HomeMy WebLinkAbout09/19/2002,.It
TOWN OF SOUTHOLD LANDFILL CLOSURE
MINUTES OF SEPTEMBER 19, 2002
PROGRESS MEETING
Attendees:
Name Affiliation
J. Bunchuck Town of Southold
I. Sikiric NYS Department of Environmental Conservation
J. Mulligan Dvirka and Bartilucci Consulting Engineers
R. Terry Terry Contracting & Materials, Inc.
T. Howell Terry Contracting & Materials, Inc.
1. Minutes of Previous (September 5 and 12, 2002) Meetings
No comments by anyone.
2. Status of Submittals
Bob Terry said he will be submitting information on an erosion control blanket
alternative and plantings along the southern boundary of the landfill.
3. Status of Sand Screening, Topsoil Manufacture and Testing
Sand screening may be completed. Current stockpile on 17 acres may be sufficient for
GVL and BPL for east half of landfill remaining to be lined. Topsoil manufacturing ceased as of
yesterday since all compost has been used. There are about 1,000 cy of contaminated (arsenic)
topsoil left in the borrow pit. Jim Mulligan questioned whether the stockpile of topsoil
(vegetative cover mix) is sufficient for the entire east half of the landfill to be covered. Bob
Terry offered for consideration to lay 14 inches of BPL and 4 inches of topsoil (total of 18 inches
over liner) and questioned Igor Sikiric if this would be possible. Igor said he will look into
whether this is acceptable to his office and asked Bob what it would cost to import topsoil from
0 1314/T0919201(ROl)
1
off-site. Bob estimated that the in-place- cost would be about $25/cy and, if 4,000 cy extra are
needed beyond what is on-site, the total cost could be $100,000. Jim Mulligan said he will
estimate the stockpile quantity to get a better handle on this issue.
4. Status of Soil Test Results and Resolution of Three Gas Vent Laver Samples
Still waiting for a response from Tectonic on the three GVL samples in question.
5. Status of Installation of Replacement of Water Supply Well
Jim Bunchuck said that the permit application has been submitted to NYSDEC for
approval and was told the review/approval process typically takes about two months. Jim asked
Igor to check into the matter and see if this could be expedited. Also, Jim said they have not
gone out to bid to secure the well drilling contractor.
6. Daily Schedule of Work for Next 2 Weeks
Tim Howell will prepare the schedule this afternoon.
7. Status of Construction on 17 -Acre Parcel
Bob Terry said they expect to begin this afternoon extending the existing RCA pad
southward. A section of the 24 -inch drainage pipe and one catch basin (on northwest part of
system) were installed yesterday. The RCA pad extension will take one day to complete. Bob
Terry and Jim Bunchuck agreed that a ramp (temporary to become permanent) would be needed
from the main access road, which would allow Town equipment to access the RCA pad on the
southern end. The ramp would be built before completing the main access road to allow the
Town to haul brush to the compost operation. Tim Howell said he will have a construction
schedule and costs to Jim Bunchuck by this coming Monday for Jim's meeting with the Town
Board on Tuesday.
0 1314lrO919201(RO1) 2
r
8. Replacement of Sand Along the McBride Property
Nothing done as of this date.
9. Status of Completion and Testing of Gas
Monitoring Wells Along Southwestern Boundary
The four wells still are not completed. Jim Mulligan and Tim Howell will test the wells
tomorrow.
10. Proposal for Plantings Along Southern Boundary
Bob Terry will submit the plantings proposal early next week.
11. Abandonment of Existing Landfill Well
Nothing further has been done on this item
12. Status of Revised Construction Schedule
Jim Mulligan pointed out that Terry is one week behind schedule with completion of
GVL and liner installation. Bob Terry agreed he is one week behind schedule with this work but
argued that, while in part his fault, mechanical breakdown (two Terex haulers) and weather also
have contributed to this. (It is noted that extraordinarily wet weather conditions have not
occurred during the construction period.)
13. Status of Installation of Vinyl Coated Fence Along Boundary of Residential Area
Bob Terry said this work will start today. Jim Bunchuck confirmed that the vinyl fence
would be installed north/south along the boundary of residents by the 17 -acre parcel, in addition
to the previously agreed to boundary running east/west by the residents abutting the landfill.
01314/rO919201(RO1) 3
14. Price for Construction of Asphalt Curb Along Permanent Road
Not discussed.
15. Status of Establishment of a Work Area Along Southeast Boundary of Landfill
Jim Bunchuck said he will have this area cleared by this coming Monday and Bob Terry
will then fence it off.
16. Metes and Bounds for New Access Road
Jim Bunchuck received the metes and bounds last week and gave to Terry. Bob Terry
said he has given the information to his surveyor, McLean Associates, who will survey the road
shortly.
17. Maintenance of the Borrow Pit Perimeter Road and Grading of the Cut Areas
Agreed to review this issue in more detail at a later date.
18. Privacy Slats Along: New Access Road to Cox Lane
Jim Bunchuck said that as of now he does not want privacy slats on the fence along the
new access road from Cox Lane.
19. Other
- Jim Bunchuck said he still is waiting for soil test results on the 17,000 cy of material
from the Calverton site. Depending on the quality of the soil, Jim questioned whether
the soil could be used for making additional vegetative cover mix or grading the
material in borrow pit area. Jim Mulligan recommended to Jim Bunchuck to have the
0 1314/r0919201(ROl) 4
soil tested for organic content should it be considered for use in making vegetative
cover mix.
- Terry submitted payment application No. 9 to Jim Mulligan for the landfill project
and to Jim Bunchuck for the compost facility project.
01314[FO919201(RO1) 5
09/17/2002 TUE 13;41 FAX Z 007/047
SOUTHOLD LANDFILL CLOSURE
AGENDA ITEMS FOR
SEPTEMBER 19, 2002, PROGRESS MEETING
1, Minutes of Previous (Soptember 5 and 12, 2002) Meetings
2, Status of Submittals
3, Status of Sand Screening, 'I'opsoil Manufacture and Testing
4. Status of Soil Test Results and Resolution of 3 Gas Vent Layer Samples
5, Status of Installation of Replacement Water Supply Well
o, Daily Schedule of Work for Next 2 Weeks
7. Status of Construction on 17 -acre Parcel
8. Replacement of Sand Along the McBride Property
9, Status of Completion and Testing of Gas 1blonitoriag Wells along Southwestern
Boundary
10. Proposal for Plantings Along Southern Boundary
11. Abandonment of Existing Landfill Nall
12. Status of Revised Construction Schedule
13. Status of Installation of Vinyl Coated Fence Along Boundary of Residential Area
14. Price for Construction of Asphalt Curb Along Permanent Road
15. Status of Establishment of a Work Area Along Southeast Boundary of Landfill
16. Metes and Bounds for New Access Road
17. Maintenance of the Borrow Pit Perimeter Road and Cmading of the Cut Areas
18. Privacy Slats Along New Access Road to Cox Lane
e
0 r3t4/ro917201(Rni)