HomeMy WebLinkAbout32569-Z
FORM NO. 4
TOWN OF SOUTHOLD
BUILDING DEPARTMENT
Office of the Building Inspector
Town Hall
Southold, N.Y.
..
CERTIFICATE OF OCCUPANCY
No: Z-32598 Date: 09/13/07
THIS CERTIFIES that the building INDUSTRIAL BUILDING
Location of Property: 315
(HOUSE NO.)
County Tax Map No. 473889 Section 96
COMMERCE DRIVE
(STREET)
Block L-
CUTCHOGUE
(HAMLET)
Lot 1. 8
SUbdivision
Filed Map No.
Lot No.
conforms substantially to the Application for Building Permit heretofore
filed in this office dated
NOVEMBER 21, 2006 pursuant to which
Building Permit No. 32569-Z
dated
DECEMBER 14, 2006
was issued, and conforms to all of the requirements of the applicable
provisions of the law. The occupancy for which this certificate is issued
is LIGHT INDUSTRIAL BUILDING (8 UNITS) AS APPLIED FOR.
The certificate is issued to M&R SOUTHOLD PROPS LLC
(OWNER)
of the aforesaid building.
SUFFOLK COUNTY DEPARTMENT OF HEALTH APPROVAL C10-06-0005
09/11/07
ELECTRICAL CERTIFICATE NO.
112956C
08/30/07
PLUMBERS CERTIFICATION DATED
08/06/07 MATTITUCK PLUMB.&HEATING
~iZ~~~-
Rev. 1/81
Sf:.,
,t, :
.'
Form No.6
TOWN OF SOUTHOLD
BUILDI:O~E:~TMENT ,.- J.,~~- @- II,' o~}irc ILu"
765-1802 I, J I ' LJ
\I'PLH' \TION FOR CERTIFICATE OF OCCUPANCY. L
bLl. '.'. DEP-:-.
, TC"\lN ('0 "'". 'THO' 'J I
This application must be: filled In hy [ypnvnter or ink and submitted to the Building Departrhent-'WJth-ttre"'foHowTIlg:--'
A. For new building or lIew use:
I. Final snrvey or pJopcrty \\'JIll accurate location of all buildings, property lines, streets, and unusual natural or
topographic features.
2. Final Approval from lIealth Dept. or water supply and sewerage-disposal (S-9 fonn).
3. Approval of elcctIical installation from Board of Fire Underwriters.
4. Sworn statement from plumber cet1ifying that the solder used in system contains less than 2/] 0 of I % lead.
5. COlllmercial building, industrial building, multiple residences and similar buildings and installations, a certificate
of Code Compliance from architect or engineer responsible for the building.
6. Submit Planning Board Approval of completed site plan requirements.
B. For existing buildings (prior to April 9, 1957) non-conforming uses, or buildings aud "pre-existing" laud uses:
1. Accurate survey of propeliy showing all property lines, streets, building and unusual natural or topographic
features.
2. A properly completed application and consent to inspect signed by the applicant. If a Certificate of Occupancy is
denied, the Building Inspector shall state the reasons therefor in writing to the applicant.
C. Fees
I. Cel1ificate of Occupancy - New dwelling $25.00, Additions to dwelling $25.00, Alterations to dwelling $25.00,
Swimming pool .$25.00, Accessory building $25.00, Additions to accessory building $25.00, Businesses $50.00.
2. Certificate of Occupancy on Pre-existing Building - $100.00
3. Copy ofCertiticilte of Occupancy - $.25
4. Updated Certiticate of Occupancy -- $50.00
5. Temporary Certiticate of Occupancy - Residential $15.00, Commercial $15.00
Date. ~_~~____
New Constmction: __ _./___ Old or Pre-existing Building:
Location of Property ____ CCli"Cl(Yle 1Y' 0 . \)ri\M'
Housc No. Street
(check one)
Owner or Ownels of PropeJ1y: ~Sc \...', \\
~
C. 11- (" ..ho~~lJ q 3S_
<J Hamlet
'\ZO(Y)(ln \A/I \ i f1S k::L_ __________
q&; Lotl-"L~ ____
Suffolk County Tax Map No 1000, Section IObD - ~- ~lock
Subdivision
Peomt No. ~-G~-
Health Dept. Approval: _
Filed Map. _______ Lot:
ApplicantM..+.Q.. '1>rQP2rhe-s
Underwriters Approval: ____ ______
Date of Permit.
Planning Board Approval:L.
Request for:
Temporary Certificate___
Final Certificate: _.L.__ (check onel
Fee Submitted $ J 50 . t;()
~
Applicant Signature
c.--O~1,.JC:;ltc-'
FORM NO. 3
TOWN OF SOUTHOLD
BUILDING DEPARTMENT
Town Hall
Southold, N.Y.
BUILDING PERMIT
(THIS PERMIT MUST BE KEPT ON THE PREMISES UNTIL FULL
COMPLETION OF THE WORK AUTHORIZED)
PERMIT NO.
32569 Z
Date DECEMBER 14, 2006
permission is hereby granted to:
M&R SOUTHOLD PROPS LLC
PO BOX 890
SOUTHOLD,NY 11971
for :
l'l 1I,..M-a. )
BUILDING AS APPLIED
FOR PER
CONSTRUCTION OF A LIGHT INDUSTRIAL
PLANNING BOARD APPROVAL.
at premises located at
20345 CR 48
CUTCHOGUE
County Tax Map No. 473889 Section 096
Block 0001
Lot No. 001.008
pursuant to application dated NOVEMBER 21, 2006 and approved by the
Building Inspector to expire on JUNE 14, 2008.
Fee $
2,180.00
,LClL
Authorized Signature
ORIGINAL
Rev. 5/8/02
Town Hall, 53095 Main Road
P.O. Box 1179
Southold, New York 11971-0959
Fax (631) 765-9502
Telephone (631) 765-1802
BUILDING DEPARTMENT
TOWN OF SOUTHOLD
CERTIFICATION
~~5~1
5~',LL
nM,_ i~ 7
Building Permit No.
Owner:/I1.+R..k
(Please print)
Plumber:. ;v'lA-/-t:J,,-h. PLt/~
(Please print)
lead.
I celiify that the solder used in the water supply system contains less than 2/J () of 1%
PL4"J
-=::>
Sworn to before me this J.!!-_
day of ~_, 20/2-1-_
L~~ ~ _~
DENISE KING " rk
bl Slate of New ,0
Notary Pu .'e, #01 K16041757
RegIstration
Qualified in Suffolk Co~~ty 2 ~
My Commission Expires May,
Notary PUbli~ll~ County
KENNETH L. EDWARDS
MARTIN H. SIDOR
GEORGE D. SOLOMON
JOSEPH L. TOWNSEND
/,7,fd~
MAIlJNG ADDRESS:
P.O. Box 1179
Southold, NY 11971
OFFICE WCAll0N:
Town Hall Annex
54375 State Route 25
(cor. Main Rd. & Youngs Ave.)
