WORK SESSION AGENDA
SOUTHOLD TOWN PLANNING BOARD
Monday, February 11, 2008 at 4:30 p.m.
4:30 p.m.
Review Public Meeting Agenda
4:45 p.m.
Site Plans and Subdivisions
Site Plans:
• Warex Terminals SCTM#: 1000-142-1-27
Location: 9945 Main Road, Mattituck
Action: Review and comment on NPV draft report & discuss comments to ZBA.
Status: Pending a SEQRA determination.
Recommendations: PB accepts SEQRA review, outlines ZBA comments.
• Seifert Construction SCTM#: 1000-141-3-44
Location: 11780 Sound Avenue, Mattituck
Action: SP status update and review of Building Inspector certification.
Status: PB will exempt under SEQRA as a Type II NYSCRR part 617.5 (7) and be
setting the Public hearing at the 2/11/08 meeting for 3/10/08.
Recommendations: PB accepts the certification as submitted and sets the hearing pending
receipt of LWRP, TE comments, MFD and SC Planning Department
comments.
Attachments: A-1
• Brewers Yacht Yard Pavilion SCTM#: 1000-43-3-2
Location: 500 Sandy Beach Road, Greenport
Action: SP status update and review of Building Inspector certification.
Status: PB will be setting the Public hearing at the 2/11/08 meeting for 3/10/08.
Recommendations: PB accepts the certification as submitted and sets the hearing pending
receipt of TE final comments and agent submitting a minimum of 6 copies
of the revised site plan.
Attachments: B-1
• Purita Winery SCTM#: 1000-51-3-4.3
Location: 19110 Sound Avenue, Southold
Action: SP status update and review of Building Inspector certification.
Status: PB will issuing a Negative Dec as a SEQRA determination and be setting
the Public hearing at the 2/11/08 meeting for 3/10/08.
Recommendations: PB accepts the certification as submitted, issues the Neg. Dec and sets the
hearing pending receipt of the comments from LWRP, TE and a minimum
of 5 revised site plans.
Attachments: C-1
• Albertson Marine SCTM#: 1000-56-3-13.4
Location: 61205 Main Road, Southold
Action: Review site plan as requested for final sign off to issue a certificate of
occupancy. Review verbal comments of site visit per staff.
Status: Pending a PB final letter.
Recommendations: PB considers final sign off letter.