Loading...
HomeMy WebLinkAbout11/02/2011 TOWN OF SOUTHOLD MS4 COMPLIANCE COMMITTEE Minutes of November 2, 20tl Present: Trustee John Bredemeyer, Jennifer Andaloro, ATA, Jamie Richter, Engineering Inspector, John Sepenoski, Technical Coordinator II, and Mark Terry, Principal Planner. Approved minutes from October 5, 2011 meeting. The Committee will file its minutes with the Town Clerk's Office. II. Draft MS4 Local Law - the additional changes were reviewed by the Committee and the Committee will place the Local Law on the Town Board Agenda for 11/9/11 for a referral to the Code Committee. Additionally, once the law is referred to Code Committee, it will be circulated to the Building Department, Planning Department, Zoning Board of Appeals, and Board of Trustees. III. Updates: Potential Illicit Discharge reported by the CAC regarding the Moore property. The Committee noted that the property is presently under review by the ZBA and will undergo additional Trustee review. Jamie will write a Memo to the ZBA pointing out that the property has a potential illicit discharge and will make recommendations, including that the ZBA should condition any variance on the submission of an SWPPP. Illicit Discharge Detection Training - is continuing and additional training may be required once the MS4 Local Law is adopted by the Town Board. Certified Contractors - prior to the enactment of the MS4 Local Law which requires certified contractors, the Town will implement a policy that an applicant for a building permit cannot receive an approval until documentation regarding a contractor's MS4 certification is supplied to the Building Department. Jamie will draft a sign to post in the Building Department and new attachments to building permit application. Additionally, Jamie will meet with Mike Verity to discuss and verify the process, as well as notifying contractors when certification training is offered and where. IV. d. Grant Update (Mark Terry): EFC Green Infrastructure Grant Program (GIGP3) application status. The grant application has been submitted for $460,000 in MS4/Green infrastructure projects including projects with biofiltration, infiltration basins. However, the Mattituck Creek project was not included in the grant because the Town does not own the property. ii. Hashamomuck Sub-Watershed (C303426) - NYSDEC Funding - This grant has already been awarded to the Town. The Committee is hopeful that the projects in this grant will go out to bid in early December. Jamie will prepare the RFP. The Town will have to coordinate an on-site meeting with the DEC and DEC is willing to extend funding. iii. Developing Priority Impaired Waterbody and Sub-watershed Management Plans - SGA 22(Goose/-l'own/Jockey Creeks) and SGA 26 (Richmond Creek) - the Town is ahead of schedule on these grants. Review of NYSDEC's modifications to the General Permit: a. The DEC has extended the retrofit deadline to September 30, 2012. b. Corrected typographical errors. The DEC has noticed the addition of 4 waterbodies in Southold Town, namely, Spring Pond, Wickham Creek, Mud Creek and East Creek. d. The DEC has also added a pollutant of concern to Maratooka Lake. Generally - the Town must assess waterbodies according to DEC models and every assessment must be approved by the DEC. The Town employees must become conversant in the DEC models. Additionally, John Sepenoski will obtain approval for multiple employees (Jamie, Mark and John) to attend meetings related to required modeling. Next meeting - the next meeting should be scheduled for the week of November 28, 2011.