Southold, NY
Telephone: 631 765-1938
Fax: 631 765-3136
PLANNING BOARD MEMBERS
JERILYN B. WOODHOUSE
Chair
August 21, 2007
PLANNING BOARD OFFICE
TOWN OF SOUTH OLD
I.
72-;:---'
Mr. Mark Schill
M & R Properties
PO Box 890
Southold, NY 11971
~! Ie; i 8
7
Re: Proposed site plan for M & R Development
Located at approximately 218 slo Corporate Drive on the wlslo Commerce
in Cutchogue. SCTM#(s) 1000-96.-1-1.8 Zone: LI (Light Industria~
Dear Mr. Schill,
At the written request of Mark Schill date received August 14, 2007 requesting final site
plan inspection, Planning Department staff performed a site visit on August 20, 2007. In
reference to the above, the Planning Board held a work session on August 20, 2007 to
discuss the submitted letter, including the approved site plan.
This is to inform you that the site plan requirements have been satisfied and include the
following items:
· The Planning Board approves the installation of all landscaping in the Fall of
2007. The Planning Board recognizes that, due to weather constraints, this will
be completed no later than November 29,2007. If the landscaping is not
installed by November 29,2007, the applicant must request an extension from
the Planning Board, in writing, detailing the expected time of completion.
· All handicap parking stalls, access aisles and signage must comply with New
York State Code and ADA requirements.
· The Planning Board approves the installation of the cupola and awnings at the
discretion of the Building Department requirements. The Planning Board
recognizes that, due to financial restraints this will be completed in the future.
· All outdoor lighting shall be shielded so that the light source is not visible from
adjacent properties and roadways. Lighting fixtures shall focus and direct the
light in such a manner as to contain the light and glare within property
boundaries. All lighting must meet town code requirements.
M & R Development
Page Two
August 21, 2007
· As per landscape survivability, the applicant agrees to replace any of the
landscaping which dies within three (3) years of planting.
This letter does not condone any changes from the as-built site plan and approvals from
other agencies if required.
Respectfully yours,
/i ,;::kJ~
~Oodhouse
Chairperson
Cc: File, Building Department, Engineering Department, James De Lucca
JAMES J. DEERKOSKI, P.E.
260 Deer Drive
Mattituck, N.Y. 11952
(631) 298-7116
Date: June 26, 2007
To: Town of South old Building Dept.
Fire wall Rating
M&R Southold Properties
Lot II North Fork Industrial Park
Cutchogue, NY 11935
To Whom It May Concern:
-- .
f- -- --,
'0'(LrnU\'l~1
I~u \]27"~:
.-.J I
bd); OEP~
___J!,WN OF l'" 'THO'
Enclosed is the fire wall system that the industrial building will be using instead of the
one specified in the original plans. This will be set up for the 3 Hr Rating. The UL
Design is # U055 (as per attached). Any questions feel free to call.
\
\~
\ '\"
.
\
\ Sincerely
\JJ~"
\
. \
'\
UL Online Certifications Directory
OCD Home Quick Guide Contact Us UL.com
BXUV.U055
Fire Resistance Ratings - ANSI/UL 263
Page Bottom
Fire Resistance Ratings - ANSI/UL 263
See General Information for Fire Resistance Ratings - ANSI/UL 263
Design No. VOSS
August 29, 2006
Nonbearing Wall Ratings - 1-1/2, 2 or 3 Hr (See Item 4)
1-112 HR CONFIGURATION
4
2 HR CONFIGURATION
4
:> HR CONFIGURATION
4
1. Floor and Ceiling Runners - (Not shown) - Channel
shaped, fabricated from min 22 MSG corrosion-protected steel,
min width to accommodate stud size, with min 1-1/4 in. long legs,
attached to floor and ceiling with fasteners 24 in. OC max.
2. Steel Studs - Channel shaped, fabricated from min 22 MSG
corrosion-protected steel, min width as indicated under Item 4, min
1-1/2 in. flanges, spaced a max of24 in. OC. Studs to be cut 3/4 in.
less than assembly height.
3. Batts and Blankets* - Mineral wool batts, friction fitted
between studs and runners. Min nom thickness and min density as
indicated under Item 4. See Batts and Blankets (BKNV or
BZJZ) Categories for names of Classified companies.
4. Building Units* - 4 ft. wide Type Dragonboard magnesium
oxide panels.
1-1/2 Hr Rating - Outer surface of steel studs (Item 2)
covered with gasket tape (Item 5) prior to panel installation.
Panels installed vertically with vertical joints centered over
studs and staggered from vertical joints on opposite side of
studs. Horizontal joints staggered from horizontal joints on
opposite side of studs and backed by a min 20 MSG, nom 3-
1/2 in. wide steel nailer plate (not shown) centered behind
the horizontal joint. Outer surface of steel nailer plate
covered with gasket tape (Item 5). Plate secured to steel
studs prior to panel placement. Max 1/16 in. separation at all
panel joints. Joint separation completely filled with fill
material (Item 6). Panels attached to studs and plates with 1-
1/4 in. long bugle head screws spaced 6 in. OC max at the
perimeter and in the field.
2 Hr Rating - Outer surface of steel studs (Item 2) covered
with gasket tape (Item 5) prior to panel installation. Panels
installed vertically with vertical joints centered over studs and
staggered from vertical joints on opposite side of studs.
Horizontal joints staggered from horizontal joints on opposite
side of studs and backed by a min 20 MSG, nom 4 in. wide
steel nailer plate (not shown) centered behind the horizontal
joint. Outer surface of steel nailer plate covered with gasket
tape (Item 5). Plate secured to steel studs prior to panel
placement. Panel joints filled with a 3/16 in. bead of fill
material (Item 6) and butted tight. Panels attached to studs
and plates with 2 in. long bugle head screws spaced 6 in.
OC max at the perimeter and in the field.
3 Hr Rating - A 3 in. wide strip of Type Dragonboard
magnesium oxide panel is secured to the outer surface of
steel studs (Item 2) prior to panel placement. Panels
installed vertically with vertical joints centered over studs and
staggered from vertical joints on opposite side of studs.
Horizontal joints staggered from horizontal joints on opposite
side of studs and backed by a min 18 MSG, nom 4 in. wide
steel nailer plate (not shown) centered behind the horizontal
joint. Plate secured to steel studs prior to panel placement.
Panel joints filled with a 3/16 in. bead of fill material (Item 6)
and butted tight. Panels attached to studs and plates with 2
in. long bugle head screws spaced 6 in. OC max at the
perimeter and in the field.
