HomeMy WebLinkAbout03/2013 SOUTHOLD PLANNING BOARD
Monthly Report Summary, March, 2013
Planning Board Applications
Currently Processin~
Subdivisions: 24
Site Plans: 21
New this Month
Subdivisions: 2
Site Plans: 0
Special Exceptions: 0
Application Fees Collected: $1,000.00
Park & Playground Fees Collected: 0
Admin./Inspection Fees Collected: 0
Actions Taken at Public Meeting
Public Hearings: 3
Site Plans Decisions: 2
Subdivision Decisions: 3
Referrals for Comments from Other Boards
· Town Board Local Laws & Other Issues: 0
· ZBA: 1
LWRP Consistency Reviews: 40
SEQRA Reviews: 0
Other Projects Summary & Progress
· Comprehensive Plan Update Land Resources Section of Natural Resources &
Enviromnental Protection Chapter drafted and 2 public input meetings held.
Planning Board Monthly Report - Subdivisions
Hamlet Project Name Tax Map # Type Zone
Cutcho§ue
Baxter, William J., Jr. 102.-5-9.4 STANDARD HB
SUBDIVISION
Cutchogue Business Center 83.-3-4.6
STANDARD LI
SUBDIVISION
Sacred Heart Church & 96.-5-10 RESUBDIVISION A-C
Valerioti (LOT LINE
MODIFICATION)
East
Marion
Aries Estates 22.-3-2
STANDARD R-80
SUBDIVISION
Peconic Land Trust and 31.-5-6
Oysterponds Historical Society
STANDARD R-80
SUBDIVISION
Greenport
Conkling Point Estates
53.-4-44.1 STANDARD R-80
SUBDIVISION
Status
CONDITIONAL
SKETCH APPROVAL
SUBDIV
PENDING
PENDING
CONDITIONAL
PRELIMINARY
APPROVAL SUBDIV
PENDING
CONDITIONAL
PRELIMINARY
APPROVAL SUBDIV
Submitted
12/31/2007
9/6/2012
3/18/2013
5/31/2006
7/25/2012
11612006
Next Steps, Comments
Referrals sent to applicable
agencies- waiting for
responses to review
Application found complete,
applicant submitted changes
requested.
The Planning Board found
the application incomplete
and requested
revisions/items to be
submitted.
Applicant provided a map
meeting minimum access
requirments. Engineering
Inspector is reviewing revised
Road and Drainage Plans.
Referals were sent to all
applicable agencies. Heath
Department approval is
needed to proceed to final
approval.
Waiting for applicant to
submit changes to the Final
Plat. Heath Department
approval needed to proceed
to final approval
consideration.
Friday, May 03, 2013 Page 1 of 4
Hamlet
Mattituck
Project Name
DiVello, John & Frances
Fohrkolb, Andrew
James Creek Landing
Koehler Family Limited
Partnership
Maaratooka North, LLC
Neumann, James
Noone, Margaret
Tax Map #
140.-2-30
107.-3-2
122.-3-1.4
115.-10-1
115.-2-6
107.-1-1.3
143.-1-4.1
Type
RESUBDIVISION
(LOT LINE
MODiFiCATION)
STANDARD
SUBDIVISION
STANDARD
SUBDIVISION
STANDARD
SUBDIVISION
CONSERVATION
SUBDiViSION
STANDARD
SUBDIVISION
STANDARD
SUBDIVISION
Zone Status
LI& RO PENDING
R-40 CONDITIONAL
SKETCH APPROVAL
SUBDIV
R-80, B CONDITIONAL
PRELIMINARY
APPROVAL SUBDIV
R-80 PENDING
A-C PENDING
R-80 CONDiTiONAL
PRELIMINARY
APPROVAL SUBDIV
B and CONDITIONAL
R-40 SKETCH APPROVAL
SUBDIV
Submitted
7/18/2012
11/20/2012
8/25/2005
4/6/2012
12/6/2010
7/9/2008
1/8/2010
Next Steps, Comments
On January 25, 2012 the
application was found
incomplete. Applicant must
submit requested revisions.
