HomeMy WebLinkAboutPBA-07/28/2014 MAILING ADDRESS:
PLANNINGBOARDOARD MEMBERS OJ.WILCENSKI �*�F yOl South 1d,Box 1179 1971
��l
Chair
OFFICE LOCATION:
WILLIAM J.CREMERS coo AMC Town Hall Annex
PIERCE R.AFFERTY G Q 54375 State Route 25
JAMES H.RICH III (cor. Main Rd. &Youngs Ave.)
MARTIN H.SIDOR l�C'M 1 1�� Southold,NY
Telephone: 631 765-1938
www.southoldtownny.gov
PLANNING BOARD OFFICE
TOWN OF SOUTHOLD
SPECIAL MEETING RECEIVED
AGENDA AUG - 1 2014
JULY 28, 2014 Southold Town Clerk
4:00 p.m.
SITE PLAN DETERMINATIONS
Greenport Harbor Brewery - This proposed Amended Site Plan is for the
renovation of three (3) existing buildings, formerly an auto dealership, into a micro-
brewery. Buildings 1 & 2 total ±13,000 sq. ft. and contain a micro-brewery
production facility; Building 3 is 2,560 sq. ft. with a 2,100 sq. ft. addition and
contains a tasting room and brew pub; Building 4 is a new 1,200 sq. ft. equipment
storage building, all on 2.89 acres in the General Business (B) Zoning District. The
property is located at 42155 Route 25, on the corner of Peconic Lane and NYS Rt.
25, Peconic. SCTM#1000-75-1-14
MAILING ADDRESS:
PLANNING BOARD MEMBERS OF S0 P.O. Box 1179
DONALD J.WILCENSKIh��� Hplo Southold,NY 11971
Chair
OFFICE LOCATION:
WILLIAM J.CREMERS Town Hall Annex
PIERCE RAFFERTY G • 54375 State Route 25
JAMES H.RICH III '�� � (cor.Main Rd. &Youngs Ave.)
MARTIN H.SIDOR l�I'oU"�y Southold, NY
'1 I' Telephone: 631 765-1938
www.southoldtow-nny.gov
PLANNING BOARD OFFICE
TOWN OF SOUTHOLD
RECEIVED
July 29, 2014
AUG - 1 2014
Mr. Richard Vandenburgh Southold Town Clerk
1405 Oak Drive
Southold, NY 11971
Re: Approval for the Proposed Site Plan for Greenport Harbor Brewery
42155 NYS Rt. 25, corner of Peconic La. & Rt. 25, Peconic
SCTM#1000-75-1-14 Zoning District: General Business (B)
Dear Mr. Vandenburgh:
The following resolutions were adopted at a Special Meeting of the Southold Town Planning
Board on July 28, 2014:
WHEREAS, this proposed Amended Site Plan is for the renovation of three (3) existing
buildings, formerly an auto dealership, into a micro-brewery. Buildings 1 & 2 total ±13,000 sq.
ft. and contain a micro-brewery production facility; Building 3 is 2,560 sq. ft. with a 2,100 sq.
ft. addition and contains a tasting room and brew pub pursuant to ZBA File#6759; Building 4
is a new 1,200 sq. ft. equipment storage building, all on 2.89 acres in the General Business
(B) Zoning District, Peconic; and
WHEREAS, on April 8, 2014, Richard Vandenburgh, owner, submitted an Amended Site Plan
Application for review; and
WHEREAS, at a Work Session held on April 21, 2014, the Planning Board reviewed the
application and accepted it as complete with further information and revisions to the Site Plan
to be done immediately; and
WHEREAS, on April 25, 2014, Richard Vandenburgh submitted the required materials and
information to the Planning Department for review; and
WHEREAS, on April 30, 2014, the Planning Board, pursuant to Southold Town Code §280-
131 C., distributed the application to the required agencies for their comments; and
Greenport Harbor Brewery Page Two July 28, 2014
WHEREAS, the Southold Town Planning Board, pursuant to State Environmental Quality
Review (SEAR) 6 NYCRR, Part 617.5, has determined that the proposed action is a Type II
Action as it falls within the following description for 6 NYCRR, Part 617.5 (c) (7) "construction
or expansion of a primary or accessory/appurtenant, non-residential structure or facility
involving less than 4,000 square feet of gross floor area and not involving a change in zoning
or a Use Variance and consistent with local land use controls, but not radio communication or
microwave transmission facilities", therefore, not subject to SEQRA review; and
WHEREAS, on May 15, 2014, the Southold Town Fire Inspector reviewed and determined
that there was adequate fire protection and emergency access for the site; and
WHEREAS, on May 15, 2014, the Southold Fire District determined there was adequate fire
protection for the site; and
WHEREAS, on May 28, 2014, the applicant submitted a revised Notice of Disapproval to the
Planning Board for a permit to construct a 1,200 sq. ft. storage building requiring an Area
Variance from the ZBA; and
WHEREAS, on June 2, 2014, a public hearing was held and subsequently closed; and
WHEREAS, on June 6, 2014, the Southold Town Architectural Review Committee reviewed
the application and provided recommendations to the Planning Board which the Board
implemented within the Site Plan design; and
WHEREAS, on June 10, 2014, the Town of Southold LWRP Coordinator reviewed the above-
referenced project and determined the proposed project to be consistent with Southold Town
LWRP policies; and
WHEREAS, on June 12, 2014, the Southold Town Engineer reviewed the above-referenced
application and required additional information and revisions to the Site Plan; and
WHEREAS, on June 19, 2014, the Southold Town Zoning Board of Appeals (ZBA) reviewed
the request for Special Exception for a drinking establishment in the General Business (B)
Zoning District. The ZBA subsequently granted the Special Exception as applied for as