The min stud depth and thickness of insulation for the 1-1/2
hr, 2 hrand 3 hr ratings are as follows:
Min Stud Min Thickness Min Density
Rating, Depth, in. of Insulation of Insulation
Hr (Item 2) (Item 3) (Item 3)
1-1/2 3-5/8 3 in. 5.7 pcf
2 3-5/8 4 in. 6.1 pcf
3 4 4in. 6.1 pef
DRAGONBOARD INC - Nom 9/16 in. thick Type
Dragonboard.
5. Gasket Tape - Foam isolator tape with foiled backing, 1-1/4
in. wide by 1/8 in. thick, with pressure-sensitive adhesive on one
side.
6. Fill, Void or Cavity Materials* - All vertical and horizontal
joints of building unit panels covered with a 4 in. wide, min 1/8 in.
thick layer of fill material. Screw heads covered with fill material.
~
..0
E
Q)
en
en
<(
,/I
/
co
$
!-. C!
::::J ::)
0 0
I:
I (l)
Q)
Q)
!-.
r
t-
"
.
"
'~ 'i
''01
..'"
;,.lo.
:.;.:" :~i, 00
,-
.
;
~
'"
'0
L
rn
o
ID
c
o
Ol,
e: ;:;:
o 'Sf
: ~"
~' ;~
~
:--'
:.:r '0 "'t
& B C
"j (j) . 'O.~
It ~ ~ B c
CJ u . en ·
co ~ OlW E
T"'" :J C :0
I · C :i.
I CJ. U
I <0 r; ·
t ...u~
'.
"
,,\
'"
N
~
N
::
J
ID
o
" 0
'"
~ l, '
co ~~.
o
11.
U
~
.
L
U
en
C
Q
en
~
"
o
N
&'
~~.
'0
L
.
o
-. ID
C
o
Ol
~
o
.
~:'
"
0-
-
- <.:'
"
<
"
;;-;- -
"
~"
"
I.
",.}
co
, '"
'....."t"",~t.
,
...
"
"
"
,
'0\,
'~
.
....,to
. ,
~. '"
>
VUll j. j. l...VVI llVII 1/::..' I. 1 J JI \.I'VuIVJlJ.,;,f\ uL,t\V lVL.
-~. ".-.
rnfl. f1V,
r, Ul
BXUV.UOSS - Fire Resistanee Ratings - ANSlIUL 263
Page 1 of2
-@ OIlIlIllIlEBTIFIUTlOR. DIAI!IlTIIRY
BXUV.U055
Fire Resl&bl"ce Ratings - ANSl/UL 263
w._
Fire Resistance Ratings - ANSI/UL 263
su...GenmU~'" RI5I,..nc@ ClAtlRM ~. ANSUW..263
_. No. UO$l
A~l.lIt ~I 2006
Non...rtna WaU RatIng. - '..1/2, Z or 3 Hr (ae. ft... 4)
1-112 HR Ctl"'FIGUR!\lION
Z HR CONFIGURATION
.
3 HR COfJFIOUR...TOI
tt-w);. tt1
t. Ploof..... CellI'''' _."".111- (Not thown) - cnanneJ Ihlped, f,~'ram mIn 22 M5G ~tected steel,
mln wldttl to accommodateltUd lID, writh mitll ~1/" 'ft. long a.gs, act:Kfted to floor aPd ~InO with fasteners 24 In. OC
max,
2. stAte'StUn _ Chonnel shapelt fabriated from mln 2:1 HSG QHTOSIOn~protarted steel, tnIn vWdth IS Indic:lI:ed under
Item 4, rnln 1~1'2 1tI. Rianoes, IlJlCed I IN~ d 24 In. ce. Studl to be w[ 3';' in. ~ ctu.1\ asse~y height,
3. a.ttIand ......... - ~ woDl baas. rrtclIon Htred between ItuM and NnMI'$. Hln nom thickness end m1n
den51ty allndlated uNler ltern 4. See ........ Am". C"MY er WI) categor~I'or names of OIIIIfted
companIes.
4. a"Udlng Unlttl. - .. ft. wide T'fPO Oragonooard mD9nesium C>>lik$e pMlea,.
1..1/2 Hr Ratino _ Outer surface 01 sreef il;vdl (Item 2) covered with gi5Mt tape (Item 5) pr1O( to pptlln~letton.
hrtn:/Idatabase.ul.comlcgi-binIXYV ItemplatelLlSEXT/1 FRAMElshowpage.html?name~B... 6/1112007
.,.......
d_ .. ." "'U..-.v'''",'' ..-......, . v....
,.... 'IV.
Vc
BXUV.U055 - Fire Resistance Ratings - ANSllUL 263
Page 2 of2
.
.,
Panels ll'lstaUed vertlClIIV with vertical JOInts cenrered over studs tlnd staggered tram venital jOints on opposite &Ide of
studS. HorIzontal JOints staQOfred from nol'11ootal JointS on oppoa;itc 'Ide of studs .n4 backed by I mlt\ 20 MSG, nom 3-1/2
In. wide steel nailer p1a~ (not shown) cemrred btI'llnd the hOrllootal Joint. Outer wrfitf;e of st.et nailer plat@ covered with
QI~et tape (1t8m 5). Plata secured to Reel $tuM priM to pantl placement. Max 1/16 In. ~r6tlon at an ~nel JOInts. )oInt
~aratlon completely fllllKl with f1_ matlrtel (item 6). Panels atblct'led to studs IInd plates with 1-1/4 In. long bugle Mad
S<:I"'l!WS spaced 6 In. OC milt at the perlmetl!lr and In tht ttetd.
Z "r Radng _ Ol,ltcr 51...1tce 01 steel 5tud~ (Item 2) t:overed with gaSket tape. (Itern 5) prior to p.neIIMtallilltlon. PlMl&
'n5ta1led vertUlly wtth vertiCIl Joints cent~ over 5tUClS and staggered (rom vent4;;., jOints on oppoSite steie of 6tu4s.
HOr~ont.al JOints 5tlogered from f'lotI2:ontal JOIntS on oppoSite side of ItudS 100 backed by a mll'l 20 MSG, I\om 4 In. wlete
steel nilt.r plate (not shOwn) centered behind the honzontll joint. Outer ~rflCe 01 steel Oilier place covered witt'l gasket
~pe (Item 5). ptate secured to steel $tu(l, prior to panel placement. Panel jolnl5 filleel with it 3116 tn. beed of "11 matenlJl
(Item 6) ilnd butted tilJI1t. panels attil,helS to mds anCl plates with 2 In. lOng bUgle Mac! screws 5QecIKI fltn. OC mall,!lt
the pf:f"lmeter and In the hek;l,
3 Hr Riltine _ A 3 In. wtde strip of Type oragonboarel mDgoetlum oxkle PJnel i$ secured to the outer surf,,, of $tH'
studs (ltem 2) Pf"Or to panfl placement. Paneli ifllttlled vertlc"ty wltr'l vertical Joints centered oytr stude and ltaQOtrM
from veracal joints on opposite ~de of ,tuds. Hortzontll joints staggcreo from honlOntal jOints on op~tf Side of $tuds
and backed bv I mln 18 MSG. nom" In. wide steel naUtr plate (ACt IhQWn) centered betllnC! me horizont.!ll JOint. Plitt
secureCl ttI steel iNets pr10r to Pfl"*1 placement. Panel Jotnt~ filled with a 311611'1. be:id at fill material (Item 6) end butted
Ught. Portels attached to studs and plates with 2 In. long bugle heM '0'eWS Spaleo 6 In. OC !'Nil at t~ perlm~tr and lf1
the tleld.
