HomeMy WebLinkAboutRecommended Bidder Report Southold Solar PV Project212,803,,B8~,8
8663798026,
i ffo@brigh~pawer,con~
I1 Hanowr Square
21st Floor
New York, NY 10005
Recommended Bidder Report
Southold Solar PV Project
Prepared for:
Town of Southold
Prepared By:
Henry Misas
Bright Power, Inc.
11 Hanover Square, 21~t FI
New York, NY 10005
212.803.5888, x2009
June 20, 2012
£ecommenc/ed B/dc/er £eport bj/ Bright Power for the Town of ~Cout/~o/d
Disclaimer
This report contains analysis and projections that are based on the best information we have available,
however this report comes with no warranties, expressed or implied. Bright Power Inc. shall not be held
liable for any losses incurred in association with the use of this report, including but not limited to lost
profits due to actions or investments made based upon the contents herein.
6155 Cox Lane, Cutchogue, NY 2
£ecommenc/ed B/dc/er £eport /~j/ Bright Power for the Town of ~Cout/~o/d
1. Executive Summary
This report provides an overview of the competitive bid process conducted for the Solar
Photovoltaic (PV) project located at the Southold municipal landfill. In June 2012, Bright Power
delivered a technical, economic, and regulatory feasibility study that recommended a solar PV
system to be installed in the landfill.
After conversations with local and national solar developers, Bright Power determined that
there was a high level of interest from bidders to respond to a fast-track Request for Proposal
(RFP) process. On June 8th 2012, an RFP was released for a land lease agreement between the
Town and the selected bidder to design, construct and operate a large-scale solar PV project.
Bids were received by June 17th, 2012.
The following bidders responded to the RFP:
Borrego Solar
East End Renewables
Sun Edison
Jordan Energy
Brightfields
After reviewing all bids and analyzing their quality and lease payment amount, Bright Power
recommends that the Town select Sun Edison to lease the landfill land for solar development.
As a global developer of 630 solar PV projects, Sun Edison is highly qualified for performing the
installation while mitigating the risks to the landfill cap. They are able to engage with LIPA and
present a complete application to interconnect into their grid under the Feed-in Tariff program.
Finally, they are experienced in the DEC approval process for landfill post-closure modification
and have successfully constructed systems on landfills.
8155 Cox Lane, Cutchogue, NY 3
£ecommenc/ed B/dc/er £eport /:)j/ Bright Power for the Town of ~Cout/~o/d
2. Bid Analysis
The criteria Bright Power used for selecting a recommended bidder were included in the bid
specification document presented to the bidders, and listed below:
a. The annual land lease payment amount
b. The selected Contractor must abide by all requirements set forth in the
specification
c. The qualifications of the bidder in developing landfill-sited solar projects
d. The plan set forth by the contractor to minimize risk of damage to the Town's
landfill cap or any other facilities of the Town
e. The plan set forth by Contractor to minimize regulatory and legal risks associated
with the PV system installation at the landfill
f. Comprehensiveness of the bid submission package
g. Commitment and readiness to adhere to the accelerated schedule to complete
and submit a SGSGIP application and Feed-in Tariff application to LIPA
tn order to evaluate these criteria, Bright Power read and annotated all the proposals, and then
followed up individually with bidders to ask for clarifications. Bidders were also asked to provide
their "best and final" lease payment amount. A Rubric matrix was created in order to rank bid
quality, as seen in Table 1. Each of the criterion~ on the matrix was given a subjective grade
ranging from 0 to 5 based on Bright Power's assessment of the bid's strength in that area.
Individual annotations for all bids are provided in Appendix A: Full Rubric Matrix Analysis.
To allow a levelized analysis of the proposals, Bright Power requested that all bidders complete
a Bid Response Form that includes the proposed system nameplate information and cost
breakdown, as well as the lease payment amount and lease contract start date. The final
response forms are provided in Appendix B: Bid Response Forms.
The bid speciation criteria were modified {or the purposes of evaluation through a Rubric matrix.