recorded in their File #6759 subject to the following one (1) condition:
1. The applicant must obtain Site Plan Approval from the Southold Town Planning
Board. Failure to do so will render this Special Exception Permit null and void;
and
WHEREAS, on July 17, 2014, the New York State Department of Transportation (NYSDOT)
issued Highway Work Permit#20141039728 to "construct and permanently maintain access
& other incidental work on the N/S/O NY 25 between MMS 1591-1592 as per attached plans
and specifications. All work shall be in accordance with all current NYSDOT
standards/specifications and shall be to the satisfaction of the resident engineer" and expires
December 1, 2014; and
Greenport Harbor Brewery Page Three July 28, 2014
WHEREAS, on July 21, 2014, the Southold Town Engineer reviewed the above-referenced
application and determined that the proposed drainage meets the minimum requirements of
Chapter 236 for Storm Water Management; and
WHEREAS, at their Work Session on July 21, 2014, the Southold Town Planning Board
determined that all applicable requirements of the Site Plan Regulations, Article XXIV, §280 —
Site Plan Approval of the Town of Southold, have been met; and
WHEREAS, on July 23, 2014, the Suffolk County Department of Health Services (SCDHS)
granted Approval Reference#C10-11-0009 for a Mixed Use at 1,726 gallons per day; and
WHEREAS, on July 24, 2014, the Southold Town Zoning Board of Appeals (ZBA) reviewed
the Area Variance request for a 1,200 sq. ft. accessory storage building not located in the
rear yard in the General Business (B) Zoning District. The ZBA subsequently granted the
Area Variance as applied for as recorded in their File#6770; and
WHEREAS, on July 24, 2014, Richard Vandenburgh, owner, filed a Covenant and Restriction
with the Office of the Suffolk County Clerk as required by the Planning Board under Liber
D00012782 Page 099, stating "(1) In the event that the adjacent parcel to the east
(SCTM#1000-75-1-15.3) is developed, the Declarant shall construct a connecting sidewalk
within 12 months in order to facilitate safe pedestrian access along NYS Rt. 25. The sidewalk
shall be constructed in compliance with all pertinent New York State Department of
Transportation (NYSDOT) rules and regulations. (2) In the event that the adjacent parcel to
the east (SCTM#1000-75-1-15.3) is developed with a commercial and/or retail use, the
Declarant shall file a Cross Access Easement in order to facilitate safe interconnectivity of the
developed lots along NYS Rt. 25"; be it therefore
RESOLVED, that the Southold Town Planning Board has determined that this proposed
action is consistent with the policies of the Town of Southold Local Waterfront Revitalization
Program; and be it further
RESOLVED, that the Southold Town Planning Board grants Approval to the Site Plan
entitled "Renovations and Additions for Mmmm Beer, LLC', prepared by Robert I. Brown,
R.A., dated July 12, 2014 and issued July 14, 2014, with one condition. Upon fulfillment of
the condition listed below, the Board authorizes the Chairman to endorse the Site Plan and
the following eleven (11) plans:
1. S1 — Site Plan
2. S2 — Site Plan Landscape and Lighting
3. S3 — Site Plan Drainage and Septic System
4. T1 NYDOT— Peconic Brewery
5. T2 NYSDOT—Site Plan Curb Cut
6. Al — First Floor Plan
7. A2 — Brewpub Plan
8. A3 —West & South Elevations
9. A4 — East & North Elevations
10.A5 — Brewpub Elevations
11.Separate Photometric Plan — (sheets 1-5) dated July 17, 2014
Greenport Harbor Brewery Page Four July 28, 2014
Condition:
1. Receipt of the Final Use Certification from the Southold Town Building
Inspector.
Please also note the following requirements in the Southold Town Code relating to Site
Plans:
1. Any outdoor lighting shall be shielded so the light source is not visible from
adjacent properties and roadways. Lighting fixtures shall focus and direct the light
in such a manner as to contain the light and glare within property boundaries.
2. All storm water run-off from grading, driveways and gravel areas must be contained
on site.
3. Proposed storm water run-off containment systems must be inspected by the Town
Engineer at the time of installation. Please call the Southold Town Engineer prior to
beginning this work.
4. Approved Site Plans are valid for eighteen (18) months from the date of approval,
within which time all proposed work must be completed, unless the Planning Board
grants an extension.
5. Any changes from the Approved Site Plan shall require Planning Board approval.
6. Prior to the issuance of a Certificate of Occupancy, the Planning Board must
inspect the site to ensure it is in conformity with the Approved Site Plan, and issue
a final site inspection approval letter. Should the site be found not in conformance
with the Approved Site Plan, no Certificate of Occupancy may be issued unless the
Planning Board approves the changes to the plan.
If you have any questions regarding the above, please contact this office.
Very truly yours,
Donald J. Wilcenski
Chairman
Encl.
cc: Building Dept. w/map
Town Engineer w/map