The mln <<lid depth 11'1(1 thickness d Insulatlon for the 1-1/2I\r, 2 hrend 31'lr ratings are ~S follOWS:
Mln Sbld "kI 1b~n Mill Denalty
RAting, 00......... of lrtMlalloa ofl....._
II< (nom 2) (I...... .) (Item])
1-1/2 '-518 3 In. 5.7 pcr
2 3.5/8 41n. 6.lpd
] . 4 In. 6.lpd
DRAGONBOARD JNC - Nom 9/1611\. thICk TYpe Dr800nboird.
S. GIIHetTllpe _ Foam Isolator tope with folleld bilcklng, 1.1/4 In. wide by 118m. thICk, wttf\ pressure-sen~tlVe aOheslve
on one 51t1..
Go f1H, Void Qr cavity' M.t.r"". - All vertical and l'lort2ontal jOint, tJI building unft panelS covered wit" a 4 In. wldt, mfl\
lIe In. thick If,yer 0' nu mmri.l. SCrew h_ds covered wltfl (III mateN!.
PASSIVE Flft. pltOTECnON PA~IR5 - Type 4800DW SC(III"nt.
*89ri"9 the UL Clas&lnCBtlOn Martl
~ataJ1 on 2006.08-29
Oll<i\Jon.i1
_ oUlW:IJImer
1'i9...I1lP
CiWVrlQl1t c::t '007 UOdf./'loWrlt,.1"!\ L.1obofataw...lnt.1Il
Thfl appeanrKe 0' 8 companv's name or produa In tMs detabale doe' not In Itself assure that produCtS SO lden[.ifit(ll'll...e been rNnurDdured
under Ul:S follOW-UP Ser'IItc.e. only those products beoring the UL Hiirk GnQuld be consJdlred to be LiSted and covered under UL'5 follow.Up
Service. Always look for the MIOl o*, the product.
Ul permIts the reprodUCtion or tne mater"l cOI'ltalned In t". Onlloe Certirlt:&DOn Directory liubJect to U"Ie rollowlng tOf'lmtlons: ),. The Guide
Informadon, Delltgrt5 bfldlor UiCinOIi (Nei) must De preMnted In theIr entlretv and jn . non-m1sl9dil'O mel\Mlf. without uy manipulttlan of the
dott {or drtlWlAg$}. 2. Tne stitWmetlt "Repnnted trom the Online Certlflf;H!Of\S Dlrec;.tory Wlttl permlsston rrom Underwriters laborltorlll!'S Inc." must
appear .dj8t:ent 10 tha .xtracted material. 11'1 IOdlClon, the rtlP!inled material must Indu4f a copyrt/iltlt notiCI In the following format: "'(:opynlJhl Q
2007 undtrwritet5 LilbOrlitorleS Inc.(i)"
^I'I ittdlllrndu," Uf9'ftll6lHIR wor~illg lor ~ 'll<l' world \fI'lln lnl~afllt. ploti,iofl '1'10 Ipl~wl..dIlG
~
~
http://database.ul.com!cgi.binlXYV ItcmplatelLISEXTIl FRAME/showpage.htrnI?name--B... 6/1112007
3 ()-S~~ :z-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1ST
[ ] FOUNDATION 2ND
[ ] FRAMING I STRAPPING
[ ] FIREPLACE & CHIMNEY
[ ] RRE RESISTANT CONSTRUC'nON
REMARKS:
[ ] ROUGH PLBG.
[ ] INSULATION
[/(FINAL
[ ] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT PENElRAnON
F ~ ~;ped:ui:
~ ok i
~ 0>-- ~
DATE
7-t.-o1
INSPECTOR ~, ~
'3;;- s~ r ::z-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
] FOUNDATION 1 ST [ ] ROUGH PLBG.
] FOUNDATION 2ND r'><[INSULATION -) _. v/ 'iI..P...)
] FRAMING I STRAPPING ~ FINAL .GE ~ fc........
] FIREPLACE & CHIMNEY [] FIRE SAFETY INSPECTION {if .",
[ ] FIRE RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRATION e... _.~
. ;
RE~~:;:; <~L~
. i ' /,.......J.- ~ I I
~ ~ 'L~yj"..,L.,
~'l:7
J\t ~~
r.-W. r
,
./
,-
d...
~-~8
f
DATE
'! ~I f,... D 7
INSPECTOR~ ~
J~S~1 ::z-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1ST
[ ] FOUNDATION 2ND
[ ] FRAMING I STRAPPING
[ ] FIREPLACE & CHIMNEY
[ ] FIRE RESISTANT CONSTRUCTION
REMARKS:
D< ROUGH PLBG.
[ ] INSULATION
[ ] FINAL
[ ] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT PENETRATION
,
~()
,
DATE
7-/3--()7
INSPECTOR
~~
3 ?-50/ :2-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1 ST
[ ] FOUNDATION 2ND
[ ] FRAMING I STRAPPING
[ ] FIREPLACE & CHIMNEY
[ ] FIRE RESISTANT CONSTRUCTION
[ ] ROUGH PLBG.
MlNSULATION
[ ] FINAL
[ ] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT PENETRATION
REMARKS:~
~b~~
~f1A;rM ...
DATE v~;;"'~07
INSPECTOR ~~
52561
---'-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1 ST
[ ] FOUNDATION 2ND
[ ] FRAMING I STRAPPING
[ ] FIREPLACE & CHIMNEY
[ ] FIRE RESISTANT CONSTRucnoN
REMARKS:
[ ] ROUGH PLBG.
[ ] INSULATION
[ ] FINAL
~IRE SAFETY INSPECTION
[ ] FIRE RESISTANT PENETRATION
fl11frl;l(J A{;S Fo!2- '( 1::;/l/1r1lJ ~Ef/tf2!R7(j\J5
.
--H~0~ 70 ~lE CLe-.ILA EO ~~
WJuR. uffi/6rV f/fUJff1;5)I{)(Ij/fL
DATE -(j - 7 -- 0 7 INSPECTOR
~ 2S'G, 9-c
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1ST [~UGH PLBG.
