follow-up call to Ed Wankel was made by Jim
Mulligan again requesting a letter from Ed confirming this seed mix recommendation by him.
Ed indicated the letter would be sent to Tom Maher shortly.
f. Daily Schedule of Work for Next 2 Weeks
See Item. No. 13.
7. Status of Construction on 17 -,Acre Parcel
Terzy continues to excavate and screen sand and is building the shelf along the westerly
property line. Extending the RCA pad southerly cannot be done until George Desmaris of H2M
gives Terry the location of the P'V'C drainage lines and catch basins. Jun Bunchuck will call
George to get this information electronically forwarded to Terry's surveyor, llld ean, so that the
drainage can be staked. The goal by Terry is to install the PVC pipe and extend the RCA pad
neat week.
8. Schedule for Completion of the Permanent Road
and'Removal of the Te=oramv Road to 17 acres
The temporary road has been removed and completion of the perm wient road will take
place in several weeks once the liner and CUM have been placed to the north of the permanent
road.
9. Design of Primary Road on to 17 -Acre Parcel
and Status of Constructs n of Secondary Road
Jim Bunchuck said that H2M is to have the road design completed by tomorrow. Terry
can begin construction of the road once he has the plans from 142M.
Q 13141T0822201(RC1) 2
08!27/6002 TUE 08:55 FAX
10. Status of Completion and Vesting of Cxas
Monitoring Wells AlongSouthwestern Boundary
Jim Mulligan said that the four wells will be tested either this afternoon or tomorrow.
11. Proposal for Plantings AlMg Southern Boundary
Z005/008
Much discussion took place regarding these plantings. Tim Howell will summarize and
submit a ;avritten proposal, including costs, in the near future. Some of the ideas discussed areas
follows:
Q Plant jVborvitae along southern property Hine by residents (near permanent road and
Recharge Basin 01). Also plant several white pines in this area.
o Plant cedar bushes along property line by now recharge basin on 17 -acre parcel and
along northern portion of westerly property line on 17 -acre parcel.
a Stone wall and plantings in area of start of permanent road to 17 -acre parcel.
* Wild flower seeds added to Fescue and rye seed at least on southern portion of east
half of landfill that will be highly visible.
m Install black vinyl chain link fencing, in lieu of galvanized chain link, along southerly
property line by residents. (Will cost more than galvanized fence.)
12. Abandonment of Existing Landfill Well
Cassola Well Drillers filled 93 feet of the 10 -inch steel casing with bentonite grout on
Monday, August 19, 2002. Terry still must cut about 2 to 3 feet off the casing and top off with
cement to bring it to Proper grade.
o 1314/r082a201(Rag) 3
08/27/'2002 TUE 08:55 FAX
13. Revised Construction Schedule
2006/008
Tina Howell submitted a revised construction sehedule dated August 23, 2002, which
shows Tern, still completing the substantial work by November 1, 2002. (See schedule
attached.)
0 1314/T0822201(R01) 4
i�h ft:2�u12 TUE 13:58 FAX
SOUTIIOL D LANDFILL CLOSURE
A.G1GNB.A ITEMS FOR
AUGUST 22 200 I>L' GRFSS MEETING
�yjinutes of Previous (August 15, 2002) Meeting
2.. Status of Submittals
3. Status of Sand Screening and Testing
4. Status of Soil Test Results and Resolution of 3 Gas Vent Layer Samples
Discussion with Ed Wankel regarding deed Mixture
6, Daily Schedule of Work for Next 2 Weeks
7, StatLAS of Construction on 17 -acre Parcel
8, Schedule for Completion of the Permanent Road and Removal of the Temporary Road to
1' -acres
9, Design of primary Road on to 17 -Acre Parcel and Status of Construction of Secondary
Roae
10. Status of Completion and Testing of Gas Monitoring Wells along Southwestern
Boundary
11. Proposal for Plantings Along Southern Boundary — 64
12, Abandonment of Existing Landlilt Wall
1.3. Revised Construction Schedule
Co-, cr& 5e_
2 �'Ca? ,s
IAJI C 1�
a 1314M8202A2(ROI)
� QQ8!QQ8 '