HomeMy WebLinkAbout10/31/200211/08/2002 FRI 09:12 FAX
TOWN OF SOUTEIQ7LD LANDFILL CLOSURE
1!' MUTES OF OCTOBER 31, 2002
PROGRESS MEETING
Attendees,
Name Affiliation
T. Maher Dvirka and Bartilucci Consulting Engineers
F. DeV'ita Dvirka and Bartilucci Consulting Engineers
R. Terry Terry Contracting & Materials, Inc.
T, Howell Terry Contracting & Materials, Inc.
Minutes of Previ us October 25 2002 Meeting
a003/009
Lased on conversations held during the Progress Meeting on October 25, 2002, Bob
Terry agreed to stake the northern property line bordering the MoRride property
within a few days after the meeting. Presently, this has not been performed. Tom
Maher stressed the importance of the survey as it relates to the construction of the
northern maintenance road and surrounding area elevations, and expressed concern
that the survey had not been completed earlier as Bob had agreed. Bob indicated that
the property line would be staked by either November 4 or -November 5 of the
following week.
Based on conversations held during the Progress Meeting on October 25, 2002, Bob
'Terry agreed to complete the installation of the head walls in Recharge Basins No. 1
and 3 by November 1. Presently, this has not been completed. Bob Terry indicated
that the head wall submittals, pertaining to reinforcement, additive mixtures, etc.,
would be provided within the next few days,
® Torn Maher indicated that the Date of Substantial Completion would be postponed to
November 8, 2002, due to the need to relocate wood chips in the area of Recharge
Basin No. 3.
® Bob Terry indicated that seeding will continue past the November 1 deadline as
specified in the Contract Documents. Bob Terry was noticed that failure of seed
germination as a result of planting past the specified period is the liability of Terry
Contracting & Materials, Inc.
013 14M 109243(x4 i )
11/08,2002 FRI 09:12 FAX
Z004/009
• Bob Terry was notified that arrangements were to be made between him and the
Town of Southold to address the restoration of all construction easements that were
disturbed. Bob Terry agreed to take the lead in these arrangements.
• Bob Terry was notified that quarterly and monthly MBE/WBE reports were to be
provided to the Town of Southold and Bob agreed to provide the reports.
2. Status of Submittals
Discussions were held concerning submittals remaining for the project. Bob Terry
indicated that they would provide a head wall submittal for review by November 1, 2002. Bob
also indicated that they would provide a well installation plan, which deviates from the Contract
Specifications, for review. Tom Maher stated that the proposed methods must be reviewed and
approved by the NYSDEC prior to being submitted for review.
3. StatIrs of Sand Screening, Topsail Manufacture and Testing
Bob Terry indicated that sand screening on 17 -acre parcel has continued to date. Bob
was reminded by Tom Maher that conformance sampling for all Barrier Protection Layer (BPL)
material must be completed in accordance with the specifications. Tim Howell acknowledged
this and agreed that additional sampling of the BPL material still was required. Tim )=Howell
indicated that the samples will be collected within the next few days for analysis.
4. Status of Soil Test Results
Discussions were held concerning the use of topsoil from the multiplex construction
project located in Riverhead as proposed by Bob Terry for the landfill project. >t wps discussed
that this material would be used mainly for the transition areas. In addition, the materia) must be
sampled for arsenic content as suggested by Bob Terry since this was former farmland, Bob
Terry agreed to collect sample-, of the topsoil and send to Tectonic for organic content and pH
analyses. Bob Terry indicated that compaction testing of the BPL on the east half of the landfill
would be ready for testing by Thursday or Friday of the following week.
0 1114M 107202(R01) 2
11/08r'2002 FRI 00:13 FAX 11005/009
5. Status of Installation of Replacement Water Sunnly Well
According to Jim Bunchuck, the Town of Southold will receive bids for construction of
the replacement water supply well on November 12, 2002.
b. Daily schedule of Work for Next Week
Tim Howell distributed the work schedule for the week beginning November 4, 2002.
Work includes:
Sand screening on 17 -acre parcel
® BPI, placement
• Completion of northern roadway to Borrow Pit (excluding asphalt for road down into
the Borrow Pit)
® Construction of main access road
A Construction of Recharge Basin No. 3
® Construction of eastern drainage system head wall.
1. Status of Construction on 17 -Acre Parcel
No work, is being undertaken pending additional Town bonding and authorization to
proceed.
8. Revlacement of Sand Along the McBride Property
This will be completed prior to the Date of Final Completion (December 1, 2002) as
agreed upon by Bob Terry and Tom Maher.
