Monthly Report Summary, May, 2014
Planning Board Applications
Currently Processing
Subdivisions: 28
Site Plans: 13
New this Month
Subdivisions: 3
Site Plans: 1
Special Exceptions: 0
Application Fees Collected: $3,000.00
Park&Playground Fees Collected: $0
Admin./Inspection Fees Collected: $0
Actions Taken at Public Meeting
Public Hearings: 4
Site Plan Decisions: 3
Subdivision Decisions: 3
Referrals for Comments from Other Boards
• Town Board Local Laws & Other Issues: 0
• ZBA: 0
LWRP Consistency Reviews: 27
SEQRA Reviews for Town Board: I
Other Projects Summary & Progress
• Comprehensive Plan Update
o Public information meetings in each hamlet on the importance of land use and
zoning to quality of life in preparation for the Land Use Chapter.
■ Greater Greenport. May 10. Nine people attended.
■ Peconic. May 12. Three people attended.
■ Mattituck & Laurel. May 17. Fifteen people attended.
■ Southold. May 22. Twenty-five people attended.
SOUTHOLD PLANNING BOARD Monthly Report Summary,March, 2014
o Information-gathering forum for real estate agents regarding their experiences
with buyers of commercial property to help us determine whether there are
businesses trying to land in Southold that cannot, and if so, if the reason was
related to land use or zoning regulations. May 29. Thirty-five people attended.
• Suffolk County Hazard Mitigation Plan. Completed Southold's part of the plan together
with Lloyd Reisenberg and Jamie Richter.
• Submitted Final Paperwork and Final Voucher in the amount of$28,054.36 for zoning
work on Plum Island with $14,027 to be reimbursed to the Town under the Planning and
Development of Town of Southold Code Revisions project(EPF LWRP Grant
C006789).
• Stormwater Management in the Town of Southold Phase II project(EPF LWRP Grant
C006878)—Requested and received an extension of grant to re-align $66,623 in state
funding to construct storm water controls in the swale off Mill Rd in Mattituck.
• New Town Code - Solar Power. Worked with Town Attorney in drafting new town code
permitting solar power facilities,prepared Planning analysis to support the new code and
conducted the environmental review(SEQR) for the local law.
• Phragmites Eradication Project. Drafted Request for Proposals, work plan and received
NYSDEC permit for phragmited eradication at Soundview Preserve.
• Drafted a list of potential zoning tools to preserve buildings owned by religious
institutions and met with Landmark Preservation Commissions to discuss.
2
Planning Board Monthly Report - Subdivisions
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Cutchogue
Baxter, William J., Jr. 102.-5-9.4 STANDARD HB CONDITIONAL 12/31/2007 The Planning Board at their
SUBDIVISION SKETCH APPROVAL March 10, 2014 public
SUBDIV meeting extended Sketch
Plan Approval to allow the
agent to complete requested
changes.
Cutchogue Business Center 83.-3-4.6 STANDARD LI CONDITIONAL 9/6/2012 The Planning Board at their
SUBDIVISION SKETCH APPROVAL 6/16/14 work session will
SUBDIV
review the revise the
preliminary road and
drainage plan and the
preliminary plat.
The Vines 73.-1-1 CONSERVATION A-C PENDING 11/14/2013 At the 4/7/14 work session
SUBDIVISION the Planning Board discussed
lot design and requested
changes be made to the
sketch plan.
East
Marion
Aries Estates 22.-3-2 STANDARD R-80 CONDITIONAL FINAL 5/31/2006 The Planning Board granted
SUBDIVISION APPROVAL SUBDIV Conditional Final Plat
Approval at their March 10,
2014 public meeting.
Monday,June 16,2014 Page 1 of 6
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Peconic Land Trust and 31.-5-6 STANDARD R-80 PENDING 7/25/2012 The Planning Board at their
Oysterponds Historical Society SUBDIVISION 6/17/13 work session
requested revisions to the
covenants and restrictions.
The applicant is waiting to
proceed with the application
until they receive approval
from the Health Department.
Treasure Island Cove, 23.-1-2.3 RESUBDIVISION R-80 PENDING 5/19/2014 The Planning Board at their
LLC/Domeluca, LLC (LOT LINE 6/16/14 work session will
MODIFICATION) review the application for
completeness.