[ ] FOUNDATION 2ND [ ] INSULATION
[ ] FRAMING I STRAPPING [] FINAL
[ ] FIREPLACE & CHIMNEY [] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRATION
REMARKS: {,,)/TstL ~ J~ c/c .
'p~.
\
DATE~ {'I- /07
I
INSPECTOR
-
~ ),-t{~ l ~.
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1 ST [ ~GH PLBG.
[ ] FOUNDATION 2ND [ ] INSULATION
[ ] FRAMING I STRAPPING [J FINAL
[ ] FIREPLACE & CHIMNEY [J FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRATION
REMARKS: ,#l~ cf:~ /111 t,/~ I~
J,/~7G-E~'1J:::/~S'
(', \. - 0
(\f A IJ~
DATE ( /-y<52
I '
INSPECTOR
3~SbfZ-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
J><f FOUNDATION 1 ST [ ] ROUGH PLBG.
~ FOUNDATION 2ND [ ] INSULATION
[ ] FRAMING I STRAPPING [] FINAL
[ ] FIREPLACE & CHIMNEY [] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRAnON
-L~
<I
"
DATE 1- 3 ... 0 7
INSPECTOR ~ ~
3 r;-Sb 1 7!-
TOWN OF SOUTHOlD BUilDING DEPT.
765.1802
INSPECTION
~ FOUNDATION 1 ST [ ] ROUGH PLBG.
[ ] FOUNDATION 2ND [ ] INSULATION
[ ] FRAMING I STRAPPING [] FINAL
[ ] FIREPLACE & CHIMNEY [] FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRAnoN
REMARKS:
J\f2
,
DATE I'). ~J-!( ~" b
r
INSPECTOR ~~
3J S C6\A1l14-bVL-e1
Cu~u?-
TOWN OF SOUTHOLD BUILDING DEPT.
765.1802
INSPECTION
[ ] FOUNDATION 1 ST [ ] ROUGH PLBG.
[ ] FOUNDATION 2ND [ ] INSULATION
[ ] FRAMING I STRAPPING [] FINAL
[ ] FIREPLACE & CHIMNEY [M FIRE SAFETY INSPECTION
[ ] FIRE RESISTANT CONSTRUCTION ( jJlRE RESISTANT PENETRAnON
REMARKS:
i71J~ hI2.G :J;JS~f;nD'5\J - fks~
f ~~ (XX ~ ) p~t.( A$ nCCAJP\ l2l')
_lAJ \ LL- ~ \ <2-t; fr- fla.-b J:1V$ ~77Qov
As ~ ~ \~ f11~l':::> oY (pV..Jf'~ J
CCVJ -l8S> &; \J W\B eJi2. ~D
(;)- (2--07
DATE ~. INSPECTOR
..c
0()
v.I ;J!-
f~
.? p
) V\
~*.~~ ~
0'
~-...
FIELD~3PECTION REPORT DATE:
"I
"'
COMMENTS
FOUNDATION (1ST)
-------jI'c:~=_;;f.1----~----
~:~~ I'J~o
FOUNDATION (2ND)
ROUGH FRAMING &
PLUMBING
=- , . ~(:A/L-kJlI..{~l-S.
--O::----M4$/~ lL.Jk
INSULATION PER N. Y.
STATE ENERGY CODE
4J\..L
~
~
FINAL
-p~ ~~
ADDITIONAL COMMENTS
'---:--- '. I/t/~ - ~ e.c J-k_ ----
,. ',If7! O,,:t ~bl u @. -\..:_~,< ~, ~~..;il~ -
u__ ce _ k~ V\.~ X-\Cv~'=----flI[JAA<; (" "
_ Qv',\ IAkJ.. "~ 5-hu_~ ~l6""' ~ 3, N--v
([ft2..L07' hl"A-L ~~. 'J.-.-.:,~~dh~ \-i-^&s'e.J
,. ;;::-.6..~ (':X::c.... -A-5__ oC-C-u.:l'.~@ LA.)1c".L ~~u, ~ A
~ 12-'; . ~se~ cJV"> '
..
ljJ
~~
\J\~
()..,
....." 'It
~'
LA~
a z
~~
~
~
~l"i
\ ~
-""
, ~
..,
c:., ~
D(>~
S?'o::
o l"i
\ ~
F!~
, el
(;, l"i
> ""
8 :"'
TOWN OF SOUTHOLD
BUILDING DEPARTMENT
TOWN HALL
SOUTHOLD, NY 11971
TEL: (631) 765-1802
FAX: (631) 765-9502
www.northfork.net/Southold/
BUILDING PERMIT APPLICATION CHECKLIST
Do you have or need the following, before applying?
Board of Health
4 sets of Building Plans
Planning Board approval
Survey ~
Check '*' "}-oD
Septic Form
N.Y.S.D.E.C.
T mitres
Contact: \~~< \'\ en
Mail to:--'.rO ~\( U 70
~u -rHot.. ~
Phone: 7(P'; - q 3 '7 7
PERMIT NO. .~;2. Sb 1 :c;-
Examined
, 200}.
,20~
Approved
Expiration
~, 20 ()i
I~
. Building Inspector
. "'ii; 2 I L~
APPLICATION FOR BUILDING PERMIT
INSTRUCTIONS
Date_H ~ d-l
,20~
a. This application MUST be completely filled in by typewriter or in ink and submitted to the Building Inspector with 4
sets of plans, accurate plot plan to scale. Fee according to schedule.
b. Plot plan showing location oflot and of buildings on premises, relationship to adjoining premises or public streets or
areas, and waterways.
c. The work covered by this application may not be commenced before issuance of Building Permit.
d. Upon approval of this application, the Building Inspector will issue a Building Permit to the applicant. Such a permit
shall be kept on the premises available for inspection throughout the work.
e. No building shall be occupied or used in whole or in part for any purpose what so ever until the Building Inspector
issues a Certificate of Occupancy.
f. Every building permit shall expire if the work authorized has not commenced within 12 months after the date of
issuance or has not been completed within 18 months from such date. If no zoning amendments or other regulations affecting the
property have been enacted in the interim, the Building Inspector may authorize, in writing, the extension of the permit for an
addition six months. Thereafter, a new permit shall be required.
APPLICA nON IS HEREBY MADE to the Building Department for the issuance of a Building Permit pursuant to the
Building Zone Ordinance of the Town of Southold, Suffolk County, New York, and other applicable Laws, Ordinances or
Regulations, for the construction of buildings, additions, or alterations or for removal or demolition as herein described. The
applicant agrees to comply with all applicable laws, ordinances, building code, housing code, and regulations, and to admit
authorized inspectors on premises and in building for necessary ins~ CC-' ~ ~~";"'..~~_
~_~,~c"- .~
~~a~re o~~, if a corporation) ---
(Mailing address of applicant)
State whether apPlicC::~ssee, agent, architect, engineer, general contractor, electrician, plumber or builder
If
r~ R $",
LL(}
Name of owner of premises
--,-
~
S (NaJJ1e apd/titl~~co:for
t:i:Jt1-* ~. w,;'/.-.;J.r'5;i:..t
Builders License No.
