Loading...
HomeMy WebLinkAboutUndergrounding-Conversion of Select LI Lighting Co Overhead Electric Lines by NYS Dept of Public Service Mar-93 ~~~ _.i~)~Mi:r).\t:~;;';;;i >, . . 'ARNOLD R. PUJl/AM . New York State ", Department of Public Service,. . " ,~ - . . , " . Undergrounding_., , Conversion of Select Long Island Lighting Company Overhead Electric Lines A Study to Assess the Cost Effectiveness Of Undergrounding's Potential to Mitigate LILCO Service Interruptions Caused By Catastrophic Storms ;. ' ,- '. . .~.. ' . Staff Report ",F MAY 0 6 1998 Southold Town . Planning Board .. , . UNDERGROUNDING CONVERSION OF SELECT LONG ISLAND LIGHTING COMPANY OVERHEAD ELECTRIC LINES A STUDY TO ASSESS THE COST EFFECTIVENESS OF UNDERGROUNDING'S POTENTIAL TO MITIGATE L1LCO SERVICE INTERRUPTIONS CAUSED BY CATASTROPHIC STORMS NEW YORK STATE DEPARTMENT OF PUBLIC SERVICE STAFF REPORT MARCH 1993 ~ TABLE OF CONTENTS Foreword Executive Summary Introduction L1LCO Service Territory History of Commission Undergrounding Proceedings Selection of Undergrounding Scenarios Substation Circuit Undergrounding Design Assumptions Substation Circuit Undergrounding Methodology - Cost Estimate - Rate Impact Costs to Underground and Resulting Rate Impacts - Indian Head Substation - Buell Substation - Amagansett to Montauk Transmission Line - Undergrounding All L1LCO Facilities Undergrounding Constraints and Benefits Conclusion Appendix A: Input Data for Strategic Financial Planning Model Appendix B: Rate Impact Worksheets Appendix C: Indian Head Worksheets Appendix D: Buell Worksheets ~ PAG: 2 3 11 13 15 18 24 26 28 39 46 FOREWORD This report on the study group's findings is brief and written without the extensive use of technical jargon. Where possible, we have included photographs of various equipment and locations to provide better references and clearer explanations. Since the subject of undergrounding is multi-faceted, we have tried to include only the areas pertinent to our study. However, we are aware that this report may foster additional questions and the study team, as well as the support team assembled by L1LCO, is prepared to give a presentation on our efforts and hopefully answer any outstanding questions. This presentation will include a discussion of the types of analyses conducted by both staff and L1LCO. Below are the members of the study team and the L1LCO support team: Study Team Communications Division: Ambrose Hock Consumer Services Division: Policy & Compliance - Raj Addepalli Office of Energy Efficiency and the Environment: Environmental Compliance and Operations - Arnold Putnam Energy and Water Division: Power Rates & Valuation - Harold Glasser Power System Operations - Alan Elberfeld - Project Leader Power System Operations - Michael Worden LILCO Support Team Facilities Planning Department: Design & Reliability Division - Ronald Ammon Area Planning Division - Frederick Albinus Electric Lines Department: Bruce Cocks Electrical Engineering Department: Thomas Spatz We also wish to acknowledge the contribution of the Office of Accounting and Finance for providing the forecast capital structure input assumptions required to finance the undergrounding scenarios. J 2 EXECUTIVE SUMMARY Introduction Catastrophic storms during 1991, including the March Ice Storm and Hurricane Bob, caused three-quarters of a million electric customers in New York State to lose service for significant periods of time. These storms impacted four of the seven major electric utilities. Catastrophic storms include hurricanes and ice storms that impact service to numerous customers for extended periods of time. Hurricane Bob, which ravaged Long Island on August 19, 1991, resulted in renewed cries for undergrounding all, or portions of, L1LCO's overhead electric facilities. The Consumer Protection Board, supported by the Office of the Attorney General, petitioned the Public Service Commission to analyze the costs and benefits of undergrounding vulnerable areas of L1LCO's electric service territory. In early 1992, commissioners, including the Chairman, asked staff to conduct such a study. In March 1992 the former Power Division, now part of the Energy and Water Division, took the lead in conducting a study to assess undergrounding's potential to mitigate L1LCO service interruptions caused by catastrophic storms. We chose L1LCO for the underground study because of its vulnerability to both hurricanes and ice storms. Staff from the Communications Division, the Consumer Services Division, and the Office of Energy Efficiency and the Environment, joined with the Power Division to form the study group. L1LCO formed a parallel group to assist and facilitate the study. At the same time, a study was undertaken to assess whether enhanced tree trimming by utilities would increase service reliability during catastrophic storms. That report is issued as a companion to this report. This study was conducted independent of the ongoing line extension case (Cases 29389/92-M-0607), although most of the study team members are involved in that proceeding. In contrast to the potentially more expansive coverage of conversion from overhead to underground anticipated for the generic line extension case, this study was limited in scope to an evaluation of undergrounding as a means of mitigating catastrophic storm-inflicted damage to L1LCO's distribution system. Secondly,this study had begun and was nearly completed before consideration of conversion was addressed in the generic proceeding. Further information about that proceeding is included later in this summary . Background In developing the workplan for the underground study, the primary concern was on what could be done to prevent damage to overhead electric facilities during catastrophic storms, and the focus of this study was L1LCO's ~ 3 . ,"~,....__',..._._.Ac...'.__..'.>_.'-..,.,,~.,-,-,..._.'.'.,.".. _.....,..-._..'-.......H.~.,.~..~.."...,~,.....~~1..'... . --.., ...~..~..-..,'_..."... ,__",",.,,-,.._,.,..,.,.._..._M'~'~ - :. .- ;:.;.;;:::.---.;-- 45,000 cable miles of overhead distribution lines'. As a practical matter, if electric utilities were to undertake a program to underground existing overhead facilities, the disposition of telephone and cable facilities would have to be addressed. It was recognized that telephone and cable facilities coexist on poles with the electric system, but in order to keep the scope of the study to a reasonable size, it was decided to focus on electric facilities. Approximately 95,000 of L1LCO's customers are served by underground facilities, as contrasted to 907,000 being served by overhead facilities. However, new construction for L1LCO's distribution system shows an increase in the installation of underground lines. In 1990-1991 L1LCO connected 4,997 new customers served by overhead lines and 3,796 new customers served by underground lines. In terms of new line construction, 1990-1991 saw 45 cable miles of new overhead lines and 186 cable miles of new underground lines. L1LCO has 45,000 cable miles of overhead distribution and 11,000 cable miles of underground distribution. Approach The initial premise of the study was to locate specific areas of the island that were most prone to damage from catastrophic storms. L1LCO provided damage patterns on catastrophic storms covering a 20-year period. The damage location data available from L1LCO is somewhat broad-based, because the focus following catastrophic storms is restoration, not data collection. Nonetheless, L1LCO still has the most comprehensive data available among New York State utilities. Unfortunately, this data revealed that no particular area consistently experienced storm damage. This is due to the fact that the landfall of the eye of the hurricane is the deciding factor in where the most severe damage will occur. There is no way to determine where landfall will occur on a statistical basis with the data available. Hurricane winds blow counter- clockwise with the highest wind speeds occurring in the northeast quadrant. If the eye of the storm has a landfall near the center of the island, the south shore bears the brunt of the storm. If the eye passes east of the island, the easternmost part of the north shore becomes the hardest hit area. Damage from ice storms, on the other hand, impacts the north-west to north-central part of the island. Finally, the One Hundred- Year Storm of December 11 and 12, 1992, caused the most severe damage in the north and south coastal areas of the western portion of the Island. The study group then examined whether undergrounding distribution lines along the shorelines of the island, which one would expect to be more susceptible to storm damage, would provide the looked-for litmus test. ~ The study only addresses undergrounding of electric lines; telephone, cable television, and street lighting facilities are assumed to remain overhead on existing poles. There are more than one-half million L1LCO and New York Telephone poles on the island, none of which are jointly owned. Around 84 percent of these poles contain both telephone and electric facilities. Cable television facilities are on approximately 75 percent of the poles. 4 Difficulties arose with this approach in that circuits meander north, south, east, and west and appropriate cut-off points for undergrounding were not .available. Staff also looked at whether undergrounding to improve reliability could be combined with road widening projects or other rebuilding programs. Although the cost of undergrounding portions of circuits involved with these projects would be partially offset by the avoided cost of moving the existing overhead lines to the outer limits of the roadway, the cost differential, depending on type and location of construction, remains three to five times as great. In addition, most of these projects involve only small segments of circuits. Thus, customers served by the underground circuit portion would be vulnerable to interruptions from the remaining overhead circuit segments. For these reasons, staff does not find this to be a viable alternative. Ultimately, staff investigated four scenarios in some depth. The first two scenarios evaluated the premise of undergrounding all circuits emanating from two particular substations. After analyzing a number of substations, we selected the Indian Head Substation located near Smithtown and the Buell Substation located in East Hampton for the first two undergrounding scenarios. In terms of size and composition of customers, these substations were considered representative of L1LCQ's 150 major substations. Indian Head, serving almost 14,000 customers in the northern part of Western Suffolk, is in an area which could be impacted by both hurricanes and ice storms. Indian Head also has a relatively high population density and serves both residential and light commercial/industrial customers. The Buell Substation serves almost 10,000 customers on the south fork of the Island. Buell serves a predominantly residential customer load. The third undergrounding scenario chosen by the study group was a project that is currently planned by L1LCQ to begin in 1993. This project involves undergrounding almost 12 miles of overhead transmission lines that run from Amagansett to Montauk--the easternmost portion of the Island's south. fork. This project is being undertaken for a variety of reasons, including aesthetics, environmental concerns, reliability, public relations, and operating considerations. The last scenario chosen by the study group entailed updating an earlier L1LCQ study that assessed the cost of undergrounding L1LCQ's entire system. The update also included select, partial undergrounding scenarios. Staff used these partial scenarios to augment the substation scenarios to provide a wide range of possible options. Factors and Assumptions Rate impacts2 were developed for an 11-year study period (1993-2003) 2 The additional costs of undergrounding telephone, cable television, and street lighting services are not included in the cost projections. ~ 5 ......_L",._,.,...,...__.,..,_...,..,"~....................___.~_...;.....~.......;.;....i7"-'-~'~ ,., 'O:;T;.-';.-:;;";' .. '_"'__".,..,."~~_"e'~_."'_ """."" which is the output limit of the Strategic Financial Planning model used in the analysis. Since the estimated installation period for undergrounding substation feeders is 10 years, the model was compatible. However, since the installation period for the entire undergrounding scenario is 25 years, we can only project rate impacts for the first 11 years of installation. Thus, additional monthly increases would occur for the remaining 14 years of the installation period. The Base Case used in the study reflects increases due to the L1LCO Ratemaking and Performance Plan, as modified in Opinion No. 91-25 (Case 91- E-1185). The costs individual customers would incur for service laterals in order to connect to L1LCO's secondary distribution system are included in the total costs indicated in this undergrounding study. Normally, the customer/builder would pay an electrician several hundred dollars to connect the service lateral to the meter. For purposes of this study, mainly because of the magnitude of the underground costs that would ultimately be borne by the customer, we thought it useful to present a complete package of the cost/rate impact that the ratepayers would bear. For an underground program of this magnitude, staff assumed that L1LCO would utilize contractors whose price includes certified electricians who are licensed to connect the service lateral to the meter. Hence, the contractor's price would be a complete package deal for connecting service laterals up to the electric meter. The consequences of effecting early retirement of its overhead distribution plant due to installation of replacement underground plant may require special accounting/financing treatment. There may be a need for rapid amortization of the loss in order to be consistent with accepted accounting practice. An amortization period shorter than the normal period during which the overhead plant would otherwise be depreciated will increase the utility's revenue requirements, thus resulting in the need for still further increases to customers' bills. Summary of Results The cost to underground all distribution lines emanating from each substation approximated $150 million. Based on the number of customers served, the rate impact to customers within the substation service territory would be to raise the average monthly residential rate between $1 29 and $1 80 depending on the substation. In contrast, undergrounding 12 miles of east-end transmission line will cost ratepayers $10.6 million. The principle difference in cost between undergrounding transmission lines as opposed to distribution lines is that the former consists of point-to-point, Le., substation-to-substation cable terminations as opposed to the myriad of distribution connections required for each household service lateral. Another factor keeping the cost of the east-end transmission line relatively low is that it consists of direct-buried cable that is ~ plowed-in along the shoulder of Montauk Highway-:-'There are few bends, trees, and crossings along the proposed cable route. 