HomeMy WebLinkAbout36737-Z Notes
1) Framing to be a Min. retention of .25 #/Cu
Ft ACQ 2x8,s @12' ❑C
2) Steps are to be 2x12 with 7' drop max.
3) Use solid blocking at mid-point of all joist
spans i
4) Footings as noted, use 3000 psi concrete,
at least 1' above grade and sloped to
provide drainage
5) Use 2 ea. 1/2' hot dipped galvanized
2.• carriage bolts on all base frame
connections
6) Railing height as noted, with 4' max baluster
spacing. See guardrail detail. Qr
7) Provide continuous handrails on each side of
ramps
8) All base girders akze. 2ea.-2x'19
g
9) Provide Simpson Strong Ties for the following
joint connections; as required
ABU66 - 6x6 post to footing - use 12-16d nails
ABU44 - 4x4 post to footing - use 12-16d nails
H3 - joist to girder - use 8-8d nails
DBT1 - decking to girder - use 1-10d nail
DRT8 - railing to post - use 2-#8 galy. screws
10) Provide 2x6 decking throughout
a 2.8-3 pl as
Unity Baptist Church
Stair & handicapped
ICC/�NSr 1117 access ramp details
�
a3
l �
4X4 posts ,
6' ❑C max.
an�rete-.x, nsert Notes
—
1) Framing to be a min, retention of .25 #/Cu
12• Dla.I\ Ft ACO 2x8,s @12' ❑C
2) Steps are to be 2x12 with 7' drop max.
2-1/2' carriage
bolts ea. 3) Use solid blocking at raid-point of all joist
spans
Cannot pass
4' spheres footing Detail 4) Footings as noted, use 3000 psi concrete,
cannot pass at least 1' above grade and sloped to
6' spheres provide drainage
3' landing 5) Use 2 ea. 1/2' hot dipped galvanized
29, carriage bolts on all base frame
g.
connections
6) Railing height as noted, with 4' max baluster
spacing. See guardrail detail.
Guardrail Detail
Existing stair IaryYing 7) Provide continuous handrails on each side of
(36' above 9r.d. - ramps..,
footings as per d tail- //
I
12 rep;.eddd---yyy 8) All base girders n.re. 2ea.-2x10
x8 a 12• Dc 9) Provide Simpson Strong Ties for the following
joint connections as required
Existing step
ABU66 - 6x6 post to footing - use 12-1 d Halls
ABU44 - 4x4 post to footing - use 12-16d nails
H3 - joist to girder - use 8-8d nails
�— ---- ____ DBT1 - decking to girder - use 1-10d nail
DRT8 - railing to post - use 2-#8 galy. screws
__-- ---- 10) Provide 2x6 decking throughout
ea-2x8 ea 2x8-3 pl
2ea-2x1 I d
See stair rail aetal
xlsting sidewalks VI
iPlan View
Framing Details
Unity Baptist Church
Stair & handicapped
access ramp details