Plumbers License No.
Electricians License No.
Other Trade's License No.
1. L09ation ofland on~hich proposed work wQl ~ done:
3 I .5 lP M. ~ (-1'2. e.. (- ~> vi E-
House Number Street
C v-1e~tot; ue
Hamlet
County Tax Map ~ 1000 Section l{ 1)S~/1
Subdivision . ~~G G~.oU~ Y\J('.
(Name)
Block q 4 - \
Filed Map No.
Lot
Lot
1.8
2. State existing use and occupancy of premijeS and intended use and oCliupancy of proposed construction:
a. Existing use and occupancy \_ ~ A:. W .( L A1J ~ . .
.-
b. Intended use and occupancy
~{:---tV1 A c
P-'L- 0 G-
~ Addition
Other Work
Alteration
3. Nature of work (check which applicable): New Building
Repair Removal Demolition
(Description)
4. Estimated Cost
Fee
5. If dwelling, number of dwelling units
If garage, number of cars
(To be paid on filing this application)
Number of dwelling units on each floor
-
6. Ifbusiness, commercial or mixed occupancy, specify nature and extent of each type of use. ~::;::: is If 7 3iJ /);sr
7. Dimensions of existing structures, if any: Front ~0tJ (- Rear Depth
Height Number of Stories
Dimensions of same structure with alterations or additions: Front fiJ tJ fJ b-
Depth Height Number of Stories
Rear
Name of Former Owner
[10
Depth '~1 \, 11
-b-bG C;Rou P
Depth
10
8. Dimensions of entire new construction: Front~Rear
Height ?- "3, Number of Stories I
9. Size oflot: Front 1t. 9C\ f6 L\ Rear ~oq , tDS
10. Date of Purchase ~ I()' 5
11. Zone or use district in which premises are situated
L---
.J-
12. Does proposed construction violate any zoning law, ordinance or regulation? YES_NO X
13. Will lot be re-graded? YES 'I-. NO_Will excess fill be removed from premises? YES-'i.- NO_
~o ~\(8fo~v1~neNo. '1bC)-93??
-e''7\JC-t1lG#J Phone No 7..) "} - IfR ( I
Phone No.
14. Names of Owner of premises LU;'l-~:r. ~~ddress
Name of Architect -Y. ""\')" I u~(l .~ Address
Name of Contractor W.:::t..,j;\..f,fL,." "S<: 1\:;;(,. L.. Address
I
15 a. Is this property within 100 feet ofa tidal wetland or a freshwater wetland? *YES_NO ~
* IF YES, SOUTHOLD TOWN TRUSTEES & D.E.C. PERMITS MAY ~REQUIRED.
b. Is this property within 300 feet of a tidal wetland? * YES NO
--
* IF YES, D.E.C. PERMITS MAY BE REQUIRED.
16. Provide survey, to scale, with accurate foundation plan and distances to property lines.
17. If elevation at any point on property is at 10 feet or below, must provide topographical data on survey.
STATE OF NEW YORK)
SS:
COUNTY OF .s Jfr.,11c )
~-4-9J S, W~L;:rt-'5D KM\{ ~1:~Qsoing duly sworn, deposes and says that (s)he is the applicant
(Name of individual signing contract) above named,
(S)He is the
~~cQ.-N ~ OFF :.:c.c-R
(Contractor, Agent, Corporate Officer, etc.)
of said owner or owners, and is duly authorized to perform or have performed the said work and to make and file this application;
that all statements contained in this application are true to the best of his knowledge and elief; and that the work will be
performed in the manner set forth in the application filed therewith.
Sworn to before me this
'2,1 j+ dayof tJG~~....b"" 20~
~u~~
Signature of Applicant
~O~~A~Y J~B~tIC, State of New York
No. 01 JU6059400
Qualified In Suffolk cOMuny~9 20 Q:J
CommIssion Expires a I
KENNETH L. EDWARDS
MARTIN H. SIDOR
GEORGE D. SOLOMON
JOSEPH L. TOWNSEND
MAIliNG ADDRESS:
P.O. Box 1179
Southold, NY 11971
OFFICE WCATlON:
Town Hall Annex
54375 State Route 25
(cor. Main Rd. & Youngs Ave.)
Southold, NY
Telephone: 631 765-1938
Fax: 631 765-3136
.
:PLANNING BOARD MEMBERS
JERILYN B. WOODHOUSE
Chair
PLANNING BOARD OFFICE
TOWN OF SOUTH OLD
August 15, 2006
Mr. James V. De Lucca, R.A.
12 Linda Lane East
Riverhead, N.Y. 11971
Re: Proposed site plan for M & R Developing ..J /I
Located at approximately 417' slo Corporate Drive on the slwlo Commerce
Drive in Cutchogue.
SCTM#(s) 1000-96.-1-1.8 Zone: LI (Light Industrial)
Dear Mr. Delucca,
The following resolutions were adopted by the Southold Town Planning Board at a meeting
held on Monday, August 14, 2006:
The final public hearing was closed.
WHEREAS, This site plan is for construction of a new 7,600 sq. ft. light industrial building
divided into eight (8) separate units with six (6) units equaling 1,000 sq. ft. of area each and
two (2) units equaling 800 sq. ft. of area each, where site plan build out includes 24 parking
spaces on a 40,000 sq. ft. vacant parcel in the LI Zone; and
WHEREAS, Tide Group, is the owner of the property located approximately 218' slo
Corporate Drive on the wlslo Commerce Drive in Cutchogue. SCTM#: 1000-96-1-1.8; and
WHEREAS, on March 31,2006, the agent, James V. De Lucca, R.A., submitted a formal
amended site plan for approval; and
WHEREAS, on June 13, 2006, the Southold Town Planning Board, acting under the State
Environmental Quality Review Act, pursuant to 6 NYCRR Part 617, made a determination
that the proposed action is an Unlisted Action and initiated the lead agency coordination
process; and
WHEREAS, on June 20, 2006, the Suffolk County Department of Public Works
reviewed an application for a highway work permit and issued a approval indicating a
permit will not be required and the Planning Boards accepts this for approval; and
.