6 L1LCO estimates the cost to underground its entire distribution system to be $20 billion. This estimate appeared reasonable to staff and WaS used in our rate impact calculations. All of the costs are predicated on the latest underground design standards currently employed by L1LCO and a 25-year installation period. This criteria basically employs "looped" underground cables, which greatly enhance underground system service reliability. The rate impact based on $20 billion would be to raise the average monthly residential rate by $108, from $83 to $191 during the first 11 years, or an average yearly increase of about 7.9 percent. Over the 25 years required to underground the system, an increase in rates of 569 percent solely due to undergrounding would be realized. The rate impact on the other service classes would also be about 569 percent, exclusive of additional increases due to all other causes. The study team also examined undergrounding select components of the distribution system, as L1LCO did in its 1978 study. The options presented focused on rear lot facilities, which sustain significant damage during catastrophic storms, and are among the last facilities to be repaired. This approach is more balanced than the substation approach because it benefits a wider customer group. However, it would not benefit all customers and would not eliminate all interruptions. The options presented range in cost from $689 million to just over $1.9 billion, with an annual rate impact on the order of 4.8 to 8.4 percent over each of the first 11 years of installation. There are cost savings to lILCQ associated with undergrounding, primarily reduced tree trimming, storm restoration, and storm insurance premium costs. These savings would be on the order of $17 million to $35 million per year for conversion of the entire distribution system. There are also secondary impacts, which the study team did not quantify, that would include business losses and real property damage. Under a 25-year total undergrounding plan, lILCO would need to finance at least $0.8 billion per year. Our finance personnel advise that a construction program of this magnitude would require L1LCO to continually go to the capital market. They advise that such a program would undoubtedly cause cash flow problems for the company which could adversely affect the rate at which L1LCO could access the capital market, or in a worse case scenario, impede its access to the capital markets. Other Effects of Undergrounding There are pros and cons to underground lines regarding reliability during normal operating conditions. Although overhead lines are not inherently unreliable, underground lines on lILCO's system are about five times more reliable on a composite basis. This basis is composed of the recently adopted Commission reliability standards that address both frequency and duration of service interruptions. The frequency of interruptions to L1LCQ's overhead system is roughly 10 times greater than that of underground. However, it takes twice as long to return underground lines to service as it does overhead lines. Although there are not many negatives associated with underground J 7 ~. ~ -~ ,-.". ,..~" .-~--..--.~... -. reliability, the service life of underground cables on L1LCQ's system has generally been less than 30 years, and replacement costs are' 3 to 5 times greater than overhead replacement costs. Overhead cable normally has a service life in excess of 50 years. Studies in Other Jurisdictions In a June 1988 study by R. W. Beck and Associates, entitled Toronto Hydro Study of Distribution Options, undergrounding was examined as an option for replacing Toronto Hydro's obsolete 4 kV overhead distribution system in the City of Toronto. The study estimated the cost of an all underground system to be $2.038 billion, compared to $295 million for an all overhead 13.8 kV system. Toronto Hydro has approximately 217,500 customers. An estimated 80 percent are served by the obsolete 4 kV system. Toronto Hydro decided to install a hybrid overhead/underground system, with all primary wires and transformers underground at a 1988 cost of $854 million. As of the end of 1991, the cost projection had escalated to $1.5 billion. Toronto Hydro has since reduced the scope of the undergrounding program due to public outcries over the cost of the endeavor. We also reviewed two recent undergrounding studies from other states. The first study, conducted by the Florida Public Service Commission, was released in December 1991. The study entitled, Report On Cost-Effectiveness of Underground Electric Distribution Facilities, concluded that undergrounding of existing facilities was not cost-effective. The second study, conducted by City Public Service, a San Antonio, Texas, utility was entitled, Feasibility Study Conversion to a Total Underground System. The cost to underground City Public Service's system was $16.9 billion; the company decided against undergrounding and said: Conversion to an underground system would require additional revenues with resultant rate increases, thus placing the financial burden upon ratepayers. Current Under grounding Proceeding The current line extension case is studying the potential of undergrounding under various scenarios. In fact, the Commission, on September 15, 1992, issued proposed rules for comment in Case 92-M-0607 that provide for a Visually Significant Resources (VSR) undergrounding program. This program applies to the new construction of distribution lines, service lines, and appurtenant facilities on public and private land in VSRs. The program will remain in effect for a period of five years after its effective date. Under the proposed annual program, L1LCO would be required to allocate at least $2.4 million (subject to adjustment for inflation) to a VSR undergrounding J fund and would be obligated to spend such amounts on the cost of installing 8 such new construction underground. Any unspent portion of L1LCQ's maximum obligation in a given year would be carried over to the next year. The VSR program would be evaluated by the Commission after the program has been in effect for two years and L1LCQ would be required to provide details of its experience as the staff and/or Commission may request. In addition, staff is involved in Case 29389, Proceeding on Motion of the Commission as to the Regulations Regarding the Installation of Distribution Lines, Service Lines, and Appurtenant Facilities by Electric and Telephone Contractors and Municipalities. Proposals before the Administrative Law Judge include conversion of lines from overhead to underground within VSRs, as well as the conversion of all overhead facilities. Staff found no significant overlap between distribution facilities located in VSRs and ones in areas that are particularly vulnerable to catastrophic storm damage. Conclusion and Recommendations The results of this study point to excessive costs, when compared to reliability benefits, as being the prohibitive factor precluding the large scale undergrounding of existing overhead facilities for the purpose of improving reliability during catastrophic storms. :stuntl ollce he average L1LCQ customer loses service only once every seven .~years due to these catastrophic storms. As explained previously, there is no data that indicates which customers would lose service due to the random damage from these storms. However, this study also shows that for specific situations, Le., the Amagansett to Montauk transmission line, other factors (such as aesthetics, environmental concerns, reliability, operational practices, public relations and economics) can off-set the high cost of undergrounding. As a practical matter, it is not reasonable to propose that L1LCQ underground all its facilities. The most effective undergrounding from a reliability standpoint would be the entire substation/circuit approach. The drawback to this approach is that only a small portion of L1LCQ's customers would benefit, even though the costs would have to be spread among all customers. For example, in simplistic terms, if each of L1LCQ's one million customers were charged an additional $150 per year for undergrounding, and assuming no cost increases or inflation, $150 million would be available ($1 00 million after taxes). At that rate, it would take 200 years to underground all of L1LCQ's distribution facilities. If undergrounding were limited to areas with rear lot overhead lines, it would cost a total of $1.5 billion and at $150 per year per customer ($100 million after taxes) would require 15 years to be completed. In our estimation, overall this is a more feasible approach, but given the high cost, limited benefits, and expected resistance from the customer due to landscape disruption, we do not recommend it. ~ 9 .~...........>......-.--~~"....,...... . .- ~ ,~_' ,_:~)~';':,,;,..,~:.,,;..::.:......~;:;:::o...,_~,::,,;....~;;. From a strict cost-benefit standpoint, staff cannot recol11mend any systematic undergrounding program for preventing damage from catastrophic storms. While total costs are difficult to estimate with precision, it is even more difficult to estimate the benefits to customers, or the "value" customers place on increased reliability. There are conflicting survey results as to what customers are willing to pay for improved reliability. Customer perceptions and preferences for conversion and what they would be willing to pay may be explored in more detail in the conversion phase of the generic line extension proceeding, currently in progress. In the companion report on tree trimming, staff found that the best way to combat the effects of a catastrophic storm is to have an adequate emergency response plan that is practiced in an emergency drill at least yearly. The Department has taken an increasingly active role in emergency planning in recent years. Last year, the Commission adopted a new rule (16 NYCRR, Part 105) concerning electric emergency plans that strengthened, among other things, training, communication, and damage assessment requirements. Although these plans cannot prevent service interruptions, we believe that outage durations can be effectively reduced when proper planning, training, and execution of emergency response plans are performed. ~ ." ~..- INTRODUCTION New York State electric utilities were impacted by two catastrophic storms during 1991, resulting in the loss of electric service to over three- quarters of a million customers3. These storms were: the March ice storm, which resulted in the loss of service to 310,000 customers of Rochester Gas & Electric (RG&EI. New York State Electric and Gas (NYSEGI. and Niagara Mohawk Power Corporation (NMPC); and Hurricane Bob, which impacted the Long Island Lighting Company's (L1LCO) system on August 19, which resulted in a loss of service to 477,000 customers. The satellite photo on page 12 shows the magnitude of Hurricane Bob. In the aftermath of Hurricane Bob, the Commission was petitioned by the Consumer Protection Board (CPB) on August 27,1991 to, among other items, conduct analyses of the costs and benefits of undergrounding vulnerable areas of electric service territories. The Office of the Attorney General supported the CPB's petition. At the January 8, 1992 Commission session, during which staff's Hurricane Bob report was presented, commissioners, including the Chairman, asked how effective undergrounding certain overhead electric lines would be in mitigating damage from catastrophic storms. The former Power Division, now part of the Energy and Water Division, committed to undertake a study that would portray the pluses and minuses of selective undergrounding scenarios. The Power Division's System Operations Section was designated as having lead responsibility and was supported by the Rates and Valuation Section. In addition, the power Division sought, and received, assistance from the Communications Division, the Consumer Services Division and the Office of Energy Efficiency and the Environment. Staff from each area formed the Undergrounding Study Team. The scenarios included in this study follow: o Undergrounding all overhead distribution facilities emanating from L1LCO's Indian Head Substation. o Undergrounding all overhead distribution facilities emanating from L1LCO's Buell Substation. o Undergrounding L1LCO's overhead transmission line from Amagansett to Montauk. o Update of a previous L1LCO study assessing the cost of undergrounding all L1LCO facilities, as well as certain other select undergrounding scenarios. 