PROGRESS MEETING
• MINUTES OF AUGUST 30, 2001
SOUTHOLD LANDFILL CLOSURE
•
Attendees:
Name Affiliation
J. Bunchuck Town of Southold
D. Zuhoski Town of Southold
D. Glass* Dvirka and Bartilucci Consulting Engineers (D&B)
J. Mulligan Dvirka and Bartilucci Consulting Engineers (D&B)
I. Sikiric NYS Department of Environmental Conservation (NYSDEC)
T. Howell Terry Contracting (Terry)
*via telephone
1. Minutes of August 23, 2001 Meeting
No comments.
2. Pesticide Contaminated Soil
Jim Bunchuck received Terry's cost proposal for $141,000 (based on 6,500 cu. yds.).
However, the Town Attorney said this work must go out to bid.. Jamie Richter is to
prepare the specifications for bidding and time is critical. Tim Howell indicated that
there is a 2 to 3 week window to accept this waste on the landfill. Dave Glass said D&B
will apply to NYSDEC for approval to accept this waste on the landfill on behalf of the
Town. Jim Bunchuck agreed. Tim Howell, at first, thought there is room at the landfill
to accept the .6,500 cu. yds. of material but later said he could not state that with any
certainty.
3. Loam Quantities
Jim. Mulligan indicated 21,000 cu. yds. of loam have been removed from the 17 -acre
parcel thus far and that an additional 40,000 cu. yds. (approximate) are still to be
removed. H2M has said that some 15,000 cu. yds. of loam can be used for proposed
berming. It was confirmed by Dave Glass that the 6 inches of sand to reach final
subgrade on the landfill would come from the 17 -acre parcel and that an approximately 5
acre area should be designated for removal of sand (4 feet deep cut) to provide for the
• 30,000 cu. yds. of sand needed for subgrade.
•
♦ 1314\F0904101.doc(R01) -1-
F'
4. Waste Excavation Area No. 2 (Extension/Asphalt Pad)
• Dave Glass agreed that as a first approach, excavating the waste to its limits should be
attempted.
• 5. Waste Excavation Area No. 3 (Northeastern perimeter)
Tim Howell said Terry Contracting wants a change order before excavating the waste
here. Dave Glass agreed to prepare and use same unit price as Waste Excavation Area
No. 1. Igor Sikiric said he would attempt to assist in inspection of both Waste
Excavation Areas Nos. 2 and 3.
6. Type I Geotextile Status
Samples of the sand on the 17 -acre parcel have been collected by Tectonic to evaluate for
compatibility with the gas venting sand, which will determine if, technically, the Type I
Geotextile can be eliminated between these two layers of material. The NYSDEC will be
asked to approve this change assuming the materials are compatible. A change order
would also have to be prepared. Since this change could impact the percent work by
MWBE Contractors, the NYSDEC will be consulted on this issue.
7. Status of Temporary and Permanent Access Roads to 17 -Acre Parcel
Tim Howell indicated that the temporary RCA road (25 ft. wide x 1 ft. thick) is
completed, but the %2 -acre RCA pad still needs to be laid. The Permanent Access Road
will be an issue for discussion at a meeting with the Town on August 31, 2001.
8. Construction Schedule
Dave Glass indicated that the Town needs an updated construction schedule from Terry
Contracting. Tim Howell agreed to update the schedule and would have it completed by
Tuesday, September 4, 2001 assuming he can reach Bob Terry to discuss.
9. Relocation of Swale at Southeastern Perimeter
Dave Glass has forwarded the plan showing the redesign of this area.
10. Furnishing and Maintenance of Office Trailer
Terry Contracting today delivered the computer and printer . with minor items still
pending.
• 11. Excavation of Sand from 17 -Acre Pdtcel
•
See Item No. 3
♦ 13 14VO904 10 1. doc(RO 1) -2-
12. Well Abandonment Schedule
Tim Howell indicated that two wells were not able to be located in the field: Jim
Bunchuck indicated that Town personnel had uncovered these wells in the -past and Ed
• (Town Foreman) would assist along with Jim Mulligan in locating these wells. The
schedule for the well abandonment will be part of the revised overall construction
schedule to be provided by Terry.