HomeMy WebLinkAboutMarion Lake Clean Up Project EstimateMarion Lake Clean Up Project Estimate
Bay Ave, East Marion
Employee Name OT hours Rate Total
Jeff S 32 53.16 $1,701.12
Tim A 32 45.11 $1,443.52
Aaron A 32 49.25 $1,576.00
Michael E 32 47.58 $1,522.56
Pete G 32 47.38 $1,516.16
Scott K 32 43.68 $1,397.76
Russell A 32 41.65 $1,332.80
Total 224 $10,489.92
Cost Equipment
Equipment Code Hours Rate Total
1 1/4 Ton Truck 8803 10 22 $220.00
(2) Dump Trucks 8720 30 35 $1,225.00
Loader Wheel 8391 10 21.5 $215.00
(2) Chain Saw 16 inch 8190 20 1.75 $35.00
Loader Wheel 8394 10 52 $520.00
Boat, Runabout 8131 24 14 $336.00
Truck, Dump 8721 15 45 $675.00
$3,226.00
Solid Waste Disposal
35 Tons C& D $70/ton $2,450
Total Estimate Completed $16,165.92