3 Catastrophic storms are generally hurricanes, ice storms, major tornadoes, etc. that cause widespread damage and result in outside forces being brought in to assist utility forces. J 11 , ,,-., ",., ~~~,'~J:~;~;:.;.:_J-!:.;.;1.~i..;.i~:~'=..it""'~ .. "'-*L .._ -~ ~.~~" ~ -. -;-.....---...;------'-"'-- ~ HURRICANE BOB - AUGUST 19, 1991 t .;r.- . '. L1LCO SERVICE TERRITORY L1LCO's service territory encompasses 1,230 square miles including Nassau County, Suffolk County, and the Fifth Ward of Queens County (the Rockaway Peninsula). This area represents less than 3 percent of the area of New York State. However, approximately 2.8 million people, or 15 percent of the state's population, reside in this location. L1LCO's electric customers number slightly in excess of one million. L1LCO has divided the territory into four operating divisions (see below): Queens/Nassau, Central, Western Suffolk, and Eastern Suffolk. l.DII6lSlA111lSOfJllll <:? '" -' o ~ ~ :> (/) BREKTWOOD WESTERN SUFFOLK DIVISION "'~ _0 ~" :;z 00 ,,~ z _ _0 !::~ ~!;i EASTERH SUFFOLK DIVISION FilE ISLAIID ATlAIIIlClICEAII MV-9 Although much of L1LCQ's service area is suburban, the eastern portion of Suffolk County is a principal agricultural and recreational site. Long Island residents have a strong interest in local control of environmental affairs, particularly air and water quality, audible noise, and aesthetics. As a result, L1LCO facilities have adopted unusually stringent design standards. Environmental pressure and the high population density of the service territory have forced virtually all new transmission underground in Nassau and part of Western Suffolk County. L1LCQ's base transmission system operates at voltages of 69 kV, 138 kV, and 345 kV. Thirty-five percent of all 138 kV transmission is comprised of underground cables. The last major transmission project (69 kV) occurred in eastern Suffolk County in 1991. It entailed connecting South old Substation on the north fork of the Island to Buell Substation on the south fork via an undersea/underground/undersea cable that crossed Shelter Island. The Town of Shelter Island mandated that the cable be installed underground and be nitrogen, rather than oil, filled. There are approximately 500,000 poles on Long Island, of which L1LCQ owns 325,000, the remainder being New York Telephone's. None of the poles are jointly owned. Eighty-four percent of these poles contain both telephone ~ 13 ._~.~-~ ~-.----~~~~.., . '. c. .:_ ~'~'J_..::....~,-i...U;'-_~i~i;~-';:~-:;;'i;~;s:tG..ri~;:,';;:;~~t;.,";,., and electric facilities, while cable television facilities are attached to 75 percent of the poles. L1LCO, at present, serves approximately 907,000 customers via overhead facilities, with about 95,000 being served via underground facilities. However, in 1990-1991 L1LCO connected 4,997 new customers served by overhead lines and 3,796 new customers served by underground lines. In terms of new line construction, 1990-1991 saw 45 cable miles of new overhead lines and 186 cable miles of new underground lines. L1LCO has 45,000 cable miles of overhead distribution lines and 11,000 cable miles of underground distribution lines in its system. Numerous town/village undergrounding ordinances are currently in effect on Long Island (most deal with undergrounding in new subdivisions). However, according to L1LCO, it is generally not restricted by these regulations from installing new single overhead services in existing residential areas, and in many cases, undergrounding exemptions are received to avoid having recently-paved roads excavated to install underground electrical facilities. Below is a sketch of a typical L1LCO transmission and distribution system. .SIl!P-UP Transtcaner Generator T"nsmis~un Line Distribution Pole line ~ y HISTORY OF COMMISSION UNDERGROUNDlNG PROCEEDINGS The Commission's earnest consideration of undergrounding' utility facilities began with proceedings initiated in 1969. The purpose of the proceedings was to determine the advisability of adopting rules pertaining to underground electric facilities (Case 25352) and to underground communication facilities (Case 25396). While the proceedings were initially intended to address contractor and developer complaints about the widely disparate utility policies and practices then in use respecting the undergrounding of new distribution lines in subdivisions, environmental and aesthetic considerations soon came to be the central focus. Shortly after the two proceedings began, they were combined and hearings were held concurrently. To facilitate consideration of the diverse complex issues involved, the proceeding was separated into four phases. I - New residential subdivisions with five or more units (initially four or more) and new multiple-occupied dwellings. I-A - New commercial and industrial customers and new residential subdivisions with less than five units. II - Conversion of existing overhead distribution facilities to underground. III - Undergrounding of new transmission facilities to which Article VII of the Public Service Law did not apply. By Opinion and Order issued December 28, 1971 the Commission established rules and regulations pertaining to underground electric and telephone facilities for new residential subdivisions (Phase I). The Commission concluded that, The case for compulsory undergrounding of distribution lines in new subdivisions is extremely strong and that iUWption of uniform rules governing the underground practices and policies of the various utilities in the State was the best way to achieve an orderly growth in undergrounding. The Commission also noted: The growing awareness of the need to preserve the scenic amenities of our environment, as well as recent technologi- cal advances, have resulted in a pronounced trend toward under grounding of utility distribution lines. Undoubtedly, this trend will continue. This is especially true in new residential subdivisions where the undergrounding of distribution lines involves little, if any, replacement of existing facilities in contrast to the extensive construction necessitated in developed areas and where, accordingly, the cost of under grounding can be held to a minimum. ~ 15 ,,",'.1 .... .. _, J ;..~<,..."~,,,...__.._':'-"."~>3~~1.."::~~ ---, Early experience with the Phase I rules demonstrated that slight modification to the rules would measurably benefit their application. The appropriate modifications were made by Commission Opinion No. 73-27, issued August 10, 1973. Continued consideration of the remaining phases in the proceeding resulted in an Examiner's recommended decision with respect to Phase II (conversion of existing overhead distribution facilities to underground!, issued January 20, 1972 and a recommended decision with respect to Phase IA (new construction not governed by Phase I rules!. issued June 26, 1972. On October 17, 1972 a recommended decision was issued relating to Phase III (Undergrounding transmission facilities not subject to Article VII of the Public Service Law!. On March 26, 1975 the Commission issued rules and regulations for Phase III requiring that, where aesthetic considerations prevail, the advantages and disadvantages of underground construction must be considered. Next, having determined that the wide range of individual circumstances present with respect to the customer classes subject to Phase I-A made generic rules impractical, the Commission by Order issued January 10, 1983 closed the proceeding with respect to Phase IA. On September 5, 1986 the Commission initiated Case 29389 to examine the desirability of changes to the electric line extension regulations (16 NYCRR Parts 98-100! to evaluate the impact of changes in the costs of installing overhead and underground lines and to review again the basis for allocating costs between applicants and the utility's general body of ratepayers. The Order instituting the proceeding closed Case 25352 (dealing with the undergrounding of electric facilities! and directed that matters previously considered in Case 25352 be dealt with in the new proceeding. Accordingly, the yet unresolved Phase II (conversion! became an issue in Case 29389. On December 9,1988 the Commission issued an Order Clarifying Scope of Proceeding which declared conversions to be within Case 29389 but that scheduling of its consideration be left up to the Administrative Law Judge. On May 15, 1989 the judge ruled that consideration of the conversion issue would be set aside for a later phase of the proceeding. In the interim, work on developing proposed regulations to replace the existing electric line extension regulations continued. On December 21, 1989 the Commission issued an order expanding the scope of the hearing to include telephone companies and also issued for comment proposed rules with respect to both electric and telephone line extensions. Of particular note in these proposed rules was that special consideration be accorded to undergrounding new lines in specified areas to preserve the aestheticS of those areas. The specified areas are referred to as Visually Significant Resources. or VSRs. The proposed regulations were subsequently modified and, under a neW case number (92-M-0607!. were reissued for comment in September 1992. The ccmments are currently being ~ -- evaluated; the Commission is expected to issue the regulations in final form in early 1993. Activities with respect to conversion were initiated by the Administrative Law Judge at a July 5, 1992 hearing conference. Submission of proposed regulations for conversion to the Commission is tentatively scheduled for early 1993. The current undergrounding proceeding is studying the potential of undergrounding under various scenarios. In fact, the Commission, on September 15, 1992, issued proposed rules for comment that provide for a VSR undergrounding program. This program applies to the new construction of distribution lines, service lines and appurtenant facilities on public and private land in VSRs. The program would remain in effect for a period of five years after its effective date. Under this proposed annual program, L1LCO would be required to allocate at least $2.4 million (subject to adjustment for inflation) to a VSR undergrounding fund and would be obligated to spend such amounts on the cost of installing such new construction underground. Any unspent portion of L1LCO's maximum obligation in a given year would be carried over to the next year. The VSR program would be evaluated by the Commission after the program has been in effect for two years and L1LCO would be required to provide details of its experience as the staff andlor Commission may request. It should be noted that this study was conducted independent of Commission undergrounding proceedings, although most of the study team members are involved in Cases 29389/92-M-0607. Below is a picture of subdivision undergrounding with a pad-mounted transformer in the foreground. .........~ .... ~ SUBDIVISION UNDER GROUNDING 17 . ..~..' ,.., . -~" ._'" __._._ 'J,",-' >':::::T::',~Oi{"";':_"'" -;'i."",,,,,;-,"""J~"'-"'-" -------------- .,,_..,_.,._...-_..~-->-_._~-- SELECTION OF UNDERGROUNDING SCENARIOS The objective in the selection of certain overhead facilities as candidates for undergrounding was rooted in the desire to ascertain which lines were more prone to catastrophic storm damage. It was understood that any undergrounding scenario would result in improved aestheticS although a significant loss of street trees would result from the underground installation. It was also desirable to have the chosen scenarios representative of L1LCO'S system. Undergrounding would have to begin at a substation in order to improve reliability in a meaningful way during catastrophic storms. To underground a section of overhead line whose supply was overhead would have limited value in terms of reliability. L1LCO provided us with storm damage locations from 1973 to 1992. The data available is somewhat broad-based, because the focus following catastrophic storms is restoration, not data collection. Nonetheless, L1LCO still has the most comprehensive data among New York State utilities. Our review of the data showed that during a December 1973 ice storm, primary line damage occurred in the Central and Western Suffolk Divisions. Specifically, this damage was concentrated in the heavily-treed areas in the northwestern portion of the villages of Stony Brook and Saint James. These areas sustained relatively little damage during Hurricane Belle (1976) and the January 1978 ice storm. The eye of Hurricane Belle passed just west of the Nassau-Suffolk County border causing 85 percent of the damage to be concentrated in Suffolk County, especiallY in the sparsely-treed areas in towns along the Great South Bay and in the heavily-treed areas east of Smithtown. The damage which occurred during the January 1978 ice storm tended to concentrate within L1LCO'S Central and Western Suffolk Divisions, especially in the heavily-treed areas of Huntington and the treed areas of Plainview, Plainedge, and Levittown. The almost 20 years of storm data we reviewed covered the entire island with damaged locations. Thus, we found there was no clear-cut area that was more prone to damage. However, one certainty was that the eastern portion of Long Island is always impacted hardest by hurricanes, with ice storms impacting the north-west to north-central portion of the island. A compounding problem with hurricanes is that if the eye of the storm passes through the center of the island, as Hurricane Gloria did in 1985, the south shore of the island is hardest hit. But, if the eye of the storm passes east of Montauk, as Hurricane Bob did in 1991 , the eastern portion of the north shore of the island joins the south shore as being hardest hit (due to the counter- clockwise wind rotation heaviest damage is always recorded east/northeast of the eye of the storm). The One Hundred- Year Storm of December 11 and 12, 1992, left western portions of the north and south shore devastated. Flooding in the Bayville/Ashroken/Eaton's Neck area cf the north shore and , I ~ I >f~> ; , ~--- "l, Massapequa/Ocean Beach, Fire Island area of the south shore was most severe. The study group then proceeded to examine whether undergrounding distribution lines along the shorelines of the island would provide the looked-for litmus test. Difficulties arose with this approach in that circuits meander north, south, east, and west and appropriate cut-off points for undergrounding were not available. The following photographs depict damage from Hurricane Bob. HURRICANE BOB - AUGUST 19, 1991 .. 