HomeMy WebLinkAbout10/28/2004Town of Southold
Hamlet Study
MEETING MINUTES
CUTCHOGUE HAMLET STAKEHOLDERS MEETING
October 28, 2004
Stakeholders present: Tom McAdam, Gwen Schroeder and Jane Minerva.
Non-stakeholders present: Pat Moore, Valerie Scopaz, Tom Wickham, Patrick Cleary and
Phillip Beltz. The meeting commenced at 6:10 p.m.
Hamlet Center BoundarF: After considerable discussion, consensus was not reached in
delineating a firm boundary. Participants felt a need to discuss the halo concept before
establishing a boundary for some properties within the hamlet center could possibly be
better suited for residential development within the halo zone.
HALO Zone: Hamlet Locus (HALO) floating zones are those areas that support
residential development outside of hamlet centers. Handouts were provided that
described: HALO zone background and purpose, standards and requirements.
Stakeholders had difficulty defining the HALO zones and believed it would be easier if
they knew exactly how many people and housing units Cutchogue would most probably
need to accommodate, based on the build-out analysis. This information is not readily
available but could possibly be provided in the future.
Hamlet Center Image Elements: A Cutchogue Hamlet Image Map was provided along
with descriptions of the five hamlet forms: paths, edges, districts, nodes and landmarks.
Sustainability Principles: A handout was provided however this was not discussed. It
was suggested that group members discuss this amongst themselves at their next meeting.
Hamlet Center Issues: Patrick provided the group with a list of "issues" (i.e. strengths
and weaknesses) that were recorded from previous meetings.
Hamlet Center Goals: The group began (but did not complete) those hamlet center
issues listed above that it wishes to: preserve, add, remove orl)rohibit. This exercise to
build a hamlet center goal matrix will also be completed when the group holds its next
meeting.
Next Meeting Items: The group will reconvene within the next several weeks seeking
greater participation from additional stakeholders. They will establish hamlet boundaries
and complete exercises as noted in the minutes.
The meeting adjourned at 8:10 pm.