4
fFecommenc/ed B/dc/er Report bj/ Br/ght Power for the Town of ~Cout/~o/c/
Table 1. Rubric Matrix of Bids
Criterion Borre§o East End Renewables Sun Edison Jordan Ener§¥ Bri§htfields
Lease payment $ :[33,750 $ :[40,000 $ :[50,000 $ :[50,500 $ 95,000
Amount
Financing s 3 S 4 5
In-house financing
Assured financing partner
Landfill Track Record 5 4 5 3 4
Environmental permitting
Number of landfill 12_.r. ojects succesfully ~_l..eted ~
Plan to mitigate risk of damage to landfill cap s 3 5 4 5
Description of construction methods
Plan to staff a civil engineer for pr__oject
Solar PV Track Record 4 3 5 3 4
N~mbe[ of Ero~ct~hE~ h~ be~? ~cessf~!~y d~!c)_p~d~ c)wn~d ~Ed ~perated
LIPA Interconnection Process 3 5 4 3 3
Previous experience interconnecting large-scale projects with LIPA grid
Knowledge of SGSGIP and Feed in Tariff _
Technical Soundness s 3 5 3 4
Technical Documentation
Arra~3(out
Project Management Quality and Structure s 4 5 3 4
Organizational checks and balances
Plan to hire local labor
Total 32 25 34 23 29
£ecommenc/ed B/dc/er £eport /:)? Bright Power for the Town of ~Cout/~o/d
3. Bidder Selection
The bids were evaluated according to the criteria presented at the beginning of this report.
Highlights of the evaluation process are presented below.
a. The annual land lease payment amount
Bidders presented an "all inclusive payment" in their proposals, which includes the lease
payment amount and any taxes assessed by the town. These payments will be flat throughout
the 20 year duration of the lease agreement. Bidders put in an initial offer, and Bright Power
requested all bidders to provide a "best and final" lease payment amount. Sun Edison and
Jordan Energy presented the highest lease payments at $150,000/yr and $150,500/yr
respectively.
b. The selected Contractor must abide by all requirements set forth in the specification
The bidders generally followed the instructions and requirements of the bid specification,
including submitting a full proposal by 11:5c~ pm on June 17th, 2012. Given the short timeframe
of the bid, some bidders presented a light proposal that did not include key technical
information on the proposed system. For instance, Jordan Energy did not provide an array
layout.
c. The qualifications of the bidder in developing landfill-sited solar projects
Borrego and Sun Edison clearly communicated their design-build experience and ownership of
landfill-sited solar systems. The other bidders had previous landfill experience, but were not
directly the owners and operators of the projects. Brightfields did demonstrate extensive landfill
experience because they are currently developing the most landfill solar projects and are also
direct owners of several land{ills.
d. The plan set forth by the contractor to minimize risk of damage to the Town's landfill
cap or any other facilities of the Town
Borrego and Sun Edison demonstrated knowledge of the regulatory process and the impact
studies that will be necessary to complete the process. Given their experience developing
landfill-sited projects in Massachusetts, where DEC requires a landfill engineer to be on site at
all times, they factored into their proposal the need to hire a civil engineer for this purpose.
e. The plan set forth by Contractor to minimize regulatory and legal risks associated with
the PV system installation at the landfill
Sun Edison presented a full project schedule indicating all the necessary regulatory milestones
during the development stage. Additionally, as one of the largest solar developers in the United
States, their assurance that the town will not face legal problems with the landfill is backed by
higher operational resources than their competitors and a large portfolio of large-scale,
operational solar system.
£ecommenc/ed B/dc/er £eport /~j/ Bright Power for the Town of ~Cout/~o/d
Comprehensiveness o{the bid submission package
Bright Power extensively analyzed the proposal's technical in{ormation, company management
structure, and previous work re{erences. Borrego provided a very detailed proposal, including
land{ill-specific construction methods that have been honed {rom their previous experience
developing land{ill-sited projects. They also provided the project management structure,
including the name and biography o{ the site superintendent that would be stationed locally
during construction. Sun Edison presented a detailed project schedule in a Gantt chart,
including all the regulatory permitting required.
We also evaluated technical competence and site-knowledge through the materials submitted.
East End Renewables selected RBI Solar as their installation contractor because o{ their
experience building landfill-sited systems. However, their array layout displayed a lack o{
consideration o{ the land{ill terrain as the system was placed on the northern, more complicated
section as opposed to the southern Iow-grade section. Overall, while the East End Renewables
management structure seemed well prepared to tackle such a project, their proposal lacked
many o{ the details that made their competitors stand apart.
g. Commitment and readiness to adhere to the accelerated schedule to complete and
submit SGSGIP application and Feed-in Tariff application to LIPA
Bright Power evaluated the understanding o{ the bidders in the process set {orth by LIPA in
their SGSGIP. East End Renewables, by having a developer that worked on the 32 MW Long
Island Solar Farm, seemed poised to engage with LIPA in order to success{ully interconnect the
Southold Project. Sun Edison presented a proposal that demonstrated knowledge o{ the
process, by stressing the timeline o{ the interconnection process: they kept the project under 2
MW in order to enter the project in the {aster CESIR process as opposed to the longer Study
Process necessary i{ the system is larger than 2 MW. Finally, Borrego did not exhibit a thorough
understanding o{ the interconnection process, as they presented objections related to the non-
negotiable terms o{ the LIPA PPA and also were not in-tune with the di{{erent LIPA project size
categories and associated time{tames.