19 ,- ,. .-.".~._..._.. .,."-....~~--...._.; HURRICANE BOB - AUGUST 19, 1991 Staff also looked at whether undergrounding could be combined with road widening projects or other rebuilding programs. Although the cost of undergrounding portions of circuits involved with these projects would be partially offset by the avoided cost of moving the existing overhead lines to the outer limits of the roadway, the cost differential remains three to five times as great. In addition, most of these projects involve only segments of circuits, thus the customers served by the underground circuit portion will be vulnerable to interruptions occurring in the overhead parts of the circuit. For these reasons, staff does not find this to be a viable alternative. I .l i Since no particular area stood out as a certainty to be impacted by catastrophic storms, it was decided to determine the cost and benefits of undergrounding all circuits emanating from a substation. Although both transmission and distribution lines are constructed according to National Electric Safety Code standards, overhead transmission line feeds to substations are less prone to catastrophic storm damage due to enhanced design criteria, as well as more stringent line clearance or tree trimming practices. ?rl , - ! ~I .-'- , -<a i 1', il ~ The two substations chosen were Indian Head in the northern part of the Western Suffolk Division and Buell, located on the south fork of L1LCO's Eastern Suffolk Division. L1LCO has 150 major substations in its system". The relative location of the two substations is shown on the following page. Indian Head Substation, located in the Town of Smithtown, has six distribution feeders serving 13,850 customers. The overhead facilities include 5,430 poles, 36 miles of primary mains, and 110 miles of branch lines. Indian Head was considered a "typical" L1LCO substation. INDIAN HEAD AREA Buell Substation, located in the Town of East Hampton, has four distribution feeders serving 9,300 customers. The overhead facilities include 4,780 power poles, 31 miles of primary mains, and 86 miles of branch lines. Buell was considered a typical "east-end" substation. J BUELL AREA 21 \ INDIAN HEAD SUBSTATION N N ro\lN or BiiQOKHAV(N . _:_ , I ~ .. r QUE(NS "", AMAGANSETT. MONTAUK LINE .r .. BUELL SUBSTATION !~/LCO SERVICE TERRITORY The substation cost estimates developed in the study should be indicative of most areas in Eastern Nassau and all of Suffolk County. L1LCO estimates, however, that circuits in the densely-populated west NassaLi area and Queens could cost up to 30 percent more to underground due to the need for more manhole and duct systems, more paving, and more below-grade transformers and switchgear. The undergrounding of the existing overhead transmission line from Amagansett to Montauk, a project that L1LCO will begin to construct in 1993, was the third undergrounding scenario chosen. In addition to these two substations and the undergrounding of the Amagansett to Montauk transmission line, L1LCO's 1978 study involving the undergrounding of L1LCO's entire system, was updated to a 1992 cost basis. It is surprising to note that technological advancements since 1978 have not significantly reduced the cost of installing underground cable. This is due to more stringent design criteria. The criteria includes manually operated "looped" cable runs for reliability, which substantially adds to the amount of cable installed; larger cable sizes to handle overloads and future growth; and sectionalizing portions of circuits to allow for isolation of faulted cables and faster restoration time. While Phase II of the line extension proceeding would be an appropriate forum to discuss these scenarios, when the decision to do this study was made, Phase I was not resolved and it was not clear when Phase II would commence. Findings were anticipated in this study rather soon compared to the lengthy generic line extension proceeding. For example, Phase I has been ongoing for over six years. In addition, the scope of the L1LCO underground study was rather limited in that it was to review the costs and benefits of overhead conversions to mitigate catastrophic storm damages whereas Phase II had not developed the rationale for conversion although it was to be more comprehensive. "- ~... ~. AMAGANSETT-MONTAUK OVERHEAD TRANSMISSION LINE ~ 23 -- ---- --.------" -~_.__._--- ..-.----- ---_.._--~.-.._.. ",-" SUBSTATION CIRCUIT UNDERGROUNDlNG DESIGN ASSUMPTIONS The detailed layouts for the Indian Head circuit and the Buell circuit are based on L1LCO's latest design standards for Commercial, Industrial Parks Underground Development (CIPUDl and Residential Underground Development (RUD1. The underground circuit main essentially follows the same route as the overhead main and has the same overall length. In some instances, it was anticipated that the main would be rerouted if it were determined that a parallel route would be more advantageous from a cost standpoint, have less impact on traffic, or have greater accessibility for locating pad mounted switchgear. For the circuits in both the Indian Head and Buell Substation areas, a direct buried cable was assumed. In other areas, especially business districts which are completely paved with sidewalks and have buildings immediately adjacent to each other, a manhole and duct system would be required to facilitate maintenance and future expansion with minimum impact on area disruptions. Pad Mounted Housing (PMHl switchgear would be located every 1,000 to 1,500 feet in order to provide sectionalizing points on the circuit main and take-off points for the CIPUD and RUD fused looped branches. The switches would be manually operated with the exception that circuit midpoint and tie point PMH gear would have supervisory sectionalizing capability similar to the overhead system whereby faults on the circuit main can be isolated to one-half of the circuit, thereby allowing rapid restoral of service to the remaining half. It has also been assumed that suitable locations would be found for the pad mounted switchgear. However, this may not always be the case. Pad mounted transformers and switchgear are L1LCO's standard installation practice for underground cable. Below-grade and direct-buried units are more difficult to locate and maintain, more difficult to keep dry, and more expensive to install. ~. ~ " .~ 'lA :~ In addition to the circuit main, there are two types of fused looped branches that supply pad mounted 13 kV to 120/240 Volt transformers: three- phase CIPUD loops for commercial/industrial load, and single-phase RUD I.oops for residential load. Both fused loops are designed with sectionalizing at each transformer such that the failure of a transformer or cable can be isolated, permitting the restoral of service to the remaining transformers on the loop. On some streets the three systemsncircuit main, CIPUD loop, and RUD 100P--would be adjacent to each other. Unlike overhead systems, considerable advanced planning is required to ensure that unanticipated operating contingencies are appropriately addressed in underground designs. For these reasons, present L1LCO standards require significant numbers of padmounted sectionalizing devices and branch cable loops to enable quick restoration of customer service. In L1LCO's existing CIPUD loops each commercial/industrial load has its own transformer. In some of the older commercial areas with small stores adjacent to each other, one transformer would supply two or three stores. In applying the RUD system designs, it is assumed that if the cable does not loop back on the same street, pad mounted transformers on one side of the street would supply houses on the other side by bringing secondary cable across the street. This secondary pattern would then supply the service pedestals that connect the various house services to the system. The overhead system would remain in service until each area was converted, and the other utilities (telephone and cable TV) had undergrounded its facilities. Removal of the overhead facilities includes removal of all poles, which assumes that service to municipal street lighting would also be undergrounded. ~ 25 ......~M.--'"',..".. i":" ..,' ..;;..~, SUBSTATION CIRCUIT UNDERGROUNDING METHODOLOGY Cost Estimate The methodology employed by L\LCO in pricing out the undergrounding of the overhead facilities related to each substation is listed below: A detailed undergrounding analysis and layout was made of a selected circuit from each substation which contained a representative mix of residential and commercial/industrial load. Indian Head circuit 6HL-816 and Buell circuit 9E-992 were the selected circuits. All circuit main and branch taps, including PMH switchgear and transformers, were laid out in accordance with current CIPUD and RUD design standards. PMH Gear ~ The methodology was to take the results of a detailed analysis of one circuit from each substation and ap!>>y it to the other circuits in the substation to arrive at an overall cost for undergrounding the entire substation area. The costs to install each component associated with ~-~"._. ~,~,,~ undergrounding the circuit mains, fused branches, and individual services were estimated based on unit cost estimates developed by L1LCO's Area Planning Division and reviewed by the Customer Design Services Department, and the Electric Lines Department. Removal costs include complete removal of all overhead facilities, including poles. The study has assumed all other facilities (Le., NY Telephone, cable TV and municipal street lighting) would also be undergrounded at the same time. The additional cost of this undergrounding is not included in the cost estimate. A summary of the total cost to underground each of the two candidate circuits was prepared by counting each specific piece of equipment on the circuit and applying the unit cost estimates explained above. To determine the costs for the remaining circuits, a residential and commercial cost per connected kV A was calculated for the transformer capacity from the two selected circuits and applied to the equivalent overhead transformer capacity on the remaining circuits. The costs for the installation of the circuit main and fused loops were compared to the totals of overhead mains and branches on the selected circuits and a corresponding cost ratio developed. This was applied to the corresponding amount of overhead circuit main and branches on the remaining circuits. Rate Impact The cost estimate together with additional L1LCO source data was used to develop inputs for the Strategic Financial Plan (SFPl computer model used by both staff and the company. The Base Case used in the study reflects increases due to the L1LCO Ratemaking and Performance Plan, as modified in Opinion No. 91-25 (Case 91-E-1185l. The SFP model produced the stream of future annual revenue requirements which would be required for the various undergrounding scenarios. Using the revenue requirements, we derived the average percent increases to ratepayer bills in all service classifications. As an example of rate impact, we computed the percent increase of the average annual bill of an average residential customer (monthly usage of 600 kWh). The composite undergrounding information inputs to the SFP model are shown in Appendix A. The summary of the revenue requirements and the concomitant rate impacts for each of the scenarios evaluated are included on the corresponding spreadsheets in Appendix B. A 27 COSTS TO UNDERGROUND AND RESULTING RATE IMPACTS The costs associated with undergrounding were derived by L1LCOand reviewed by the study team. The cost/rate impact data for both the $20 billion updated L1LCO 1978 study and that for undergrounding the Indian Head and Buell substations includes the cost for both customer service laterals and the costs to connect these service laterals to the electric meters located on the outside of the house. Normally the customer/builder would pay an electrician to connect the service lateral to the meter. For purposes of this study, mainly because of the magnitude of the underground costs which would ultimately be borne by the customer, we thought it useful to present a complete package of the cost/rate impact which the ratepayers would bear. For an underground program of this magnitude, staff assumed that L1LCO would utilize contractors whose price includes certified electricians, who are licensed to connect the service lateral to the meter. Hence, the contractor's price would be a complete package. The additional costs of undergrounding telephone, cable television, and street lighting services are not included in the cost projections. Rate impacts were developed for an 11-year study period (1993-2003) which is the output limit of the Strategic Financial Planning model used in the analysis. Since the estimated installation