TOWN OF SOUTHOLID
LANDFILL CLOSURE
MINLTI+ S OF JANUARY 10, 2002
PROGRESS MEETING
Affliation
Town of Southold
Town of Southold
Town of Southold
NYSDBC
Dvirka and Bartiluod Consulting Engineers -
Dvirka and Bartilueci Consulting Engineers
Terry Contracting & Materials
Terry Contracting & Materials
I . Minutes of previous (January 3, 2002"f Meeting
No comments by anyone on the January 3, 2002, minutes. Bob Terry to provide
comments on December 27, 2001, minutes.
2. Recharge Basin #4 — Drainage Redesign Cos-, Estimate
Bob Terry submitted a cost estimate to constrict the new drainage system along
the eastern landfill boundary. Bob also is to submit a proposal to eliminate the
waterproofing epoxy from the manhole which cannot be applied udder 40° F. The;
proposed change would result in a $2,100 credit to the Town.
3, Status of Aerial Photograph
Jim 13unchuck said he has contacted Geo -maps and will make arrangements for a
fly -over.
0 1314/r0114203(R01)
I
Qpp3 008
01/16/2002 VIED 14:00 FAX
• 4. Nonnotable Well -Relocation Plan, Permitting and Method of Construction
Toro Maher stated that as a result of the Fire Department's requirements for the
nonpotable well, the budget for redesign of the well and electrical equipment is $12,882..
John Romanelli suggested that the Town Board review and approve the redesign budget.
Torn asked Bob Terry when he will need the well to be completed. Bob responded it is
needed as soon as possible so the cxdsting well can be abandoned. Bob also said the
existing well will be surrounded by geomembrane within two weeks, resulting in the need
for the new well.
5. - Nest Half of Landfill — Status and Plan for Completion
Tom Maher asked Bob Terry the status of the west half of the landfill. Bob said
the work is weather dependent, but that geocomposite is being installed today and he
expects liner installation to resume today or tomorrow. Bob also said that barrier
protection layer placement could begin on Monday and, if the change to the precast
structures is approved, the drainage system work in the southwestern area of the landfill
could begin next week or the week after. Bob asked Tom if a decision has been reached
on the spacing of the vents in the gas migration control trenches. Tom said no, but would
let Bob know shortly. Bob said he needs to submit a design proposal for the wind driven
vents.
G. Golf DrivigZ.R.an&e Design
John Romanelli said the Town Board is meeting on Tuesday to review feasibility
study proposals. Bob Terry stated his concem with the amount of time the project may
take, John said he understands Bob's concern and will make it known to the Board.
0 13141T0114203[ROlj- 2
R004/006
01/16,12002 ITER 14:00 Fax
?. Status of Submittals
Tom Maher said he believes all submittals are up to date except for the formal
submittal on the. geocomposite. Tim Howell provided the submittal for the underdrain
Pipes in the swales to Torte Maher.
9. Vegetative Cover Mix — Agronomist Certification
Bob Terry said his agronomist is attempting to revise his recommendations to use
all of the c:ontxninated topsoil. Tom Maher asked Jim Bunch.uck if he has contacted
anyone for a second analysis of the material. Jim said he is in the process of doing so.
Tom asked Bob by what date the issue needs to be resolved. Bob replied March 1 at the
earliest.
9. Status of Sand Screening and Testing -
Use of 17 -Acre Material for Eastern Portion of Landfill/Cu
Tim Dowell said all testing is up to date.
10. jtgj Q s Vents on Eastern Portion of Landfill
Chris Morris said the wells were tested producing no significant odors. -
11. Regrading of Northeast Area to 3:1 Slope/
Replacement of Cap Material to Meet 1{rig.Ugn Angle Requirements
Jim Bunchuck said fie and Bob Terry rrlet with Schroder on Monday, Bob stated
that he believes the area could be cut 10-15 feet, but Scbroder agreed only to cut the area
6 feet. Toren asked how much sand would be produced from the cut. Bob responded that
the total would,be approximately 1,000 cy. Bob also said that Schroder indicated he may
want a barrier erected in the area.
O ISI41 0114203(ROI) 3
a oo a %oos
01/18/2002 ITEU 14:01 FAX
12, flan for Dust Control During Winter -bleed for Submittal
Tim Howell provided Tom Maher with a letter on the issue from $ob Terry. -
13. Removal of Material in Easement Area o C ni Pro e
Tom Maher asked Bob Terry if material still needs to be moved off the easement.
Bob said yes, when the drainage: pipe is installed. 'Porn asked Bob and Jim Bttnchuck to
delineate the area that needs to be cleared. Bob said he will resolve -the problem with
Corazzini.
14. Soil Test Resells
See Item 9.
15. Completion of Submissions
See Item 7.
16. Winter Work Schedule
Tum Maher asked Bob Terry if he intends to work throughout the winter if the -
driving range plan does not go through. Bob said yes, unless the temperature falls below
100F. Bob stated that the area south of the temporary access road needs to be completed,
some contouring of the east side needs to be done regardless of the final plan, and the
drainage system on the east side also needs to be constructed.
17. _Charge for Use of Unscreened Material and
Screening of Material from 17 -Acre Parcel
Torn M2her provided a summary of use of 17 -acre material to all attendees. Town
calculated that after all of the 17 -acre sand is used, an additional 40,000 cy of material
will have to be used fz-om the borrow pit stockpile. Toni estimated there are 104,000
41314/i$114203(Ul) 4
Q 008/008
01/10/2002 WED 14:02 FAX
c«bic yards of material available in the borrow pit with approximately 80,000 cy of that
total is stockpiled material. Tom stated that there has been confusion over how the
material moved off the 17 -acre parcel is to be paid, as it was not part of the landfill or
compost facility contract. Bob Terry said he has completed approximately $300,000
worth of work on this task to this point. Bob added that there is an addendum to the
compost facility contract stating that the landfill contractor is responsible for moving the
material off the 17 -acre parcel. Tom stated his concern with having a major increase to
the compost facility Contract. Bob said he believes a third contract is neaded for the
work, which will negate the need for a change to the compost facility contract. Toni
noted that 'ferry's bid price for transporting material was the lowest of all the landfill
closure bids. Torn added he believes a third contract involving; the transportation of the
17 -acre material off the facility based on the landfill closure bid prices could be possible,
along with a change order to this third contract for screening the 17 -acre material.
18. Other
Bob Terry said that he needs the sound barrier design, for the southwestern area.
Bob asked about the property swap between the Town and Corazzini. John
Romanelli said the Town and Corazzini have an agreement, but will not be ready to go
forward with it until the spring.