Fishers
Island
Fishers Island Utility Company 9.-2-13.1 RESUBDIVISION R-80 PENDING 6/11/2014
& Coleman (LOT LINE
MODIFICATION)
Gordon, Estate of Albert H. 9.-7-8.2 RESUBDIVISION R-80 PENDING 5/9/2014
(LOT LINE
MODIFICATION)
Ridgway 6.-1-3 STANDARD R-80 PENDING 12/23/2013 The Planning Board at their
SUBDIVISION March 10, 2014 work session
reviewed the application for
completeness and requested
items to be submitted.
Greenport
Torell, Arthur 33.-2-10 RESUBDIVISION R-40 PENDING 4/28/2014 The Planning Board will
(LOT LINE review the application for
MODIFICATION) completeness at their June
2nd work session .
Laurel
Monday,June 16,2014 Page 2 of 6
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Harbes, Peter Lot Creation 120.-3-11.11 CONSERVATION A-C PENDING 5/21/2013 The Planning Board at their
SUBDIVISION 8/5/13 work session
requested changes be made
to the final map.
Mattituck
DiVello, John & Frances 140.-2-30 RESUBDIVISION LI &RO PENDING 7/18/2012 On January 25, 2012 the
(LOT LINE application was found
MODIFICATION) incomplete. Applicant must
submit requested revisions.
Fohrkolb, Andrew 107.-3-2 STANDARD R-40 CONDITIONAL 11/20/2012 The Planning Board at their
SUBDIVISION PRELIMINARY April 7, 2014 public meeting
APPROVAL SUBDIV granted conditional
preliminary plat approval.
Harold R. Reeve & Sons, Inc. 140.-1-6 STANDARD B PENDING 2/18/2014 The Planning Board agreed to
SUBDIVISION accept the yield of the
property and is discussing
the proposed zone change
with the applicant.
James Creek Landing 122.-3-1.4 STANDARD R-80, B CONDITIONAL 8/25/2005 The Planning Board reviewed
SUBDIVISION PRELIMINARY the application at their May
APPROVAL SUBDIV 19, 2014 work session and
requested items to be
submitted.
Koehler Family Limited 115.-10-1 STANDARD R-80 CONDITIONAL 4/6/2012 Received Conditional Sketch
Partnership SUBDIVISION SKETCH APPROVAL Plan approval on 7/1/13
SUBDIV
Monday,June 16,2014 Page 3 of 6
Hamlet Project Name Tax Map# Tye Zone State Submitted ext Steps, Comments
Neumann, James 107.4-1.3 STANDARD R-80 CONDITIONAL 7/9/2008 Waiting for applicant to
SUBDIVISION PRELIMINARY submit changes to the open
APPROVAL SUBDIV
space easement as discussed
with the applicant's agent
while concurrently, Planning
Staff is coordinating with the
Engineering Department to
finalize the drainage
easement language.
Orient
Crossroads Atlantic LLC 19.-1-14.9 CONSERVATION R-80 CONDITIONAL 10/9/2013 The Planning Board issued
SUBDIVISION SKETCH APPROVAL conditional sketch plan
SUBDIV approval at their March 10,
2014 work session.
Mazzoni, 500 Soundview 13.-2-8.2 STANDARD PENDING 3/12/2014 At the April 25th work
Drive, LLC SUBDIVISION session the Planning Board
requested revised plans to
be submitted.
The Orchards (Martocello) 27.-1-3 STANDARD R-80 CONDITIONAL 7/1/2013 The Planning Board issued
SUBDIVISION SKETCH APPROVAL conditional sketch plan
SUBDIV approval at their March 10,
2014 work session.
Peconic
Beninati, Lee & Marie 74.-3-15 STANDARD RO PENDING 5/13/2014 The Planning Board will
SUBDIVISION review the application at
their 6/16/14 work session
for completeness.
Monday,June 16,2014 Page 4 of 6
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Brantuk& Pearson 75.-6-7.2 RESUBDIVISION A-C PENDING 4/27/2011 On 10/1/13 the Planning
(LOT LINE Board sent a letter to the
MODIFICATION) applicant requiring a
covenant to prevent a
second future dock on Lot
1(SCTM1000-86-3-31) as per
the intent of the original
1985 subdivision.
Robertson and Johnson 67.-3-10 RESUBDIVISION R-40 PENDING 11/7/2012 The Planning Board at their
(LOT LINE 12/3/13 work session found
MODIFICATION) the application incomplete.
The applicant must get
Zoning Board of Appeals
approval for numerous
setback variances.
Skwara, The Estate of Joyce 86.-1-14 STANDARD R-80 CONDITIONAL 2/24/2014 The Planning Board at their
SUBDIVISION SKETCH APPROVAL 6/2/14 Public Meeting
SUBDIV granted Conditional Sketch
Plan Approval.