period for undergrounding substation feeders is 10 years, the model was compatible. However, since the installation period for the entire undergrounding scenario is 25 years, we can only project rate impacts for the first 11 years of installation. Thus, additional monthly increases would occur for the remaining 14 years of the installation period. The rate impact of undergrounding L1LCO's entire distribution system would be to raise the average monthly residential rate by $108, from $83 to $191 during the first 11 years, or an average yearly increase of about 7.9 percent. Over the entire 25 years required to underground the entire system, a 569 percent increase in rates solely due to undergrounding would be realized. The rate impact on the other service classes would also be about 569 percent, exclusive of additional increases due to all other causes. Under a 25-year plan, L1LCO would need to finance at least $0.8 billion per year. Our finance personnel advised that a construction program of this magnitude would require L1LCO to continually access the capital market. They further indicated that such a program would undoubtedly cause cash flow problems for the company which could adversely affect the rate at which L1LCO could access the capital market, or in a worse case scenario, impede its access to the capital market. The consequences of effecting early retirement of all overhead transmission and distribution plant due to installation of replacement underground plant may require special accounting/financing treatment. There may be a need for rapid amortization of the loss in order to be consistent with J 28 accepted accounting practice. An amortization period shorter than the normal period during which the overhead plant would otherwise be depreciated will increase the utility's revenue requirements, thus resulting in the need for still further increases to customers' bills. The cost/rate impact of undergrounding the entire distribution system is the aggregate of undergrounding all of L1LCO's 150 major substations. By deriving the impacts for two individual substations (Buell and Indian Head) we give a sense of the rates that would impact all of L1LCO's ratepayers, based on undergrounding the entire system in conformance with current L1LCO design standards. INDIAN HEAD SUBSTATION As mentioned previously, Indian Head Substation employs six circuits to serve 13,850 customers (of 1,005,000) over 146 miles of main and branch lines supported by 5,430 power poles. During Hurricane Bob, 1,400 customers lost electric service. During Hurricane Gloria in 1985 all customers lost electric service. The Indian Head Substation is pictured below. ~ 29 . ,'" -c. . '; ;~-;:;- .:;;. _._..-.---_.~---_.._-~ The cost in 1992 dollars to underground all circuits, as well as the cost to remove the overhead lines including salvage, is $156,707.000." The undergrounding installation is projected to be performed in equal segments over ten years. with additions entered to plant-in-service for each of the years. The detailed work sheets supporting this figure can be found in Appendix C. Rate Impacts The summary computer run for the rate impacts that would result from undergrounding all primary and secondary distribution lines from the substation, including customer service laterals, is detailed in Appendix B. Undergrounding the Indian Head circuits will increase L1LCQ's cumulative revenue requirements by nearly $299 million over the study period (1993-20031. Alternative #1: RATEPAYERS SERVED FROM THE SUBSTATION PAY ALL COSTS The impacts on Indian Head customers who would benefit directly, solely due to the cost of undergrounding would be to: o Increase the average residential customer's present monthly bill ($83 for 600 kWh usagel by $129 by the year 2003, which is an increase of 155 percent. UNDERGROUND INDIAN HEAD SUBSTATION Impact on Residential Monthly Bills Indian Head Customers Only Dollars 300 Cents/KwH 50.00 100 41.67 250 33.33 200 ............................ .... 25.00 150 16.67 8.33 50 0.00 o 1992 1994 1996 1998 2000 2002 _ W/O Undergroundlng -;- With Undergroundlng ~ _:--~ .t _.~ Alternative #2: ALL L1LCO RATEPAYERS PAY THE COSTS The impacts on all L1LCO customers solely due to the cost of undergrounding the lines emanating from the Indian Head Substation would be to: o Increase the average residential customer's present monthly bill ($83) by $2 by the year 2003, which is an increase of 2.4 percent. BUELL SUBSTATION The Buell Substation utilizes four circuits to serve 9,300 customers over 117 miles of main and branch lines supported by 4,780 power poles. During both Hurricane Bob and Hurricane Gloria all customers lost electric service. The Buell Substation is pictured below. J 31 _._ ._.___.______..__,____~.._____..__..._._.~_".____c....._~....~_..__....~.~,_____... The cost in 1992 dollars to underground all circuits, as well as the cost to remove the overhead lines including salvage, is $147,355,600. The undergrounding installation is projected to be performed in equal segments over ten years, with additions entered to plant-in-service for each of the years. The detailed work sheets supporting this figure can be found in Appendix D. Rate Impacts Undergrounding all Buell circuits will increase L1LCQ's revenue requirements by nearly $281 million over the study period (1993-2003). Alternative #1: RATEPAYERS SERVED FROM THE SUBSTATION PAY ALL COSTS The impacts on Buell customers who would benefit directly, solely due to the cost of undergrounding would be to: o Increase the average residential customer's present monthly bill ($83 for 600 kWh usage) by $180 by the year 2003, which is an increase of 217 percent. UNDERGROUND BUELL SUBSTATION Impact on Residential Monthly Bills Buell Customers Only 250 Cents/KwH 50.00 Dollars 300 41.67 33.33 200 100 25.00 150 .......................-.......--...............-... 16.67 8.33 50 0.00 o 1992 1994 1996 1998 2000 2002 _ W/o Undergroundlng -i- With Undergroundlng Alternative #2: ALL L1LCO RATEPAYERS PAY THE COSTS The impacts on all L1LCO customers solely due to the cost of undergrounding the lines emanating from the substation would be to: o Increase the average residential customer's present monthly bill ($83) by $2 by the year 2003, which is an increase of 2.4 percent. "- ~ 32 AMAGANSETT TO MONTAUK TRANSMISSION LINE At the outset of this study, L1LCO personnel were preparing to go before the Board of Directors with a plan to replace the existing two circuits of 23 kV overhead transmission lines, which run from the Amagansett Substation to the Montauk Substation, with two 23 kV underground circuits. The undergrounding installation is projected to be performed in equal segments over six years, with additions entered to plant-in-service for each of the years. The Board of Directors has approved the project, and construction of the line is scheduled to commence early in 1993 and conclude in 1998. Since the driving force behind this project was enhanced reliability during major storms, aesthetic gains resulting from the removal of the overhead lines, and relief of the overloaded overhead lines, it was decided to include this project as one of our scenarios. The preliminary cost estimate for the two 11.5 mile circuits and the removal of the existing overhead facilities in 1992 dollars is approximately $10,600,000. The total revenue requirements are calculated to be $14.5 million for the six-year period. The costs of a transmission line are allocated to all (1,005,000) L1LCO ratepayers. This amount would, accordingly, have a de minimus impact on rates. HISTORY The existing transmission line between the Amagansett and Montauk Substations consists of a double circuit overhead 23 kV pole line, most of which runs through an extremely environmentally-sensitive wetland area (see below). \ A 33 During 1991 's Hurricane Bob, one of the wooden transmission poles broke, thereby causing the loss of power in both circuits for several days. This effectively caused outages to all points east of the broken pole. Repair of the pole was extremely difficult since the area was flooded. and L1LCO could not obtain a permit to bring mechanized equipment into the environmentally- sensitive area. Shortly after this incident, L1LCO embarked on its undergrounding plan. L1LCO's decision was based on the following: Environmental Concerns - Based on the existence of the line in an environmentally-sensitive area, continued maintenance, repair, and reconstruction would be costly, time consuming, and difficult. Reliabilitv - Reliability to the east-end substations will be greatly enhanced by placing circuits underground. Five substations that relied on a single double-circuit pole line will now be served by underground cables. Visuallmoact - The existing overhead pole line is in an area where predominant foliage consists of small pine trees, wetlands, and scrub oak, and is highly visible. The area's predominant business is tourism. Removal of the overhead pole line will greatly enhance the scenic aspects of the area. Public Relations Considerations - The Town of East Hampton has requested the undergrounding of the facilities for environmental, reliability, and tourist reasons. .. EXISTING AMAGANSETT TO MONTAUK OVERHEAD LINE 34 PRESENT STATUS The first phase of the project calls for one new cable to be placed.along Montauk Highway from the Amagansett Substation east to the general vicinity of Montauk State Parkway and Old Montauk Highway - a distance of approximately five miles. The plan is to complete the first underground circuit and have it in service before the summer peak load period in 1993. At that time, the two existing overhead circuits will be combined into one circuit. The second phase of cable installation will start later in 1993 and will continue the cable all the way to the Montauk Substation. The underground circuit and diversity of route will improve reliability to the Montauk area. During the 1994 to 1998 time period, the second underground circuit will be installed. When the second circuit has been placed in service and has demonstrated its service reliability, the existing overhead line between Amagansett and Montauk will be removed. r -' . . ../ ~ 35 For comparison purposes, we asked L1LCO to estimate the cost of removing the double-circuited portion of the line which runs through the wetlands and erecting it as an overhead line on Montauk Highway. L1LCO estimated the cost at $6,251,000; however, L1LCO points out that all recent attempts to obtain permission to install overhead transmission in the Town of East Hampton have met with rejection by the Town. ~ EXISTING AMAGANSETT TO MONTAUK"OVERHEAD LINE ~ 36 UNDERGROUNDING ALL L1LCO FACILITIES In 1978 L1LCO conducted a study that estimated the cost of undergrounding all L1LCO facilities to be $6.7 billion. In 1990 L1LCO updated that study to $13 billion. The undergrounding installation was projected to be performed in equal segments over 25 years, with additions entered to plant-in- service for each of the years. The study group has applied an 8.5 percent, two-year inflation factor to the 1990 L1LCO estimate, yielding a total of $14.2 billion. It should be noted, however, that the new, more stringent design criteria adopted by L1LCO has not been factored into this update. In addition, no dollar allowance has been made for overhead lines constructed during the last two years to be converted to underground. Thus, by employing only an inflation update, the cost of undergrounding L1LCO's entire system is understated. L1LCO estimates that the total cost including the more stringent design criteria for its distribution system alone would approximate $20 billion. For comparison purposes, if one multiplied the $150 million per substation figure by L1LCO's 150 substations, the total cost of distribution undergrounding would be $22.5 billion. Thus, L1LCO's estimate of $20 billion appears reasonable. It should be noted that L1LCO's total net utility plant approximates $3 billion. Using L1LCO's $20 billion distribution undergrounding estimate we updated the cost of various partial undergrounding scenarios. The results in 1992 dollars follow: Replace existing rear lot overhead branch $1,473,281,000 lines with standard RUD type underground cable. Replace existing rear lot primary overhead $ 689,327,000 branch lines with underground primary in sidewalk areas but retain overhead transformers, secondaries, and rear lot services. Replace existing rear lot primary branch $ 781,717,650 overhead with underground primary in sidewalk areas. Replace existing overhead transformers with pad-mounted units at street property lines. Retain overhead secondaries and rear lot services. Replace existing overhead branch primary on $1,933,128,000 highways (4,015 miles) with underground cable in sidewalk area. Retain overhead transformers, secondaries, and services on highways. " ~ 37 Rate Impacts The summary computer run for the rate impacts that would result from undergrounding L1LCO's entire distribution system is detailed in Appendix B. Undergrounding will increase L1LCO's cumulative revenue requirements by approximately $18.5 billion over the 11 year study periocf (1993-2003). However, it must be noted that the installation period for this scenario is 25 years. The rate impact depicted here represents only the first 11 years of costs. Additional monthly increases would continue for the remaining 14 years of the installation period. The impacts on all customers solely due to undergrounding by year 2003 would be to: o Increase the average residential customer's present monthly bill ($83 for 600 kWh usage) by $108 by 2003, which is an increase of 130 percent. There are cost savings associated with undergrounding, primarily reduced tree trimming, storm restoration, and storm insurance premium costs. However, these savings, which would be on the order of $17 million per year, are dwarfed by the costs of undergrounding. The study team also examined undergrounding select components of the distribution system, as L1LCO did in its 1978 study. The options presented focused on rear lot facilities, which sustain significant damage during catastrophic storms, and are among the last facilities to be repaired. This approach is more balanced than the substation approach because it benefits a wider customer group; however, it would not benefit all customers and would not eliminate all interruptions. The options presented range in cost from $656 million to just over $1.9 billion, with an annual rate impact on the order of 4.8 to 8.4 percent over the first 11 years of installation. 