4. Conclusion
The bidder that best meets the criteria set {orth {or the Southold Land{ill Solar Project is Sun
Edison. They proposed one o{ the highest: lease payment coupled with a high quality technical
proposal. They have an impressive overall track record in Solar PV systems as well as experience
constructing land{ill-sited PV systems. Bright Power is confident the recommended bidder can
meet the deadlines and regulatory requirements set {orth in the RFP and that the project will
provide the Town with significant long-term passive income.
2 Another bidder, Jordan Energy, proposed a slightly higher lease payment but presented a weaker
technical proposal.
f~ecommenc/ed B/dc/er Report bj/ Br/ght Power for the Town of ~Cout/~o/c/
Appendix A: Full Rubric Matrix Analysis
Criterion IBorrego East End Renewables Sun Edison
Lease payment , $ 133,7s0 , $ 140,000 $ 150,000
Established partnerships with large
Financing In-House 5 Various financing relationships 3 financing agents
2 completed, others in construction and 2 completed, management team
Landfill Track Record development 5 1 completed by EPC 4 experience
Plan to mitigate risk of damage Presented landfill-specific construction Will source local landfill engineers and
to landfill cap methods, theywill hire KLMA 5 Proposal light on details. 3 staff a project civil engineer
Solar PV Track Record ,loso projects nationally 4 Newly started company 3 630 PV systems constructed globally
LIPA Interconnection Process ,No significant experience .3 Developer of Long Island Solar Farm 5 Other FiT projects in development
Layout was not optimal (only north
Technical Soundness Optimal use of terrain 5 terrain used) 3 Optimal use of terrain
Project Management Quality In house EPCteam, local electrical and Experience developing local large In house EPCteam, local electrical
and Structure construction labor 5 scale project 4 and construction labor
Criterion Jordan Ene r_~y Bri.~.htfields _
Lease payment $ 1so, soo $ 95,000
Financing VCAP Financial 4 Clean Focus 5
17 solar projects developed,
Landfil~ Track Record Management Team Experience 3 7 landfills owned or operated 4
Plan to mitigate risk of damage Will hire AMEC for environmental work,
to landfill cap Will hire TRC for environmental work 4 have extensive landfill operation experience 5
Solar PV Track Record Newly started company 3 40 MW total ground mount projects 4
LiPA Interconnection Process No significant experience 3 No significant experience 3
Technical Soundness No layout provided 3 No outstanding advantage 4
Project Management Quality
and Structure No outstanding advantage 4 No outstanding advantage 4
£ecommenc/ed B/dc/er £eport /3), Bright Power for the Town of ~Cout/~o/d
Appendix B: Bid Response Forms
9
£ecommencJed B/dc/er £eport /:)j/ Bright Power for the Town of ~Cout/so/c/
Henr;,,
~.s a fetlew up te oor submission last night and our discussions today, Monday, June 18th Borrege Solar SFstems is pleased to mai(e a revised lease offer to Bright Power
end the Town el SoutheI~.
Replace Item #7, page 9 from the former proposal submitted on 6/17 2912 with the following clauses:
7, LAND LEASE CONTRACT
Berrege Solar is pleased to offer the following payment option:
$50,000 S133,750 S 2,675,000
1. Per the RFP, the lease payment does not escalate, and it includes all present and future real and personal properr~ tax payments
All ot~er terms a~d cordilleras a~d designs remak~ ~ke same,
&long with this more a~ractive lease rate, please consider Borrego's qualifications, completed lanrJill projects, and demonstrated approach to successfLdty designing,
constructing and operating a solar system on a landfill
Thank you!
Dsvi¢ M Sugrue
Senior Projed Developer
Borrego Solar Systems, [nc
23g Sea Pice Drive
Egg Harbor Township, HJ 08234
Phone; 716-341-2824
Fax: ~888~, 843-6778
10
£ecommenc/ed B/dc/er £eport /~j/ Bright Power for the Town of ~Cout/~o/d
11
£ecommencYed B/dc/er £eport /3j/ Bright Power for the Town of Sout/~o/d
12
£ecommenc/ed B/dc/er £eport /~? Bright Power for the Town of Southo/d
L 7M%~
13
£ecommenc/ed B/dc/er £eport bj/ Bright Power for the Town of ~Cout/?o/d
14