M & R Developino
Paoe Two
Auoust 15. 2006
WHEREAS, on June 21, 2006, the Suffolk County Department of Planning responded
after a review and determined this matter is for "local determination as there appears to
be no significant county-wide or inter-community impact(s)" and the Planning Board
accepts this pursuant to 239L & M General Municipal Law; and
WHEREAS, on July 7,2006, the LWRP Coordinator reviewed the action and recommended
that "the proposed action is generally consistent with the Policy Standards and therefore is
consistent with the LWRP; and
WHEREAS, on July 11, 2006, the Southold Town Planning Board, acting under the
State Environmental Quality Review Act, performed a coordinated review of
the Unlisted Action. The Planning Board established itself as lead agency, and as lead
agency, made a determination of non-significance and granted a Negative Declaration; and
WHEREAS, on July 13, 2006, the Architectural Review Committee reviewed the associated
site plan materials and conditionally approved the sketch plan dated July 10, 2006 as noted
and indicating a drawing will need to be submitted for the file and Southold Town Planning
Board accepted this approval; and
WHEREAS, on July 14, 2006, the Southold Town Building Inspector reviewed and certified
the site plan for "Light Industrial Building" use and the Planning Board accepts the
certification for approval; and
WHEREAS, on August 7,2006, the Southold Town Engineer reviewed the site plan
materials and approved the drainage of existing conditions along with the proposed
construction subject to comments/conditions and the Southold Town Planning Board
incorporates such comments /conditions as requirements in this approval; and
WHEREAS, on August 13,2006, the Cutchogue Fire District reviewed and approved the
site plan and the Planning Board accepts the approval; and
WHEREAS, the Southold Town Planning Board, pursuant to Chapter 58, Notice of Public
Hearing, has received affidavits that the applicant has complied with the notification
provisions; and
WHEREAS, the following items shall be required:
1. All outdoor lighting shall be shielded so that the light source is not visible from
adjacent properties and roadways. Lighting fixtures shall focus and direct the light in
such a manner as to contain the light and glare within property boundaries. The
lighting must meet town code requirements.
2. All signs shall meet Southold Town Zoning Codes and shall be subject to the
approval of the Southold Town Building Inspector.
3. Landscape survivability guarantee, the applicant agrees to replace any of the
landscape which dies within three years of planting; be it therefore
,
M & R DevelopinQ
PaQe Three
AUQust 15. 2006
RESOLVED, that pursuant to Southold Town Code 100-254 Part 1, the applicant agrees to
incorporate all the requirements, comments, and recommendations of each reviewing
agency as referenced above and as indicated on the site plan and corresponding
attachments; and be it further
RESOLVED, that the Southold Town Planning Board has reviewed the proposed action
under the policies of the Town of Southold Local Waterfront Revitalization Program and has
determined that the action is consistent provided that the best management practices
outlined in the July 31,2006 memo prepared by the LWRP Coordinator; and be it further
RESOLVED, that the Southold Town Planning Board grant approval on the site plan
prepared and certified by both Joseph A, Ingegno, Land Surveyor and James V. DeLucca,
Registered Architect dated July 19, 2005, and last revised July 14, 2006 and the building
plan prepared by James V. DeLucca, R.A. and authorize the Chairperson to endorse the
final site plan with the following conditions:
1. The owner, agent and/or applicant shall receive approval from the Suffolk County
Department of Health Services for the approved construction and submit such
approval to the South old Town Planning Department for review. If such approval
varies from this approved site plan, the Planning Board reserves the right to the
review of a new and site plan application.
2. The owner, agent and/or applicant agrees to not utilize the existing 50' non
disturbance buffer and will not have any construction occur in such area as
shown on the site plan.
/3.
The applicant must obtain a SPDES General Permit (NYR-10H057) for Storm
Water Discharges (General Permit Number GP-02-01) from the New York State
Department of Environmental Conservation for the construction activities.
t The applicant must obtain the required approval or permit from the New York
". State Department of Agriculture and Markets for the construction activities.
5. The site plan approval requires that all work proposed on the site plan shall be
completed within three (3) years from the date of this resolution.
6. Prior to the request for the Certificate of Occupancy, the owner or authorized agent
must request the said Building Inspector and the Planning Board to perform an on-
site inspection to find the site improvements are in conformity with the approved site
plan.
7. If the as-built site improvements vary from the approved site plan, the Planning
Board reserves the right to request a certified as-built amended site plan detailing all
the changes.
8. Any changes from the approved site plan shall require Planning Board approval, and
any such changes without Planning Board approval will be subject to referral to the
Town Attorney's Office for possible legal action.
'.
M & R DevelopinQ
PaQe Four
AUQust 15. 2006
9. The Planning Board will issue a final amended site plan approval in the form of a
letter following a site inspection and at the time the site improvements are found to
be in conformance with the approved site plan.
A copy of the approved site plan is enclosed for your records. As per the Town Code, one
copy each will be distributed to the Building Department and Town Engineer/Highway
Department.
If you have any questions regarding the above, please contact this office.
Very truly yours,
~~
erilyn B. Woodhouse
Chairperson
enc.
cc: Southold Town Building Department
South old Town Engineer
SUFFOLK COUNTY WATER AUTHORITY
2045 Route 112 Suite 1 Coram, New York 11727-3085
(631) 698-9500 Fax (631) 698-9851
June 12,2006
James DeLucca
12 Linda Lane 1;;,
Riverhead, NY 1190 I
Re: Water Availability - Commerce Drive, Cutchogue
SCTM # I 000-96-1-1.2
File #4505188
Dear Mr. DeLucca:
Reference is made to your request for information regarding availability of public water service
to the above referenced property.
There is an existing water main available to the above captioned property from Commerce Drive.
Connection fees, application, RPZ approval and inspection will be required for the lateral service
line installation.
We have kept a copy of your survey on file. Generally there is a three to four week waiting
period from the time all Authority requirements have been met to the time of installation.
lf you have any further questions, please feel free to contact our New Service Department at
(li31) li9R-9500, Ext. 2, or me directly at (631) 563-5672.
Sincerely,
(YWtJ-C)
Lisa Cella
New Service Supervisor
LC:bhr
CUTCHOGUE FIRE DISTRICT
Board of Fire Commissioners
260 New Suffolk Road. Cutchogue. NY 11935
Telephone (631) 734-6907. Fax (631) 734-7079
E-maJI. cutfd@optonline.net
August 13,2006
Southold Town Planning Board
Mr. Bruno Simone
PO Box 11179
Southold, NY 11971
.
.
Ref: Northfork Industrial Park
Lot # II for Wilinski & Schill
Dear Mr. Simone,
The Cutchogue Board of Fire Commissioners have reviewed the above site plan
and being consistent with our letter to Mr. Henry Raynor in October of 2004 stated that
2-Electric Fire Wells be installed for fire protection, one at each end of Commerce
Drive.
The wells are to meet our specifications on file in your office. In the event that
water mains are installed with fire hydrants producing 500 gallon per minute, the wells
would not be necessary.
Thank you for your correspondence and feel free to contact this office at any time
with your questions.