4 Eleven years is the maximum period for which the computer model is designed to accept inputs. J 38 UNDERGROUNDING CONSTRAINTS AND BENEFITS The following construction, operating, and maintenance considerations impact on undergrounding: The cost of undergrounding existing overhead lines is in many cases prohibitive. A major problem is the siting of PMH switchgear and in some cases, pad mounted transformers. It is anticipated that there would be extensive negotiations required for easements. It is also anticipated that there would be many instances of legal action on the part of the public to prevent the location of above-grade facilities on or near their property. Also, many municipalities may enact ordinances to prohibit, or as a minimum, limit the installation of above-grade facilities. Under the assumption that other utilities (telephone, cable TV, municipal street light services, and traffic signal services) would be undergrounded along with electric, there is the problem of providing special utility corridors in the road for each utility. This is necessary to maintain the integrity of each system. This presents problems on some roads where there are existing gas, water, storm drains, and sewer facilities, which limit the ability to establish these corridors. The Communications Division points out that the conversion of existing overhead to underground facilities is fraught with difficulties because of fences, hedges, driveways, sidewalks, and other residential property enhancements which add substantially to undergrounding costs and will generally adversely affect the company's public relations image. Costs will multiply because of the fact that when power lines are placed underground, telephone and cable TV would most likely follow. Furthermore, future replacement of buried plant is extremely costly and difficult. Much of the telephone wire which was buried (not in conduit) years ago and is presently deteriorating and in need of replacement is being placed overhead because the homeowner does not want the landscape disrupted. Since the wire was buried, homeowners have placed shrubs, driveways, trees, lawns, sidewalks, etc., on top of the buried plant and are not at all interested in replacing or repairing their property after it has been worked over by a utility crew. Neither is a utility willing to foot the high cost of making these changes, nor is it willing to consider the liability in these scenarios should something go wrong. In many instances, municipal, county, and state road widenings, storm drain installations, and sewer projects affect L1LCO facilities. By law, L1LCO must move these facilities at ratepayers' expense. In an all-underground area, many of these projects entail installing new facilities and abandoning existing facilities. Cable failures on an underground circuit main place more of a strain on surrounding circuits than on an equivalent overhead system. As is the case on the overhead system, faults on the circuit main "are isolated and the load temporarily transferred to surrounding circuits. However, where overhead ~ 39 faults can be located and repaired in a matter of hours, some underground failures could take days to locate and repair. It is, therefore, more critical to assure that surrounding circuits can handle the emergency loading for longer periods. This could be a major problem in cold weather where snow and ice conditions could make fault location and repair very difficult and time consuming. The service life of underground facilities is less than overhead facilities (30 years versus 50 years), and the initial installation costs and replacement costs are higher. A frequently-cited benefit of undergrounding distribution facilities is avoidance of the visual intrusion imposed by overhead systems. Additionally, undergrounding also eliminates the sometimes conspicuous and objectionable appearance resulting from tree trimming necessary to insure safe and reliable operation. Of course, appearance is a subjective matter and overhead systems can vary greatly in its visual impact depending upon such factors as design, location and exposure to view. Thus, depending on the specifics of the situation, the perceived degree of visual improvement of an underground system in contrast to an overhead system can be quite variable. Since underground systems do not require the extensive tree trimming operations necessary to insure the safe and reliable operation of overhead systems, the cost of maintaining such operations would consequently decrease. ~ HURRICANE BOB DAMAGE Avoided insurance premiums are also a benefit of undergrounding. L1LCO reacquired hurricane insurance in 1989. L1LCO's deductible was $5,000,000, with coverage of $25 million above the deductible. L1LCO's premium prior to August 19, 1991 (Hurricane Bob) was $1,119,000. Damage sustained during Hurricane Bob amounted to approximately $27 million. However, L1LCO remains in danger of having its insurance canceled. L1LCO's latest premium of $5,200,000 provides for $37 million of coverage above a $5,000,000 deductible. The undergrounding of distribution facilities, however, offers certain advantages not found in overhead systems. One such advantage is the virtual elimination of outages, and accompanying repair expenses, caused by weather- related impacts, including strong winds, snow, and ice storms. Additionally, the decreased exposure of an underground system reduces the probability of outages caused by motor vehicles and other foreign objects coming into contact with the system. As a result, underground construction can be viewed as enhancing the reliability of the distribution system's operation. Reliability, especially in the early years of an underground cable's service life {30 years estimated!. is greater in terms of frequency of interruptions (a recently adopted Commission performance standard). The offshoot, though, is that the other recently adopted reliability standard-duration of interruption is considerably longer for underground than for overhead facilities. Data indicate that interruptions involving the underground CIPUD/RUD system account for approximately .9 percent of L1LCO's total customer interruptions. The average customer was affected by an interruption to the overhead distribution system once every 8.6 months compared to once every 7 years for a customer affected by failure of a CIPUD/RUD component. On the basis of frequency only, therefore, underground service in L1LCO's service territory is about ten times more reliable than overhead service. Restoration time, however, for a CIPUD/RUD system outage is about twice that of overhead. On a composite reliability basis, therefore, underground systems are roughly five times more reliable than overhead systems. Customer expectations research shows that reliability of service is a very important factor to customers. However, there is no accepted dollar value of how much customers are willing to pay for improved reliability. While there have been several theoretical and empirical studies on this topic, including one recently conducted by Resource Management International for Niagara Mohawk Power Corporation, the Commission has never endorsed any dollar value or any particular methodology for evaluating the value customers place on enhanced reliability. The Commission has also not endorsed any explicit dollar value for improvements in aesthetics. ~ 41 , '.. ....,.,",.,.------...-...,.,.-"..--------- OTHER FACTORS RELATED TO RELIABILITY Although hurricanes and ice storms cause the largest number of service interruptions, the chart below shows that there have been only ten catastrophic storms since 1960, or one about every three years. However, the average customer is interrupted as a result of these storms about once every seven years. HURRICANES AND ICE STORMS 1960 - 1991 STORM !DONNA 9/12/60 ESTHER 9/21/61 11/12/68'j 8128171 iiI 12/17/73.~ BELLE 8/9176 ICE STORM 1/13/78 DAVID 9/6/79 GLORIA 9/27/85 !BOB 8/19/91, o 200 400 600 800 1,000 1,200 THOUSANDS OF CUSTOMERS . GUST INTERRUPTED. GUST SERVED I ~ 42 Customer interruptions also stem from other events, as the chart below shows. CAUSES OF CUSTOMER INTERRUPTIONS Unknown Failed Connectors 70/. Fuses, Transf, etc 0 6% Potheads/Splices 7% Cable Failures 8% Trees 26% Miscellaneous 9% Birds/Squirrels 4% Lightning 10% Motor Vehicles 10% Hot Line ClamplTaps 13% ~ 43 . . , There are reliability measures, other than undergrounding. which can be employed by utilities. lILCO has embarked on a distribution system upgrade program to improve service reliability. lILCO's expenditures in the area of distribution upgrades are shown below. The goal of L1LCO's program is to improve both the frequency and duration of outages to customers by 40 to 50 percent by the mid-to-Iate 1990's. MAJOR UPGRADE PROGRAM EXPENDITURES (ANNUAL AVERAGES IN CONSTANT 1990 $'s) // 30 / 26 CJ) z 20' o ..J ..J15.' :2 >< _Ill 10 .' * 4,]. / / 25 . 5' - ~-: -' . '. ~ - -:. "" . _. _u "/ - . ~-- ~; ~ ..; . ";; .-"--.- { . ! . ~" - ~ . i - - '. . // / 0" 1980 - 1988 1989 . 1991 1992 . 1999 ~ 44 The results of this spending program in millions of dollars can be seen below. . UPGRADE PROGRAM ACCOMPLISHMENTS AND EXPENDITURES 1989 - 1991 ACCOAq;;:"'!5H~gE}~7S $!~ ;: ~~-:;~~~:;~7J~ Distribution Tree Trim 5,360 Miles Trimmed 21.6 Hot Line Clamp Replacements 103,300 Clamps Replaced 15.5 12,835 Line Breakers Removed Supervisory Controlled 250 Switches Installed 10.5 Switches Covered Wire 160 Miles of Bare Wire Replaced 11.6 Primary Cable Replacements 18 Miles of Cable Replaced 4.9 Lightning Arresters 1..600 Silicone Carbide 0.7 Arresters Replaced Infrared Surveys Surveyed Entire Transmission System 0.5 and 300 Distribution Circuits Yearly Replace Potheads 104 Potheads Changed Out 0.2 Elbow Xrays, Splicer Training, etc. 10.7 76.2 ~ 45 i,! .__,.. ...._..,..._,._--'-._M__'-~.~"--.+_'.'-'_._~...~..___._..~_.._~~ -- , "._..n_""__. __".,..., ~"'_"J"" CONCLUSION The purpose of this study was to assess undergrounding's potential to mitigate L1LCO service interruptions caused by catastrophic storms. The result of the study, which was not unexpected, was that undergrounding would most definitely reduce, to a significant degree, service interruptions during catastrophic storms. Overhead systems bear the brunt of the ravages of hurricanes and ice storms, while underground systems remain relatively protected. Not surprisingly, it is the exorbitant costs of undergrounding existing overhead lines which has always precluded massive undergrounding measures and will probably continue to do so. As this study showed, the rate impact on the consumer of any significant undergrounding scenario prohibits the pursuit of most undergrounding proposals. L1LCO's major weapon in preventing service interruptions from major storms is its enhanced reliability programs. These programs are proving successful in reducing service interruptions throughout L1LCO's territory. However, during catastrophic storms, such as hurricanes and ice storms, even these measures are not effective in preventing interruptions. Fortunately, the catastrophic storms occur infrequently. In addition, L1LCO has the most comprehensive Emergency Response Plan in the state, which enhances the company's ability to rapidly recover from storm devastation. Although this study, which pertains only to L1LCO's facilities, shows the rate shock which results from massive undergrounding, it also shows that for certain specific situations, undergrounding an overhead line is not only viable but may be the preferred course of action. The undergrounding of the Island's east-end transmission line is being undertaken for visual, aesthetic, reliability, maintenance, and public relations reasons, as well as to meet future load growth requirements on the South Fork, and appears to have been the proper choice. Although not detailed in the study, L1LCO does underground certain portions of existing overhead lines, albeit on a far smaller scale, for exactly the same reasons. The feasibility of this approach to undergrounding was not within the scope of this study, but could well be included in the Commission':; generic proceeding on undergrounding. Another possible approach to undergrounding existing overhead facilities lies in the Commission's recently adopted reliability performance criteria. Each utility must, among other things, report annually on the worst-performinG circuits (in terms of frequency and duration of interruptions) and indicate the planned corrective actions. In this regard, the utilities could be made to evaluate the benefits/cost ratio for undergrounding said circuits. This area could be further studied in the ongoing ,Phase II undergrounding proceeding. ~ 4.fl Inout Data for StrateQic Financial PlanninCl Model General AssumDtions Return on equity/debt per Opinion 91-25 L1LCO C. 90-E-1185 Installation work on each scenario commences January 1, 1993 Average Service Life (ASL) of UG distribution & transmission = 30 years (w/zero salvage) Input data amounts are in 1992 dollars