-01314rr:10720SWI) 3
1108/2002 FRI 09:13 FAX a 006/009
9. Status of Completion and Testing of Gas
Monitoring Wells Along Southwestern Boundary
Wells still need sampling ports to be installed. This, plus construction of all groundwater
and landfill gas wells, will be completed prior to the Date of Final Completion as agreed upon by
Bob Terre and Tom Maher
10. Status of Revised Construction Schedule
Except for topsoil to complete the project, according to Bob Terry, the project is 2-3 days
behind schedule. Toni Maher reiterated that the Date of Substantial Completion is November 8,
2002, and that liquidated damages twill be incurred thereafter.
11, Status of Vinyl Coated Fence Along
Boundary of Residential Area and Route 48
No work performed this week, since it is part of the 17 -acre project.
12. Status of New Access Road to Cox Lane
Jim Btimchuck stated that the stratus of. the Phase II investigation testing should be
provided to the Town by October 25, 2002. Further discussions regarding transfer of the
property to the Town will occur subsequent to receipt of the test results.
13- Maintenance of the Borrow Pit Perimeter Road and Grading of the Cut Areas
This will be completed prior to the Date of Final Completion Date as agreed upon by Bob
Terry and Torn Maher,
01314frt10720.'(ROI) 4
11/08/2002 FRI 09:13 FAX
14. Privacy Slats Along New Access Road to Cox Lane
This work will be addressed pending resolution of the property transfer.
15. Topsoil Requirements to Complete the Project
2007/009
Tom Maher requested that Bob Terry, Jim Bunchuck and representatives froze. Long
Island Compost meet later in the day to discuss contractual agreements to provide material to
manufacture topsoil for completion of the cap. Bob and Jim stated that a meeting was scheduled
for that afternoon.
Bob Terry indicated that the main access road will not be completed for anticipated
topsoil delivery starting November 7, 2002. However, Bob stated that the north maintenance
road and the road down to the Borrow Pit will be completed by the afternoon of November 7 or
the morning of November 3. It was agreed that the construction of the road down to the Borrow
Pit, pertaining to the asphalt paving, would be postponed until all topsoil hauling activities Wow
completed.
15. Items to be Completed for Substantial Completion
Bob Terry was notified that the following items are required (but not limited to these
items) to be completed for Substantial Completion:
• Completion of placement of .8PL material
• Completion of final grading of Recharge Basins No. 1 and 2
® Completion of construction of Recharge Basin No. 3
• Completion of southwest drainage system into Recharge Basin No. 1
Completion of eastern drainage system into Recharge Basin No. 3
• Completion of main access road (including concrete aprons)
• Completion of all drainage swales and structures
e Completion of all maintenance roads
® Completion of landfill gas vents
e Installation of guide rails.
0] 114r1-1107201(Rol) 5
11,`08!2002 FRI 09:14 FAX X1008/000
17, Repair of Erosion Daman Along Swales to Recharge Basin No. 3 _
Bob Terry was notified that the erosion damage occurred in the area of the incomplete
swales to recharge Basin No. 3. This and any subsequent erosion damage caused by incomplete
construction and repairs caused by erosion is the responsibility of TC&M.
0i3I4/rl lon03(ROl) 6
10/29/2002 TUE 15:01 FAX
SOUTHOLD LANDFILL CLOSURE
AGENDA ITEMS FOR
OCTO13ER 31, 2002, PROCaESS MEETING
] _ Minutes of Previous (October 25, 2002) Meeting
2. Status of Submittals
3. Status of Sand Screening, Topsoil Manufacture and Testing
4. Status of Soil Test Results
5. Status of Installation of Replacement Water Supply Well
5. Daily Schedule of Work for Next Week
7. Status of Construction on 17 -acre Parcel
S. Replacement of Sand Along the McBride Property
9. Status of Completion and Testing of Gas Monitoring Wells along Southwestern
Boundary
10. Status of Revised Construction Schedule
11. Status of Installation of Vinyl Coated fence Along Boundary of Residential Arca and
Route 48
12. Status of New Access Road to Cox lane
13. Maintenance of the Borrow Pit Perimeter Road and Grading of the Cut Areas
14. Privacy Slats Along New Access Road to Cox Lane
15. Topsoil to Complete Project
14. Iterns tQ be Completed for Substantial Completion
17. Repair of Erosion Damage Along Swales to Recharge Basin No. 3
01314,71029101