Southold
Bayberry Estates 2006 55.-6-35 STANDARD R-80 CONDITIONAL FINAL 3/17/2006 Conditional Final Approval
SUBDIVISION APPROVAL SUBDIV has expired and the applicant
has not fulfiled the
requested conditions.
Colony Pond 52.-5-60.3 STANDARD R-80 CONDITIONAL 6/9/2006 The Planning Board at their
SUBDIVISION PRELIMINARY 6/2/14 Public Meeting
APPROVAL SUBDIV agreed to set the Final Public
Hearing.
Stanton, Phil &Jennifer 64.-1-29 STANDARD R-40 CONDITIONAL 1/18/2012 The Planning Board at their
SUBDIVISION PRELIMINARY 6/2/14 Public Meeting
APPROVAL SUBDIV granted Conditional
Preliminary Plat Approval.
Monday,June 16,2014 Page 5 of 6
Hamlet Project Name Tax Map# Tye Zone Stags Submitted ext Steps, Comments
Sutton, Alexander&Tracy 78.-9-54 STANDARD CONDITIONAL 5/20/2008 The Planning Board at their
SUBDIVISION SKETCH APPROVAL 6/2/14 Work Session
SUBDIV
accepted the application as
complete and agreed to set
the Preliminary Plat Public
hearing.
Monday,June 16,2014 Page 6 of 6
Planning Board Monthly Report - Site Plans
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Cutchogue
Cutchogue Business Center 83.-3-4.6 AMENDED SITE LI PENDING 2/15/2013 PB to review revised site plan
Site Plan PLAN at their 6/16/14 work
session
Malon Industries, Inc. 97.-5-4.5 AMENDED SITE PENDING 8/23/2013 Revised plans and additional
Amended PLAN information has been
submitted, public hearing set
for July 7, 2014
East
Marion
The Blue Inn 31.-6-17.2 AMENDED SITE RO PENDING 7/8/2013 Public hearing June 2, 2014
PLAN held open to July 7, 2014 for
comments and additional
information
Greenport
Brewer Sterling Harbor 36.-1-1 SITE PLAN Mil PENDING 7/24/2012 Public hearing held and
closed. Referral comments
reviewed at PB's 9/23/13
work session, revised plans
forthcoming
Crescent Beach 35.-8-3.2 SITE PLAN RR PENDING 11/7/2013 revised site plan and
Condominiums Storage engineer comments to be
Facility reviewed at PB's 5/19/14
work session
Peconic Landing Amended 35.-1-25 AMENDED SITE HD PENDING 10/23/2013 Currently in SEAR process;
2013 PLAN referral review to be
conducted at PB's 7/7/14
work session
Monday,June 16,2014 Page 1 of 3
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Peconic Landing Tennis Courts 35.-1-25 AMENDED SITE HD PENDING 5/7/2014 Amended site plan has been
PLAN accepted for review, referrals
sent to interested/relevant
agencies, public hearing set
for 7/7/14
Mattituck
Goggins, William 114.-11-9.1 SITE PLAN HB PENDING 1/31/2012 Revised site plan and
RESIDENTIAL photometric plan to be
reviewed at PB's 6/16/14
work session
Price, Mary Ann 140.-2-18 SITE PLAN HB PENDING 6/27/2011 Reviewed at 10/21/13 work
session, revised site plans
forthcoming.
New
Suffolk
New Suffolk Waterfront Fund, 117.-8-18 SITE PLAN Mil PENDING 4/8/2014 Public hearing June 2, 2014
Inc. held open to July 7, 2014 for
further comments and
information.
Peconic
Greenport Harbor Brewery 75.-1-14 SITE PLAN B PENDING 4/8/2014 Referrals have been sent out
to relevant/interested
agencies; public hearing set
for June 2, 2014
Southold
Filipkowski Air, Inc. 59.-10-5 SITE PLAN LB PENDING 4/15/2014 New application submitted
4/15/14; special exception
and multiple area variances
required for the proposed
project
Monday,June 16,2014 Page 2 of 3
Hamlet Project Name Tax Map# Tye Zone Status Submitted ext Steps, Comments
Surrey Lane, LLC Amended 69.-5-18.6 AMENDED SITE A-C PENDING 8/14/2013 Public hearing closed. SEQRA
PLAN Type II. Referral review
conducted with no further
revisions. SCDHS approval
needed from the SC Board of
Review in order to receive PB
determination.
Monday,June 16,2014 Page 3 of 3