unless stated otherwise Prospective inflation rate for UG is 4.2% (approx. GDP inflation +0.5%*) * L1LCO T&D generally tracks 0.5% to 1.0% above GDP UG Cost Elements as % of investment Composite O&M = 3.6% Admin & General = 3.3% ** Property Tax = 6.5% ** GRT = 5.5% * * to be modified when respective projected A&G and property taxes reach saturation levels Caoital Structure Additional capital to finance UG (50% debt, 50% equity) O&M UG Costs vs. O&M Savinas for OH (overheadllines reo laced (based on actual 1991 data) Additional Cost UG $/mile Savings OH $/mile routine O&M emergency service tree trim $1 ,521 545 286 $1,096 3,550 1.807 $6,453 TOTAL O&M/mile $2,352 ~ Scenario AssumDtions 1. UG lines Buell + Indian Head Substations Capital Construction (excl. AFC) Indian Head Substation Buell Substation - UG Distribution lines emanating from substation incl. services and removal of OH lines' - Installation in equal segments over 10 years - Assume each year's CWIP is closed to plant-in service 2. UG all L1LCO overhead facilities2 Capital Construction (excl. AFC) - UG Distribution = Trans. lines + Service Laterals + Street Lights and remove OH lines - Installation in equal segments over 25 years - Assume each year's CWIP is closed to plant-in service 1 No costs are included to reflect the early retirement of the overhead lines. $ millions $156.7 147.4 $ billions $20.0 2 Based on the updated cost for the 1978 study which is understated because of significant ~ changes in design specifications. ~ . LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY SAMPLE CALCULATIONS FOR EXECUTIVE SUMMARY Ratiol% Notes/Source Data Effect of only UnderQroundinQ on Residential Rates for initial 11 years initial rates= $83/mo. ; final rates= S191/mo. " increase ratio=191/83= average yearly increase=7.9%; check: (1.079) ^ 11 =2.308; rounded 2.30 " 2.30 %increase in rates in 11 years =0ncrease ratio-1)*100= (2.3-1)*100 check: (191-83)*100/83= 130% 130% "" Effect of only UnderQroundinQ on Residential Rates for initial 25 years increase ratio= (1.079) ^ 25= 6.69 Initial Rates = $83/mo. final rates=6.69*83/mo.= $55527/mo. %increase in rates in 25 years =(increase ratio-l)*100= (6.69-1)*100 569% "" * source data= Appendix B; worksheet titled Scenerio #1 ....the rates of all service classifications will increase by approximately this percentage lIlCO\Undergro\Exec-SUm.wk3 ~ , LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY DECEMBFR 1992 SCENARIO #1 TOTAL OF BASE CASE + INCREMENTAL EFFECT OF INCREMENTAL EFFECT OF BASE CASE. UNDERGROUNDING ENTIRE SYSTEM.' SCENARIO #1 Approx. Approx. InCLlo Approx. Base Base Resident. Residential IncLlo Incr. to Resident. Total Base Base Monthly Base Base Monthly Avg. Monthly Revenue Revenue Bin'" Revenue Revenue BIII"""4 Revenue BlII". YEAR ($M) (c/KwH) ($) ($M) (c/KwH) ($) (c/KwH) ($) $2,234 2,341 2,462 2,595 2,723 2,859 3,002 3,038 3,050 3,185 3,301 3,480 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 I I 2017 UIIl" NoIOS: 1110 Oas8 Case assumption, undorlylng IhelLCO Rale Moderallon plan 8S modlllod In Opinion 91 - 25, was updated 10 roflect nec8s8Bfy caplals,,"ucllIO modlflcallons fOf Scenario II 1. ... undorgoundlnglnslalJollonw:. $ 20 billIon (1092 OOllo(8)- 10 be Inslalled In equal sogments OV'Of 25 VOIfS ".. assumos monthlv U80 per realdonUal customer d 600 KwU ..... glvon an Incroase o. $108 In mo. hills solely duo 10 uder(Joundlng from $H3/mo 10 $19'/mo.- or 8n Inaoase 0' 130% In 11 years; tho avorage Incroase to monlhly billa would be 7.9 " compounded annually solely due 10 under(Joundlng, I.e. In addillon to Iho base caso Inaoases Indlcaled "'"",,'" ;$Y'l3n<tS 'G'ii~1c.;'msnt. a~(; ri?lt6F.fP.:'{er ~i1~ ~"1l!8 continue 10 increase unlit undorgroundlng compkrUon In 2011 13.84 14.39 14.96 15.57 16.16 16.79 17.45 17.47 17.32 17.87 18.29 19.05 $83 $86 $90 $93 $97 $101 $105 $105 $104 $107 $110 $114 $0 178 436 704 1,005 1,324 1,640 1.992 2,354 2,652 2,962 3,292 $18.538 Sub-Total nla 1.09 2.66 4.22 5.97 7.78 9.54 11.45 13.36 14.88 16.42 18.02 nla $7 16 25 36 47 57 69 80 89 98 13.84 15.48 17.62 19.79 22.13 24.57 26.99 28.92 30.68 32.75 34.71 37.07 108 ..u $83 93 106 119 133 147 162 174 184 197 208 222 . \ LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY AUGUST 1992 SCENARIO #2B EFFECT OF UNDERGROUNDING (UG) DISTRIBUTION LINES FROM INDIAN HEAD SUBSTATION" IlllCrnstlives IN-HD RATEPAYERS SERVED FROM ALL ULCO RATEPAYERS UNES INDIAN HEAD BEAR THE BEAR THE BASE CASE. UG Ui'jQERGROUND/NG COSTS UNDERGROUNDING COSTS Approx. Approx. Approx. Iner. Iner. New Iner. New Res/d. 10 to tner. to Resld. 10 Iner. 10 Res/d. Base Avg. Month. Bese Base Base Month. Base Basa Month. Revenue Revenue Bill." Rev. Rev. Revenue Bill""" Rev. Revenue Bill". YEAR ($M) (e/KwH) ($) ($M) (e/Kw~ (%) ($) (e/KwH) (%) ($) 1992 $2,234 13.84 $83 n/a nla nla $83 0.000 nla $83 1993 2,341 14.39 86 $1.5 0.69 5.0% 91 0.010 0.1% 86 1994 2,462 14.96 90 7.7 3.43 19.0% 110 0.047 0.3% 90 1995 2,595 15.57 93 11.3 4.97 10.3% 123 0.060 0.1% 94 1996 2,723 16.16 97 15.5 6.70 11.1% 137 0.092 0.2% 98 1997 2,059 16.79 101 20.1 8.62 11.9% 152 0.118 0.2% 101 1998 3,002 17.45 105 25.8 10.94 13.8% 170 0.150 0.2% 106 1999 3,038 17.47 105 31.4 13.20 13.0% 184 0.181 0,2% 106 2000 3,050 17.32 104 37.1 15.39 12.5% 196 0.211 0.2% 105 2001 3,185 17.87 107 44.3 18.15 16.0% 216 0.249 0.2% 109 2002 3,301 18.29 110 50.0 20.22 11.6% 231 0.277 0.2% 111 2003 3,480 19.05 114 53.6 21.42 6.6% UH 243 0.293 0.1% 116 Total $298.3 Notes: The Base Case assumpllon, underlying the lIlCO Rale Moderallon plan as modllted In OpinIon 91- 25, was updated 10 rell9Ct necessary capllal structure modl/lcallons for Scenarlo '28. undergroundlng to be Installed In equaleogmenls ovor 10 years assumes monthly use per resldenllal cuslomor or 600 KwH ~ ~ u ~olallncree.se 10 t?3'O' ff;es by ysa, :<::;03 Is 193% !llndlsn Head ,ntopayers bear the UG cosls . , LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY AUGUST 1992 SCENARIO #2A EFFECT OF UNDERGROUNDING (UG) DISTRIBUTION LINES FROM BUELL SUBSTATION .. 111lernnli....es BUELL RATEPAYERS SERVED FROM ALL ULCO RATEPAYERS UNES BUELL BEAR THE BEAR THE BASE CASE' UG UNDERGROUNDING COSTS UNDERGROUNDING COSTS Approx. Approx. Approx. Iner. Iner. New Iner. New Resld. to to Iner. to Resid. to Iner. to Resld. Base Avg. Month. Base Base Base Monlh. Base Base Month. Revenue Revenue Bill."" Rev. Rev. Revenue Bill"'.. Rev. Revenue Bill'" YEAR ($M) (e/KwH) ($) ($M) (e/Kwf (%) ($) (e/KwH) (%) ($) 1992 $2,234 13.84 $83 nla nla n/a $83 0.000 n/a $83 1993 2,341 14.39 86 $1.5 0.97 7.0% 92 0.009 0.1% 86 1994 2,462 14.96 90 7.3 4.80 26.6% 119 0.044 0.2% 90 1995 2,595 15.57 93 10.7 6.96 14.4% 135 0.064 0.1% 94 1996 2,723 16.16 97 14.5 9.38 15.6% 153 0.086 0.1% 97 1997 2,859 16.79 101 18.9 12.07 16.6% 173 0.111 0.2% 101 1998 3,002 17.45 105 24.2 15.31 19.3% 197 0.141 0.2% 106 1999 3,038 17.47 105 29.6 18.48 18.2% 216 0.170 0.2% 106 2000 3,050 17.32 104 34.9 21.55 17.5% 233 0.198 0.2% 105 2001 3,185 17.87 107 41.7 25.42 22.4% 260 0.234 0.2% 109 2002 3,301 18.29 110 47.0 28.32 16.2% 280 0.260 0.1% 111 2003 3,480 19.05 114 50.4 30.00 9.2% u""" 294 0.276 0.1% 116 TOlal $280.6 Noles: The Base Case assumplloll, underlying Ihe UlCO Rale MOderallon plan 8S modified In Opinion 91-25, was updated 10 rellect necessary capllal structure modlrlcallons for ScenarIo N2A. .. undorgroundlng 10 be Installed In equal segments ovor 10 years ... - assumes monthly use per ros/danllal customo, 01 600 KwH lolallncreaso to base rates by yoar 2003 Is 254% II Buell ratepayers bear Ilia UO costs , LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY DECEMBER 1992 f3ASE c~ INCflEMENTAl EFFECT OF nEPIACING nEAn LOT on tiNeS WITll STD. nUD TVD6 UNOEnGnOUNl}yAULt~ TOT At OF BASE CASE + INCIlEMENTAI.. fTfECT OF PA!:!!~UNnEI~onOUNDING Approx. Base Residential Base Base Monthly Revenue Revenue Bill'" YEAR ($M) (c/KwH) ($) Approx. Incr. to Base Incr. to Incr. to Resident. Base Base Monthly Revenue Revenue BillA-U ($M) (c/KwH) ($) Avg. Approx. Resident. Total Monthly BII'''' Revenue (c/KwH) ($) 1992 $2,234 13.84 $83 $0 nla nla 13.84 $83 1993 2,341 14.39 $86 12 0.Q7 $0 14.46 87 1994 2,462 14.96 $90 29 0.17 1 15.13 91 1995 2,595 15.57 $93 46 0.28 2 15.85 95 1996 2,723 16.16 $97 66 0.39 2 16.55 99 1997 2,859 16.79 $101 87 0.51 3 17.30 104 1998 3,002 17.45 $105 108 0.63 4 18.08 108 1999 3,038 17.47 $105 131 0.75 5 18.22 109 2000 3,050 17.32 $104 155 0.88 5 18.20 109 2001 3,185 17.87 $107 175 0.98 6 18.85 113 2002 3,301 18.29 $110 195 1.08 6 19.37 116 2003 3,480 19.05 $114 217 1.19 7 .... 20.24 121 I Sub- Total $1,223 I 2017 t.UH Noles: TI10 Base Caso assumpUon, UndlYlylng IheLLCO Ralo Mod9'alfon plan as modmed In Opinion 91-25, was updalod 10 reflect noc8s9l1'Y caplal sluchn modlllcaUons tOf' Sconarlo Ii 1. unde-goundlng InslaUadon= $ 1.32 bllllon (1992 OOIl..-s) - to bolnslalled In eqUal segmenls over 25 yoars .... assumes monthly use per residential customer ol600 KwH ...u given an Inaea.. of $ 7 In mo. billa solely due 10 udergroundlng trom S83/mo to S90/mo.- or an IflCfeas8 0' 8.4 " In 11 yoalS; Ihe average Incroase ;0 monlhly bllts would be 0.74 'J(, compoundod annually 80101., due 10 UndOflJ'oUndlng, 1.0. In addltfon 10 Ihe base case Inao8so8 IndleJl\ted .......... I:'ev.g.r~u". t"!,-,;o""oem~N:s .no:: ".a~0~Z:Yo/ ~m3 "VI:! co.,~r~....l!' 10 IrH;"''J'.?!$ao ~~W undergroU!nd1ng complotlon In 29H \ ..--JJA8E CASE' DECEMBER 1992 LONG ISLAND LIGHTING COMPANY UNDERGROUNDING STUDY INCREMENTAL EFFECT OF AfPtACING REAR tor PRIMARY au tiNES WITH UO PfUMAHY IN SIDEWALK AHEAS AND RHAIN 011 TRANSfORMER SfeONllAfIIfS AND SEfJY!l;fS~ TOTAL OF BASt CASE; INeflfMfNTJlI. Hrfer Of PARTiAl UNOfllal!~~QlliQ. Approx, Base Reeldsflllal Base Base Monthly Revenue Revenue Bill""" YEAR ($M) (e/KwH) ($) Approx, tncr, 10 Base tneLlo Iner. to Residant. Bass Bass Monthly Rsvenue Revenue Bill"'""" ($M) (e/KwH) ($) $2,234 2,341 2,462 , 2,595 2,723 2,869 3,002 3,036 3,050 3.165 3,301 3,460 13,64 14.39 14,96 10.57 16.16 16,79 17.45 17.47 17.32 17.67 16.29 19,05 $63 $66 $90 $93 $97 $101 $105 $105 $104 ST07 $110 $114 $0 6 14 23 33 44 54 65 77 67 97 106 $609 n/a 0.04 0.09 0.14 0,20 0,26 0,31 0.3f 0.41 0.41 0.5\ o,m Avg, Revenue (c/KwH) n/n so 1 1 1 2 2 2 3 3 3 Approx, 11esident. rotat Mont/lly Bill'" ($) 1992 1993 1994 1995 1996 1997 1996 1999 2000 2001 2002 2003 I I 2017 """"""""" Nolos: TllO BaSI) Caso "ssUrT\!JDOn, l.Il,dOl'lylng theLI.CO nata ModOfallon plan as modlllodln OphlionI1-25. was updatodlU foiled nlu;li9SIlf y caplalstlJCluro JIlOlllltaltolls IOf Sconwlo IJ I. UII(J(JfgOUIUJil'fJ Ins'allotlon '" $ 0.7 billion (1992 CkIUiWS)- 10 bo Installed In oqIJ81 segrnullts 0191' 25 year, .... assurnos llIo,IIhlVJ90 W H.sJeklnUal cUIlI\lnu.ll (II fHX) KNU ..... \Jlvon an Ina.a,.o of' .. hi mo. billa ftOl.l~ due 10 udOI{poufllJlnu hom $83/mu u S81/mt.- Of an lncruasfl 01 4.6 '" In 11 V'oa'8: Iho ItIIUfalJU IflaOsae 10 OIC>lllh'Y hlllll *uuld be 0.4:1 'H> comlloundud allnllallV' aOI.I, dun 10 undOfyr.)'JIldiflU. Ie. III add/lion 10 'ho b..so c.se Inaoasos Indlctlhtct .......... ~f]v'1~'V(l lfJ'."'J~ ym-:OrJ.. ,.,,,~ ,1!'.~"'r,,~~e1' bl!!'1. 'i"'11! c"I\:lnuu Iu D~Q'OJM.O unlll undOf (JI'oundlOO clmlllellon In 20,1' Sub- Total 13.64 144:1 15,05 15.71 16.36 17.05 17.76 17.85 17.76 16.36 18.83 19.64 4 .......... $83 67 90 94 98 102 t07 107 107 110 113 118 , MAY, 1992 PSC STUDY DETAll.ED ANALYSIS OF COST TO UNDERGROUND SUBST A nON SUMMARY SHEET INDIAN HEAD COST TO INSTALL COST TO REMOVE CIRCUIT UNDERGROUND OVERHEAD * TOTAL COST 6HL- 811 $20,832,700 $2,733,900 $23,566,600 6HL - 812 $31,143,000 $4,023,400 $35,166,400 6HL - 813 $24,052,300 $3,183,200 $27,235,500 6HL - 814 $27,158,200 $3,539,000 $30,697,200 6HL - 815 $17,639,700 $2,256,700 $19,896,400 6HL - 816 $17,869,500 $2,275,400 $20,144,900 TOTAL: $138,695,400 $18,011,600 $156,707,000 * - OVERHEAD REMOVAL COSTS INCLUDE SALVAGE VALUE OF OVERHEAD CONDUCTORS. ~ REV. 06/30/92 MAY, 1992 PSC STUDY DET All..ED A..NAL YSIS OF COST TO UNDERGROUND ($ X (00) SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONAlIZING UNITS CAPACITORS MISC. EQUIPMENT 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT ~ CIRCUIT: COST TO INSTALL 3,676.2 1,255.4 50.1 0.0 0.0 0.0 0.0 2,566.0 44.5 618.7 84.0 0.0 0.0 0.0 0.0 0.0 7,812.0 544.9 2,929.5 1,251.4 0.0 0.0 0.0 0.0 0.0 TOTAL: 6HL- 811 SUBTOTAL $4,981.70 $3,313.2 $12,53'1.8 $20,83:>.f PAGE 1 OF 3 REV. 06/30/92 r ' . , MAY, 1992 PSC STUDY DETAiLED ANALYSIS OF COST TO UNDERGROUND ($ X 000) SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 811 FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 48.5 2 PHASE 5.1 1 PHASE 95.1 SUBTOTAL $148.7 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 18.7 2.8 49.2 23.1 10.8 0.0 0.0 0.0 0.0 0.0 $104.6 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) 8.7 62.7 63.9 24.6 0.0 1,315.4 1,031.7 0.0 0.0 TOTAL: $2,507.0 $2,760.3 ~ PAGE 2 OF 3 MAY, 1992 PSC STUDY DETAIT...ED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL- 811 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $20,832.7 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $2,760.3 3. SALVAGE VALUE OVERHEAD CONDUCTORS ($26.4) TOTAL COST: $23,566.6 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUr"L) DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 201,600 CONDUCTOR FEET OF WIRE AND 11,000 KVA OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DET All.ED ANAL YSrS OF COST TO UNDERGROUND ($ X (00) SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONAUZING UNITS CAPACITORS MISC. EQUIPMENT 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT # CIRCUIT: COSTTO INSTALL 5,395.8 1,842.6 175.6 0.0 0.0 0.0 0.0 3,766.1 73.5 1,096.7 320.0 0.0 0.0 0.0 0.0 0.0 11,466.0 965.8 4,299.8 1,741.1 0.0 0.0 0.0 0.0 0.0 TOTAL: 6HL - 812 SUBTOTAL $7,414.00 $5,256.3 $18,472.7 $31,143.0 PAGE 1 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) SUBSTATION: INDIAN HEAD FACILITIES TO BE REMOVED: 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 2 PHASE 1 PHASE 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) ~ CIRCUIT: COST TO REMOVE 88.6 6.1 103.5 27.5 4.9 87.2 33.9 19.2 0.0 0.0 0.0 0.0 0.0 12.7 111.0 79.2 43.5 0.0 1,930.7 1,514.2 0.0 0.0 TOTAL: 6HL - 812 SUBTOTAL $198.2 $172.7 $3,691.3 $4,062.2 PAGE 2 OF 3 MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 812 1. COST TO INSTALL NEW UNDERGROUND DiSTRIBUTION SYSTEM . . . . . . .. $31,143.0 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $4,062.2 3. SALVAGE VALUE OVERHEAD CONDUCTORS ($38.8) TOTAL COST: $35,166.4 THIS is THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 296,200 CONDUCTOR FEET OF WIRE AND 19,500 KVA OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06{30{92 SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1. 