HomeMy WebLinkAbout09/13/2001W
• TOWN OF SOUTHOLD
LANDFILL CLOSURE
MINUTES OF SEPTEMBER 13, 2001.
• PROGRESS MEETING
Attendees:
Name ' Affiliation
J. Bunchuck
Town of Southold
D. Zuhoski
Town of Southold
T. Maher*
Dvirka and Bartilucci Consulting -,Engineers.
J. Mulligan
Dvirka and Bartilucci Consulting Engineers
I. Sikiric
New York State Department of Environmental Conservation
R. Terry
Terry Contracting & Materials
T. Howell
Terry Contracting & Materials
*Via telephone
1. Comments on Minutes of August 30, 2001, Meeting
2. Comments on Minutes of September 6, 2001 Meeting
No one provided comments. Any comments must be received in writing by Friday,
September 14, 2001, as per T. Maher. If no comments are received, the minutes of these
meetings will be final.
3. Town m
CopcA
As.for the suitability of the existing compost for making vegetative cover medium, Bob
.Terry indicated that the specifications require a soil scientist to evaluate the compost. Bob also
indicated that some of the compost will have to be passed through a trommel to remove excess
plastics and also screened to one -inch minus. Just under 13,000 cy of compost is needed to
• manufacture the medium and it is estimated by Dave Zuhoski that 7,000 cy of compost now
exist. Jim Bunchuck felt the Town would have sufficient compost by the spring of 2002 since
more will be made in this fall and winter. Tom Maher, therefore, said we should assume the
Town will have an adequate quantity of compost when needed; however, Bob Terry -should
0 1314/T0913101(R02) 1
r�
develop ,contingency. plans to provide vegetative cover medium if needed to supplement the
Town's compost.
• 4. 6,500 cy of Pesticide Contaminated Soil
•
Tim Howell left the meeting to submit Terry Contracting's bid due in Town Hall today
by 10 a.m. Tim indicated upon return to the meeting that theirs was the only bid received by the
Town in the amount of $110,000. ',Since this price includes only excavating and hauling the soil
to the landfill site, Tom Maher asked Bob Terry to submit a cost for spreading and compacting
this material on the landfill. Bob -Terry agree to do so.
5. Available Remaining Space for Waste
Bob Terry said their survey by McLean Associates showed that 2.1,000 cy of space still is
available on the landfill based on D&B's revised subgrade plan less 6 inches. Most of the space
will be needed for material from Waste Excavation Areas 2 and 3, the 6,500 cy of pesticide
contaminated soil, brush and C&D.
6. Waste Excavation Area 2
Bob Terry said they may run into a problem since the excavation is so deep. Tom Maher
said that Bob must solve this problem. Immediately after the meeting, the excavation was
looked at in the presence of I. Sikiric, J. Mulligan, J. Bunchuck, D. Zuhoski, R. Terry and T.
Howell. Igor Sikiric said that,the excavation of waste under the asphalt pad could stop since the
material remaining under the asphalt was primarily concrete and brick. Approximately 20 feet of
asphalt (northeast corner) had been removed to that point. The remaining deep waste still is to
be excavated.
0 1314/1'0913101(R02) 2
• 7. Water Excavation Area 3
Jim Mulligan indicated most of the waste has been removed in this area except for some
• waste to the west and waste running north under the gas venting stockpile. Igor Sikiric, J.
Mulligan, R. Terry and T. Howell inspected this waste area after the meeting. Igor Sikiric wants
to check with his office on whether the soil remaining under the excavated waste has to be tested
for contamination before Terry can backfill.
8. Screening Sand from 17 -Acre Parcel for Barrier Protection Laver
Tom Maher said he believes we have sufficient native material for the barrier protection
layer (located behind the gas venting material stockpile), such that we may not have to screen
sand from the 17 -acre parcel. However, Tom Maher still wants a price from Bob Terry for
screening sand in case it becomes necessary to do so.
0 9. Dust Control
Bob Terry said they have installed a generator to get water from the existing well and that
this has considerably shortened the time to fill up the water tank. The water gun from the Town
is not working well. Tom Maher requested that the water gun not be used since the well water
may be contaminated and aerosols are a concern.
10. Construction Schedule/Sequence of Work
Because of the additional work to remove waste from Waste Excavation Areas 2 and 3,
Tom Maher indicated his concern to Bob Terry about schedule and how the project will be
completed on time, in particular, laying the geomembrane and barrier protection layer this year.
• Tom Maher asked Bob Terry for a detailed schedule by early next week on how this is to be
accomplished assuming completion of excavation of waste by, the end of next week (September
21). Bob Terry agreed to do so.
r1
U
01314/1'0913101(R02) 3
k!
•
U'
•
is
11. Redesign of Roads Based on Town's Decision
Tom Maher summarized the road changes to be undertaken and said D&B will begin the
redesign. He asked Jim Bunchuck to advise the Town Board that D&B will proceed with the
design work. Tom indicated that new subgrades and swale locations will be established in the
southwestern area of the landfill as a result of the road redesign.
12. M/WBE Utilization
Bob Terry has not been able to reach "Pauline" in NYSDEC to discuss anis issue. He
feels that enough material may be purchased from Holbrook Pipe that the WBE requirement may
be met. Tom Maher asked Bob Terry for a revised M/WBE plan.
13. Change Orders
Tom Maher said he has prepared a change order to accommodate the Town paying Terry
Contracting $25 per ton for handling the C&D and brush disposed at the landfill after the
baseline topographic survey was completed. Tom said no change order is necessary for the
temporary road to the 17 -acre parcel since it is not related to landfill closure, and that the cost of
the temporary road should be paid in the same manner as the temporary pad on the 17 -acre
parcel as a separate payment item. Bob Terry said that the September 12, 2001, letter from Tom
Maher to Bob Terry regarding payment/work in Waste Excavation Area 3 was sufficient and no
change order is necessary so long as he can be paid for the work.
14. Compactor
Jim Mulligan indicated that the compactor has not been used the last few days .while
under repair and that waste (primarily from Waste Excavation Area 2) is being spread in 1- to 2 -
foot lifts without the use of the compactor.' Bob Terry argued that D&B has given approval to
compact by passing the Terex Haulers over the waste and that compaction has not been a
problem both now and in the past. Tom Maher asked that Bob Terryprovide this D&B approval
0 1314/r0913101(R02) 4
® to him. Tom Maher insisted the compactor pass over the waste at least once when it is back on
the job to ensure that the deflection is 2 inches or less in order for D&B to certify adequate
• compaction, and that Bob Terry should consider renting a compactor in the meantime.
f
•
r
15. Other
- Bob Terry said he is still holding up any permanent fencing due to changes
anticipated along the road to Cox Lane.
- Bob Terry asked about the "missing" monitoring wells (northwest portion of landfill)
and Jim Bunchuck responded by giving Bob Terry a location sketch of these two
wells that Dave Glass had forwarded to Jim last week. Bob Terry indicated that the
sketch should be sufficient to locate the wells for proper abandonment.
01314/70913101(R02) 5