The Planning Boad has issued
Sketch Plan Approval.
Waiting for the agent to
submit a Preliminary Plat
Application.
Referrals were sent to all
applicable agencies
Agent submitted revised
Maps. Planning Board will
review at the May 20, 2013
work session.
Applicant must file approved
Covenants and Restrictions
(C&Rs) with the County Clerk.
After the C&Rs have been
filed the Planning Board will
make a Sketch Plan
determination
The Planning Board is
reviewing changes made to
the Open Space Conservation
Easement.
Waiting for applicant to
submit Preliminary Plat
application
Friday, May 03, 2013 Page 2 of 4
Ham~
Orient
Peconic
Southold
Project Name
Winston, Eve
Droskoski and Sepenoski
Jameson Farms
Rand, Bight Road, LLC
Brantuk & Pearson
Robertson and Johnson
Bayberry Estates 2006
Tax Map #
105.-1-4
18.-4-7.4
13.-2-7.12
14.-2-11.4
75.-6-7.2
67.-3-10
55.-6-35
Type
STANDARD
SUBDIVISION
RESUBDIVISION
(LOT LINE
MODIFICATION
STANDARD
SUBDIVISION
RESUBDIVISION
(LOT LINE
MODIFICATION
RESUBDIVISION
(LOT LINE
MODIFICATION
RESUBDIVISION
(LOT LINE
MODIFICATION
STANDARD
SUBDIVISION
Zone Status
R-80 CONDITIONAL
SKETCH APPROVAL
SUBDIV
R-80 CONDITIONAL FINAL
APPROVAL SUBDIV
R-80 PENDING
R-40 PENDING
A-C PENDING
R-40 PENDING
R-80 CONDITIONAL FINAL
APPROVAL SUBDIV
Submitted
4/7/2009
1/26/2011
10/5/2011
7/17/2012
4/27/2011
11/7/2012
3/17/2006
Next Step% Comments
Waiting for the applicant to
submit a preliminary plat
application and address the
conditions in conditional
sketch approval.
Next Steps: Need to receive
Heath Department stamp
and Draft Deeds. Applicant
applied for an extension.
The Planning Board found
application incomplete.
Waiting for applicant to
address completeness issues.
The Planning Board found
the application incomplete.
Waiting for applicant to
address completeness issues.
Waiting for submission of
requested items.
The Planning Board found
the application incomplete.
The applicant must get
Zoning Board of Appeals
approval for numerous
setback variances.
Waiting for the applicant to
submit the requested items.
Friday, May 03, 2013 Page 3 of 4
Nam~
Project Name
Colony Pond
Southview Preserve
Tax Map #
52.-5-60.3
87.-5-21.7
Type
STANDARD
SUBDIVISION
STANDARD
SUBDiViSiON
Zone
R-80
AC
Status
CONDITIONAL
PRELIMINARY
APPROVAL SUBDJV
CONDITIONAL FINAL
APPROVAL SUBDIV
Submitted Next Steps~ Comments
6/9/2006 Waiting for agent to submit
requested items.
6/9/2005 Waiting for the applicant to
address conditions.
Stanton, Phil & Jennifer
64.-1-29
STANDARD
SUBDiViSiON
R-40
CONDITIONAL
SKETCH APPROVAL
SUBDIV
1/18/2012 Stafffound the Preliminary
Plat application incomplete.
Agent must submit road and
drainage plans as per town
code.
Friday, May 03, 2013 Page 4 of 4
Planning Board Monthly Report - Site Plans
Hamlet Project Name Tax Map# Type Zone Status
Cutcho§ue
Corazzini, Richard 2012 84.-1-32.1 SITE PLAN LI PENDING
Crystal Clear Cleaning Corp. 109.-7-9.3 SITE PLAN LB PENDING
Cutchogue Business Center
Site Plan
83.-3-4.6 SITE PLAN LI PENDING
Heritage at Cutchogue
Peconic Bay Winery 2010
102.-1-33.3 SITE PLAN
103.-1-19.12 SITE PLAN
Tikal 1 Convenience Store 97.-1-6.1
SITE PLAN
Vineyard 48 96.-4-4.3 AMENDED SITE
PLAN
Greenport
Barszczewski, Joseph Jr.