3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT ~ CIRCUIT: COST TO INSTALL 4,298.8 1,468.0 139.9 0.0 0.0 0.0 0.0 3,000.5 60.8 864.4 189.2 0.0 0.0 0.0 0.0 0.0 9,135.0 761.3 3,425.6 708.8 0.0 0.0 0.0 0.0 0.0 TOTAL: 6HL - 813 SUBTOTAL $5,906.70 $4,114.9 $14 Q',("1 "/ 1'<'" ..-., $24,O~,~U; PAGE 1 OF 3 REV. 06/30/92 MAY, 1992 PSC STIJDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 813 FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 90.1 2 PHASE 1.1 1 PHASE 46.6 SUBTOTAL $137.8 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 21.9 3.9 68.7 27.0 15.1 0.0 0.0 0.0 0.0 0.0 $136.6 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) 10.2 87.5 63.1 34.3 0.0 1,538.2 1,206.4 0.0 0.0 $2,939.7 TOTAL: $3,214.1 ~ PAGE 2 OF 3 MAY, 1992 PSC STIJDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 813 1. COST TO INSTAll NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $24,052.3 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $3,214.1 3. SALVAGE VALUE OVERHEAD CONDUCTORS ($30.9) TOTAL COST: $27,235.5 THIS IS THE ESTIMATED TOTAL COST TO INSTAll AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 237,000 CONDUCTOR FEET OF WIRE AND 15,400 'r<YA OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X (00) SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT CIRCUIT: 6HL - 814 COSTrO INSTALL SUBTOTAL 4,713.9 1,609.7 153.4 0.0 0.0 0.0 0.0 $6,477.00 3,290.2 64.2 995.3 238.7 0.0 0.0 0.0 0.0 0.0 $4,588.4 10,017.0 876.6 3,756.4 1,442.8 0.0 0.0 0.0 0.0 0.0 $16,092.8 TOTAL $27,158.2 PAGE 1 OF 3 ~ REV. 06/30/92 MAY, 1992 PSC STUDY DET All..ED ANALYSIS OF COST TO UNDERGROUND ($ X (00) SUBSTATION: INDIAN HEAD FACILITIES TO BE REMOVED: 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 2 PHASE 1 PHASE 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) ~ CIRCUIT: COST TO REMOVE 68.0 1.8 118.4 24.0 4.4 79.1 29.6 17.4 0.0 0.0 0.0 0.0 0.0 11.1 100.8 69.2 39.5 0.0 1,686.7 1,322.9 0.0 0.0 TOTAL: 6HL - 814 SUBTOTAL $188.2 $154.5 $3,230.2 $3,572.9 PAGE 2 OF 3 . , MAY, 1992 PSC STUDY DET All..ED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 814 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $27,158.2 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $3,572.9 3. SALVAGE VALUE OVERHEAD CONDUCTORS ." ........ ($33.9) TOTAL COST: $30,697.2 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 259,800 CONDUCTOR FEET OF WIRE AND 17,700 KYA OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06{30{92 . SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONAUZING UNITS CAPACITORS MISC. EQUIPMENT MAY, 1992 PSC STUDY DETAll.ED ANALYSIS OF COST TO UNDERGROUND ($ X 000) 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT ~ CIRCUIT: COST TO INSTALL 2,952.8 1,008.5 96.1 0.0 0.0 0.0 0.0 2,061.0 40.2 757.7 249.4 0.0 0.0 0.0 0.0 0.0 6,274.8 667.3 2,353.1 1,178.8 0.0 0.0 0.0 0.0 0.0 TOTAL: 6HL - 815 SUBTOTAL $4,057.40 $3,108.3 $10,474.0 $17,639.7' PAGE 1 OF 3 REV. 06/30/92 -,~~~#-~~~~~.,:;;;h~-t.;J::1:j~:~~::':.'"."'~",'~~:'~'~ "",_.~,.~,.,_v"~", . . ,. _ _, __. _ _ ~_,.__,~ g-~':"'S:.F.~--''':lEJ.:.u:.~;.':;,i.:-'"~''':~-' ,.'. ~ - -,"""~<':Li~';<;''''.':'",;;-,,, ,," ';}'}'r,"" '{ '.., ....'.-- ,--. .,. "..:.a.>L-.c..:.-.'--_"''--~,",..",..",;,:. - ,'- MAY, 1992 PSC STUDY DETAll..ED ANALYSIS OF COST TO UNDERGROuND ($ X 000) SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 815 FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 34.4 2 PHASE 4.4 1 PHASE 86.3 SUBTOTAL $125.1 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 15.0 3.4 60.2 18.5 13.3 0.0 0.0 0.0 0.0 0.0 $110A 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) 7.0 76.7 43.3 30.1 0.0 1,056.6 828.7 0.0 0.0 TOTAL: $2,042.4 $2,277.9 ~ PAGE 2 OF 3 , MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 815 1. COST TO INSTAll NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $17,639.7 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $2,277.9 3. SALVAGE VALUE OVERHEAD CONDUCTORS ... ........ ($21.2) TOTAL COST: $19,896.4 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 162,300 CONDUCTOR FEET OF WIRE AND 13,500 ~A OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06/30/92 ii I Ii II , SUBSTATION: INDIAN HEAD FACILITIES TO BE INSTALLED: 1. 3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE SECTIONALlZING UNITS TRANSFORMERS SERVICES MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT ~ CIRCUIT: COST TO INSTALL 2,964.7 1,012.4 96.5 0.0 0.0 0.0 0.0 2,069.3 40.4 896.7 335.4 0.0 0.0 0.0 0.0 0.0 6,300.0 789.7 2,362.5 1,001.9 0.0 0.0 0.0 0.0 0.0 TOTAL: 6HL - 816 SUBTOTAL $4,073.60 $3,341.8 $10,454.1 $17,869.5 PAGE 1 OF 3 REV. 06/30/92 . . MAY, 1992 PSC STUDY DETAilED ANALYSIS OF COST TO UNDERGROm.rn ($ X (00) SUBSTATION: INDIAN HEAD CIRCUIT: FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 55.6 2 PHASE 1.1 1 PHASE 45.6 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) ~ 15.1 4.0 71.3 18.6 15.7 0.0 0.0 0.0 0.0 0.0 7.0 90.8 43.5 35.6 0.0 1,060.8 832.0 0.0 0.0 TOTAL: 6HL - 816 SUBTOTAL $102.3 $124.7 $2,069.7 $2,296.7 PAGE 2 OF 3 MAY, 1992 PSC STUDY DETAILED A.NALYSIS OF COST TO UNDERGROUND ($ X (00) CIRCUIT SUMMARY SHEET SUBSTATION: INDIAN HEAD CIRCUIT: 6HL - 816 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $17,869.5 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $2,296.7 3. SALVAGE VALUE OVERHEAD CONDUCTORS ($21.3) TOTAL COST: $20,144.9 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 163,000 CONDUCTOR FEET OF WIRE AND 15,950 KYA OF DISTRIBUTION TRANSFORMER CAPACITY. ~ PAGE 3 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DETAll..ED ANALYSIS OF COST TO l!NTIERGROUND SUBSTATION SUMMARY SHEET BUELL COST TO INSTALL COST TO REMOVE CIRCUIT UNDERGROUND OVERHEAD * TOTAL COST 9E - 934 $49,436,000 $4,062,000 $53,498,000 9E - 985 $29,995,700 $2,392,900 $32,388,600 9E - 991 $9,445,900 $764,600 $10,210,500 9E - 992 $47,405,700 $3,852,800 $51,258,500 TOTAL: $136.283,300 $11.072.300 $147.355.600 * - OVERHEAD REMOVAL COSTS INCLUDE SALVAGE VALUE OF OVERHEAD CONDUCTORS. ~ REV. 06/30/92 . , SUBSTATION: BUELL MAY, 1992 PSC STUDY DETAll.ED At"lAL YSIS OF COST TO UNDERGROUND ($ X 000) FACILITIES TO BE INSTALLED: 1. 3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT CIRCUIT: COST TO INSTALL 14,085.7 1,072.5 102.3 0.0 0.0 0.0 0.0 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE 953.0 SECTIONALlZING UNITS 600.3 TRANSFORMERS 163.8 SERVICES 482.0 MISC. EQUIPMENT 0.0 0.0 0.0 0.0 0.0 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT LB CTA 21,412.8 2,436.3 6,857.0 1,180.1 0.0 90.2 0.0 0.0 0.0 TOTAL: 9E - 934 SUBTOTAL $15,260.50 $2,199.1 $31,976.4 $49,436.0 PAGE 1 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DETAILED A~AL YSIS OF COST TO UNDERGRotJND ($ X 000) SUBSTATION: BUELL FACILITIES TO BE REMOVED: 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 2 PHASE 1 PHASE 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WlRE SERVICES MISC. EQUIPMENT 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WlRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) CIRCUIT: 9E - 934 COST TO REMOVE 106.7 8.1 140.4 12.9 4.1 7.9 21.8 0.8 0.0 0.0 0.0 0.0 0.0 7.4 212.3 151.7 106.2 0.0 3,173.0 274.2 0.0 0.0 TOTAL: SUBTOTAL $255.2 $47.5 $3,924.8 $4,227.5 PAGE 2 OF 3 - MAY, 1992 PSC STUDY DETAll..ED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: BUELL CIRCUIT: 9E - 934 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . ., $49,436.0 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . ., $4,227.5 3. SALVAGE VALUE OVERHEAD CONDUCTORS ... ........ ($165.5) TOTAL COST: $53,498.0 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 391,950 CONDUCTOR FEET OF WIRE AND 25,500KVA OF DISTRIBUTION TRANSFORMER CAPACITY. PAGE 3 OF 3 REV. 06/30/92 ~ " SUBSTATION: BUELL MAY, 1992 PSC STIJDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X (00) FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT CIRCUIT: COST TO INSTALL 8,398.3 639.5 61.0 0.0 0.0 0.0 0.0 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE 568.2 SECTIONALIZING UNITS 357.9 TRANSFORMERS 124.0 SERVICES 152.7 MISC. EQUIPMENT 0.0 0.0 0.0 0.0 0.0 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT LBCTA ~ 12,766.9 1,843.9 4,088.3 941.2 0.0 53.8 0.0 0.0 0.0 TOTAL: 9E - 985 SUBTOTAL $9,098.80 $1,202.8 $19,694.1 $29,995.7 PAGE 1 OF 3 REV. 06/30192 - -- MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) SUBSTATION: BUELL CIRCUIT: 9E - 985 FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 68.3 2 PHASE 0.0 1 PHASE 81.3 SUBTOTAL $149.6 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 7.7 3.1 5.9 13.0 0.6 0.0 0.0 0.0 0.0 0.0 $30.8 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWT') REMOVE POLE (RP) 4.4 160.7 90.4 0.9 0.0 1,891.8 163.5 0.0 0.0 TOTAL: $2,311.7 $2,491.(\ ~ PAGE 2 OF 3 ,.". ~.,<'-"~"".~"-"'~.'. ,''''~-~'_'~''''~,..,~.<"-~"_.,,..-..,,.~~._.,..~~.-.---- -. -~ . ...~..,,,.,.,,. " ""...,~'" "..., 'q' ,. -'_._'""-'.'-'~'.""''' . I . MAY, 1992 PSC STUDY DETAlLED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET SUBSTATION: BUELL CIRCUIT: 9E - 985 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $29,995.7 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . .. $2,491.6 3. SALVAGE VALUE OVERHEAD CONDUCTORS ($98.7) TOTAL COST: $32,388.6 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 233,550 CONDUCTOR FEET OF WIRE AND 19,200 KVA OF DISTRIBUTION TRANSFORMER CAPACITY. PAGE 3 OF 3 REV. 06/30/92 MAY, 1992 PSC STUDY DETAILED ANALYSIS OF cosr TO UNDERGROUND ($ X (00) 2. 3 PHASE SUPPUES (LOOPED & RADIAL) PRIMARY CABLE 182.5 SECTIONAUZING UNITS 115.0 TRANSFORMERS 30.8 SERVICES 111.8 MISC. EQUIPMENT 0.0 0.0 0.0 0.0 0.0 SUBSTATION: BUELL FACILITIES TO BE INSTALLED: 1. 3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT LB CT A - CIRCUIT: COST TO INSTALL 2,697.5 205.4 19.6 0.0 0.0 0.0 0.0 4,100.8 458.6 1,313.2 193.4 0.0 17.3 0.0 0.0 0.0 TOTAL: 9E - 991 SUBTOTAL $2,922.50 $440.1 $6,083.3 $9,445JJ PAGE 1 OF 3 REV. 06/30/92 ~ . j MAY, 1992 PSC STUDY DET AILED ANALYSIS OF COST TO UNDERGROUND ($ X 000) SUBSTATION: CIRCUIT: BUELL FACILITIES TO BE REMOVED: COST TO REMOVE 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 32.8 2 PHASE 0.0 1 PHASE 3.3 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 2.8 0.8 1.5 4.2 0.2 0.0 0.0 '0.0 0.0 0.0 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS 1.4 TRANSFORMERS 40.0 SECONDARY WIRE 29.1 SERVICES 20.0 MISC. EQUIPMENT 0.0 REMOVE POLE (HWY) 607.7 REMOVE POLE (RP) 52.5 0.0 0.0 TOTAL: 9E - 991 PAGE 2 OF 3 SUBTOTAL $36.1 $9.5 $750.7 $796.3 -- . . MAY, 1992 PSC STUDY DETAILED ANALYSIS OF COST TO UNDERGROUND ($ X (00) CIRCUIT SUMMARY SHEET SUBSTATION: BUELL CIRCUIT: 9E - 991 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $9,445.9 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM $796.3 3. SALVAGE VALUE OVERHEAD CONDUCTORS ... ........ ($31.7) TOTAL COST: $10,210.5 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 75,000 CONDUCTOR FEET OF WIRE AND 4,800 KNA OF DISTRIBUTION TRANSFORMER CAPACITY. PAGE 3 OF 3 REV. 06/30/92 -- . , . SUBSTATION: BUELL MAY, 1992 PSC STUDY DEfAll..ED ANALYSIS OF COST TO UNDERGROUND ($ X (00) FACILITIES TO BE INSTALLED: 1.3 PHASE U.G. MAIN PRIMARY CABLE SECTIONALlZING UNITS CAPACITORS MISC. EQUIPMENT CIRCUIT: COST TO INSTALL 13,288.4 1,011.8 96.5 0.0 0.0 0.0 0.0 2. 3 PHASE SUPPLIES (LOOPED & RADIAL) PRI MARY CABLE 899.1 SECTIONALlZING UNITS 566.3 TRANSFORMERS 160.6 SERVICES 479.5 MISC. EQUIPMENT 0.0 0.0 0.0 0.0 0.0 3. 1 PHASE SUPPLIES (LOOPED & RADIAL) PRIMARY CABLE TRANSFORMERS SECONDARY CABLE SERVICES MISC. EQUIPMENT LB CT A - 20,200.8 2,388.5 6,468.9 1,760.2 0.0 85.1 0.0 0.0 0.0 TOTAL: 9E - 992 SUBTOTAL $14,396.70 S2,105.G $30,903.5 $47,405.'/ PAGE 1 OF 3 REV. 06/30/92 ,. , . , . MAY, 1992 PSC STUDY DET All..ED ANALYSIS OF COST TO UNDERGROUND (S X 000) SUBSTATION: BUELL FACILITIES TO BE REMOVED: 1. OVERHEAD PRIMARY CONDUCTORS 3 PHASE 2 PHASE 1 PHASE 2. 3 PHASE EQUIPMENT SWITCHES CAPACITORS 3 PHASE TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT 3. BRANCH LINE EQUIPMENT FUSED CUTOUTS TRANSFORMERS SECONDARY WIRE SERVICES MISC. EQUIPMENT REMOVE POLE (HWY) REMOVE POLE (RP) CIRCUIT: COST TO REMOVE 93.2 7.6 148.4 12.2 4.0 7.7 20.6 0.8 0.0 0.0 0.0 0.0 0.0 7.0 208.1 143.1 104.1 0.0 2,993.4 258.7 0.0 0.0 TOTAL: III U 9E - 992 SUBTOTAL $249.2 $~t~.~'~ "'3 -,'<(. (. ~l..1 I.., $4,ooe.p PAGE 2 OF 3 ..., . MAY, 1992 PSC STUDY DET AlLED ANALYSIS OF COST TO UNDERGROUND ($ X 000) CIRCUIT SUMMARY SHEET ;UBSTATION: BUELL CIRCUIT: 9E - 992 1. COST TO INSTALL NEW UNDERGROUND DISTRIBUTION SYSTEM . . . . . . .. $47,405.7 2. COST TO REMOVE EXISTING OVERHEAD DISTRIBUTION SYSTEM . . . . . . " $4,008.9 3. SALVAGE VALUE OVERHEAD CONDUCTORS ... ......... ($156.1) TOTAL COST: $51,258.5 THIS IS THE ESTIMATED TOTAL COST TO INSTALL AN UNDERGROUND DISTRIBUTION SYSTEM THAT WOULD BE REQUIRED TO REPLACE AN EXISTING OVERHEAD DISTRIBUTION SYSTEM COMPRISED OF APPROXIMATELY 370,000 CONDUCTOR FEET OF WIRE AND 24,900KVA OF DISTRIBUTION TRANSFORMER CAPACITY. - PAGE 3 OF 3 REV. 06/30/92