f TOWN OF SOUTHOLD
LANDFILL CLOSURE
MINUTES OF NOVEMBER 29, 2001
PROGRESS MEETING
Attendees:
Name Affiliation
J. Bunchuck
Town of Southold
J. Romanelli
Town of Southold '
T. Maher
Dvirka and Bartilucci Consulting Engineers
J. Mulligan
Dvirka and Bartilucci Consulting Engineers
R. Terry
Terry Contracting & Materials
T. Howell
Terry Contracting & Materials
1. Minutes of Previous (November 21, 2001) Meeting
No comments by anyone.
2. Recharge Basin #4 — Drainage Redesign
Tom Maher said he is proceeding with the preliminary design which should be
complete by the end of next week.
3. 17 -Acre Grading, Plan
Bob Terry has the plans from H2M and indicated that the bids are due in to the
Town today by 11 a.m. Bob said he did not see any problems with these plans and the
transition to the landfill grading.
4.& 5. Nonpotable Well
Tom Maher will be sending a proposal letter to Jim Bunchuck for the work
involved with the nonpotable well, fire hydrant, controls, etc. Jim Bunchuck asked if an
O 1314/F1130101(RO1) 1
:1
1 oil -water separator would be needed for washing down the Town's equipment. This
needs further consideration. Tom asked Bob Terry to submit the well driller's (Cassola)
proposal for drilling the well. Bob Terry will do so and also will move in submitting the
well permit application to NYSDEC. Tom asked Jim Mulligan to check with Cassola on
the issue of possibly "breaking suction."
6. Comments on Draft Field Order #2 and Change Orders #5, 6 and 7
Bob Terry is to submit any comments by Monday (December 3, 2001). Jim
Bunchuck will review the change orders with Jim Mulligan.
7. MBE/WBE and EEO Work Plan
Tom Maher has spoken to Ken Shider who will be approving the revised plan.
Ken indicated that the Work Plan approval would be sent to John Cushman, Town
Comptroller.
8. Subgrade on West Half of Landfill
Bob Terry said that Barry Quimet (Tectonic Engineering) is continuing with their
compaction testing. Excess contour grading material has been removed and the surveyor
(McLean) is to shoot the elevations tomorrow. Contour grading has been completed from
the siren to the north end. Bob questioned whether Barry could test fast enough, since
Bob wants to start laying the gas venting material next Monday. Tom asked Jim
Mulligan to confer with Barry on this issue. Tom asked Bob Terry to send the laboratory
results of the screened sand (for gas venting material) directly to Pete Sutherland.
01314M 130101(RO1) 2
I
Y 9. Golf Driving _Range Design
Tom Maher said he would have a plan ready in about two weeks at which time he
will review same with the Town and then with NYSDEC. Tom also will ask Bob Terry
for a cost estimate on doing the work, since Jim Bunchuck is concerned with the cost.
10. Status of Submittals
Tim Howell said he still owes certain submittals to D&B and will be addressing
them shortly.
11. Vegetative Cover Mix
Tim Howell indicated that the agronomist still is awaiting laboratory results.
12. Completion of Waste Excavation Area 3
Bob Terry indicated it will be completed today.
13. Status of Sand Screening and Testing -
Sufficient Stone for Gas Migration Control Trench
Bob Terry said he thinks he will have enough stone for the gas trenches as a result
of the sand screening on the 17 -acre parcel. If not, Bob said he will import stone from his
Riverhead facility.
14. Test Gas Vents on Eastern Portion of Landfill
Bob Terry said the two test vents will be installed today or tomorrow.
U 1314/T'1130101(RO1) 3
15. Regrading of Northeast Area to 3:1 Slope
Bob Terry said he will set up a meeting with the adjacent property owner, Mr.
Shroder. Tom Maher emphasized the need to do this soon.
16. Property Line Survey
Bob Terry said the surveyor, Young and Young, has completed the property line
survey as of today.
17. Plan for Dust Control During Winter
Bob Terry said he will have the plan by the next Progress Meeting.
18. Waste Excavation Along Eastern Boundary and
Removal of Material in Easement Area on Corrazini Property
John Romanelli said he will be meeting with Corrazini on Monday, December 3,
2001, at which time he will discuss this issue with Corrazini.
19. Soil Test Results — Need for Two Additional Contour Grading Material Sam lames
Tim Howell confirmed the need for Terry Contracting to collect these two
samples.
20. Compaction Test Results on West Half of Landfill by Tectonic
Results of compaction tests on November 28, 2001, were satisfactory. Testing by
Tectonic is continuing.
0 1314/r1130101(R01) 4
21. Work Schedule
The goal is to complete the contour grading compaction, lay the gas venting
material and compact same, and begin installing the liner on the west half of the landfill.
Bob Terry indicated he has the drainage pipe for the drainage system in the southwest
quadrant and can begin that work. Because of the temporary and permanent road in the
south, the liner may initially be installed only as far south as the siren according to Bob
Terry with Chenango having to then be remobilized to install the remaining liner after the
road work is completed.