TOWN OF SOUTHOLD LANDFILL CLOSURE
MINUTES OF SEPTEMBER S, 2002
PROGRESS MEETING
Affiliation
Touai of Southold
Town of Southold
Dvirka and Bartilucci Consulting Engineers
Dvirka and Bartilucci Consulting Engineers
Terry Contracting & Materials, Inc.
Terry Contracting & Materials, Inc.
1- Minutes of Previous (August 15, 22 and 30, 2002) Meetings
Q Op3; 008
Bob Terry read the minutes of the August 15 and 22 meetings and had no comments, but
said he has not read the August 30 meeting minutes. There were no. comments from Anyone else.
2. Status of Submittals
Torn Maher said that Bob Terry should receive D&B's approval on the fencing submittal,
but lie still needs a submission by Terry for a credit on the elimination of the privacy slats. Tian
Howell said his is waiting for D&B's response on his submittal for the grass seed mix.
3. latus of Sand Screening and Testing
;Bob Terry said they stopped screening sand as of September 4, 2002, and the power
screener has been moved to the Borrow Pit to manufacture topsoil (vegetative growth mix). It
remains to be seen if the current stockpile of screened sand is adequate for the remaining GVL
and BPL necessary for completion of closure construction.
t;i3141r0906201(R01) 1
09/09/2002 MOIL 12:54 FAX 1@004/008
4. Status of Soil Test Results and Resolution of Three Oras Vent Layer Samples
Jim Mulligan has called peter Sutherland (Tectonic Engineering) twice regarding
resolution of the three gas vent layer samples, but Peter has been on vacation. Jim said he will
call again shortly..
5. Discussion with Ed Wankel Regarding Seed Mixture,
Including Wildflower Mix Along Southern Area of Landfill
Jim Bunchuck said that he wants the wildflower seed to he planted on the southern
portion of the east half of the landfill. All agreed that the wildflower seed would be, applied in an
area running approximately 100 feet north of the southernmost swale and 500 feet east -west on
the east side of the landfill. The wildflower seeds will be in addition to the rye/fescue seed mix.
This area is satisfactory to Ed Wankel based on Jim Mulligan's telephone conversation with Ed.
5. Daily Schedule of Work for Next 2 Weeks
Tim Howell will have next week's work schedule worked up by tomorrow.
7_ Status of C".onstniction on 17 -Acre Parcel
Jamie Richter presented an autocad plan showing details regarding the site grading,
drainage and road work. This plan was then reviewed and additional details were added based
on agreement reached among Jamie, Bob Terry and Tom Maher. Jamie is to electronically
forward the revised plan to Terry's surveyor, McLean Associates, so that critical items, including
catch basins and road construction, can be staked by McLean before Terry begins work. Bob
Terry estimated that the work would take about three weeks from the time that McLean sets the
stakes and he, has the drainage pipe on-site. All agreed that expansion of the existing RCA pad is
critical so that the Town has working room for the handling of the fall brush and leaves and that
it will be completed the end of September.
Q U IVW906201(R01) 2
09/09%2002 MON 12:55 FAX
9. Alternate Barrier Along Perm anent Road
Q 005!0018
Although many consider the concrete .blocks now in place along the pennarient .road not
to be. the most pleasant visually, no one was able to present a low cost alternate. Jim Bunchuck
would like to see rumple strips or speed bumps and signs installed in the roadway to control the
speed of vehicles. Rumple strips were thought best by most people and Bob Terry said this
could be worked into the final surface course of asphalt still to be applied or applied after
completion of the roadway. Jim said that the concrete blacks should remain along the shoulders
of the road.
9.. Status of Completion and Testing of Gas
Monitoring Wells Along Southwestern Boundary
Jinn Mulligan reported that he and Tim Howell had tested the four monitoring wells this
morning and all tested negative.
10. Prnnosal for Planting; Along Southern Boundary
Bob Terry said he will have the planting proposal prepared by Monday, September 9,
2002.
11, abandonment of Bxisting_l,andfill Well
Tire Howell said they still must cut the steel casing and fill with concrete,
12. Status of Revised Construction Schedule
Tim Howell said they are ahead of schedule in applying the contour grading material, but
behind schedule on seeding.
13. Schedule for Installation of Vinyl Coated Fence Alona Boundary of Residential Area
4
c„3�arra9a�zaitaal> 3
09/09/2002 MOI^' 12:55 FAX
Bob Terry said this work will be performed next week.
14. Price for Construction of Asphalt Curb Along Permanent Road
Bob Terry said he still has to get a price from P.J. Corazini.
15. Establish Work Area Along Southeast Boundary of Landfill
2006/008
Bob Terry said they will need a 40 -foot width of area and he will work with Jim
Bunchuck in seeing that both his workers and the Town's workers utilize this area cooperatively.
Using this area is a problem since this is where the public is dropping off their brush. Bob Terry
suggested that the brush could be dropped off by the new access road Corazini is to convey to the
Town, assuming the legal wort: is complete.
16. Metes and Bounds for New Access Road
Jim Bunchuck said he will call the Town Attorney to find out the status of this issue and
will get the metes and bounds if available. If the legal work is completed, this access road could
then be cleared to some extent and thereby provide room for the drop -oto' of brush by the public.
17. Other
- Recharae Basin No. 3
The cost to construct Recbarge Basin No. 3 must be resolved by Bob Terry and Tom
Maher.
- MBElWBE Utilization RZQort
Bob Terry will provide a copy of his latest report to Jim Bunchuck for the Town to
submit to the Mate.
0 1314iTO906201;R01) 4
09/09/2002 MON 12:56 FAX
Haulingof Gravel Off --site
1@ 007/008
Jim Bunchuck was under the impression that the lamer gravel (>1'/z"), from the sand
screening on the 17 -acre parcel, was to be used as needed for the landfill project, but
that any excess gravel would be the Town's property. The minutes of the previous
meetings in September and October 2001, indicate that all gravel from the screening
coperation is the property of Terry. Based on this, Jim Bunchuck agreed that Terry
cim remove the gravel from the site as they scc fit.
01314,70906201(ROI) 5