HD PENDING
B PENDING
B PENDING
A-C PENDING
53,-2-9 SITE PLAN LI PENDING
Submitted
12/17/2012
711112011
2/15/2013
3~28/2005
8/10/2010
9/26/2012
1/16/2013
6/5/2012
Nex"~ Steps, Comments
Comments from referrals
reviewed at the 4/22/13
work session. Review will
continue at the 5/6/13 work
session.
Planning Dept. waiting for
applicant to receive SCDHS
approval and submit revised
site plans.
Accepted as complete with
revisions to be made at PB's
April 8, 2013 work session.
Revised plans forthcoming.
in litigation.
Inactive applicant - follow up
letter to be sent
As of 2/14/13, application
has been withdrawn.
Amended site plan accepted
as complete with revisions to
be made at PB's March 25,
2013 work session. Referrals
to be sent out.
Applicant has applied for a
DEC tidal wetlands permit.
Revised plans forthcoming.
Friday, May 03, 2013 Page 1 of 3
Mattituck
Project Name
Brewer Yacht Yard at
Greenport
Brostar, LLC (Spanos)
Mill Creek Inn & Marina
Goggins, William
Harbes Greenhouse & Farm
Shed
Price, Mary Ann
Sherwood House Vineyards
2011
Sterling Idea Ventures
Tax Map #
36.-1-1
34.-3-22
56.-7-2
114,-11-9,1
120.-1-3
140.-2-18
100.-4-5.3
122.-6-31
Type
SITE PLAN
SITE PLAN
SITE PLAN
SITE PLAN
RESIDENTIAL
SITE PLAN
AGRICULTURAL
SITE PLAN
SITE PLAN
AGRICULTURAL
SITE PLAN
Zone
Mil
R-40
Mil
HB
A-C
HB
A-C
Status
PENDING
PENDING
PENDING
PENDING
PENDING
PENDING
PENDING
PENDING
Submitted
7/24/2012
12/26/2012
3/6/2012
1/31/2012
3/15/2013
6/27/2011
4/15/2011
9/25/2012
Next Steps, Comments
Accepted for review at the
PB's 8/27/12 work session.
PB is awaiting revised plans
to be submitted from the
applicant.
Reviewed at PB's 1/28/13
work session, application
found incomplete. Revisions
and additional information
forthcoming.
Scheduled for review of
photometric plan at PB's May
6, 2013 work session. SCDHS
approval remains
outstanding.
Applicant has to obtain a
NYSDOT Highway Work
Permit and approval from
SCDHS (currently before the
Board of review). Applicant
revised the proposal 1/25/13
prompting further review.
Application scheduled to be
reviewed for completeness at
PB's 5/6/13 work session
Inactive applicant - follow up
letter to be sent
Approval from SCDHS has
been obtained. Scheduled for
determination at PB's May 6,
2013 public meeting.
Friday, May 03, 2013 Page 2 of 3
Nam~
Peconic
Southold
Project Name
T,K, Alpha, LLC 5hopping
Center
MMMM Beer, LLC
Tax Map #
140.-2-20
75,-i-i4
New Cingular Wireless 1040 63.-1-10
Horton
Tidy Car 2000, 2009 55.-5-2.2
Type
SITE PLAN
SITE PLAN
SITE PLAN
AMENDED SITE
PLAN
Zome
HB
LI
Status
PENDING
PENDING
PENDING
PENDING
Submitted Next Steps, Comments
10/14/2010 PB is waiting for revised
plans, revised photometric
plan and further information
pursuant to April 12, 2013
letter.
12/19/2012
6/2/2010 On hold per Applicant
7/28/2000 PB reviewed application at
March 18, 2013 work session.
Further revisions required,
revised plans forthcoming.
Friday, May 03, 2013 Page 3 of 3