.
Very truly yours,
Board of Fire Commissioners
1t~)ltfa~
Matthew J. Martin
District Secretary
J
.
NOTICE OF INTENT
0-
New York State Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor
Albany, New York 12233-3505
Stormwater Discharges Associated with Construction Activity Under State
Pollutant Discharge Elimination System (SPDES) General Permit # GP-02-0l
All sections must be completed unless otherwise noted. Failure to complete all items may
result in this form being returned to you, thereby delaying your coverage under this
General Permit. Applicants must read and understand the conditions of the permit and
prepare a Storrnwater Pollution Prevention Plan prior to submitting this Nor. Applicants
are responsible for identifying and obtaining other DEe permits that may be required.
TO properly complete this form, please refer to the Instruction Manual which can be
accessed at www.dec.state.ny.us/website/dow/toolbox/instr_man.pdt
-IMPORTANT-
THIS FORM FOR HANDPRINT ONLY
PRINT CAPITAL LETTERS IN BLACK INK AND AVOID CONTACT WITH
FILL IN CIRCLES COMPLETELY AND DO NOT USE CHECKMARKS
OWNER/OPERATOR MUST SIGN FORM
THE EDGE OF BOXES
Page 1 of 9
.
.~
11906
0-
1. Provide the Geographic Coordinates for the project site in NYTM Units. TO do this you
must go to the NYSDEC Stormwater Interactive Map on the DEe website at:
www.dec.state.ny.us/website/imsmaps/stormwater/v1ewer.htm
Zoom into your Project Location such that you can accurately click on the centroid of
your site. Once you have located your project site go to the dropdown menu on the left
and choose "Get Coordinates". Click on the center of your site and a small window
containing the X, Y coordinates in UTM will pop up. Transcribe these coordinates into the
boxes below. For problems with the interactive map use the help function.
2. What is the nature of this construction project?
.
Page 2 of 9
.
.~
11906
0-
3. Select the predominant land use for both pre and post development conditions.
SELECT ONLY ONE CHOICE FOR EACH
4. Will future use of this site be an agricultural property as defined
by the NYS Agriculture and Markets Law?
5. Is this a remediation project conducted in accordance with a NYSDEC
approved work plan?
6. Is this property owned by a state authority, state agency or local
government?
7. In accordance with the larger common plan of development or sale; enter the total
project site acreage, the acreage to be disturbed and the future impervious area
(acreage)withln the disturbed area. Round to the nearest tenth of an acre.
8. Will there be more than 5 acres disturbed at any given time?
9. Indicate the percentage of each Hydrologic Soil Group (HSG) at the site.
.
.
.
~
11906
10. Is this a phased project? (if yes, The SWPPP must address all planned
phases)
0-
11. Enter the planned start and end
dates of the disturbance activities
12. Provide the name of the surface waterbody(ies) into which construction site runoff
15. Does the site runoff enter a separate storm sewer system-
including roadside drainsi .swales, ditches, culverts, etc?
(if no, skip question 16 )
16. What is the name of the muniCipality/entity that owns the separate storm sewer system?
17. Does any runoff from the site enter a sewer classified as
a Combined Sewer?
Page 4 of 9
.
.
.~
11906
18. Has the required Erosion and Sediment Control component of the SWPPP
been developed in conformance with the current NYS Standards and
Specifications for Erosion and Sediment Control (aka Blue Book) ?
0-
19. Does this construction activity require the development of a SWPPP that
includes Water Quality and Quantity Control components (Post-Construction
Storrnwater Management Practices) If no, Skip question 20
20. Have the Water Quality and Quantity Control components of the SWPPP
been developed in comformance with the current NYS Stormwater Management
Design Manual ?
NOTE: If you answered no to question 18 or 20, Pursuant to Part r.D.3. (b) of the permit,
you must have your SWPPP prepared and certified by a licensed/certified professional and
the SWPPP is subject to a 60-business day review. Please provide further details in the
details/comment section on the last page of this form.
21. The Stormwater Pollution Prevention Plan (SWPPP) was prepared by:
.
.
.~
11906
Erosion and Sediment Control Practices
0-
22. Has a construction sequence schedule for the planned management
practices been prepared?
23. Select all of the erosion and sediment control practices that will be employed
on the project site.
.
.
.~
11906
Water Quality and Quantity Control
0-
Important:Completion of Questions 24-30 is not required if the project:
Disturbs less than 5 acres and is planned for single-family residential homes (including
subdivisions) or construction on agricultural property and does not have a discharge to
a 303(d) water or is'not located within a TMDL watershe~
Additionally, sites where there will be no future impervious area within the disturbed
area and that do not have a change (pre to post developrnent)in hydrology do not need to
complete questions 24-30.
24. Indicate all the permanent Stormwater Management Practice(s) that will be
installed on this site
.
Page 7 of 9
.
~
11906
0-
25. Provide the total water quality volume required and the total provided for the site.
26. Provide the following Unified Stormwater Sizing Criteria for the site.
IMPORTANT: For questions 27 and 28 impervious area should be calculated considering the'
project site and all offsite areas that drain to the post-construction stormwater
management practice(s) (Total Drainage Area = Project Site + Offsite areas)
,27. Pre-Construction Impervious Area - As a percent of the ~
Drainage Area enter the percentage of the existing impervious areas
before construction begins.
~8. Post-Construction Impervious Area - As a percent of the Total
Drainage Area enter the percentage of the future impervious areas that
will be created/remain on the site after completion of c~nstruction.
29. Indicate the total number of permanent stormwater management
practices to be installed
30. Provide the total number of stormwater discharge points from the
site (include discharges to either surface waters or to seperate
storm sewer systems)
.
Page 8 of 9
.
,'.
~
11906
-
0-
If this NOI is b~idg submitted for the purpose of continuing coverage under a
general permit for stor.mwater runoff from construction activities, .please indicate
the former SPDES number assigned.
-
I have read or been advised of the permit conditions and believe that I understand them. I also
understand that, under the terms of the permit, there may be reporting requirements. I also certify under
penalty of law that this document and. the corresponding documents were prepared under my direction or
supervision in accordance with a system designed to assure that qualified personnel properly gather and
evaluate the information submitted. Based on my inquiry of the person'ls) who manage the system, or those
persons directly responsible for gathering the information, the information submitted is, to the best of
my knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for
submitting false information, including the possibility of fine and imprisonment for knowing violations.
I further understarid that coverage under the general permit will be identified in the aCknowledgment that
I will receive as a result of submittin9 this NO! and can be as long as sixty (60) days as provided for
in the general permit. I also understand that, by submitting this NOI, I am acknowledging that the SWPPP
has been developed and will be implemented as the first element of construction. and agreeing to comply
with all the terms and conditions of the general permit for which this ~OI is being submitted.
I.':
~:T,
;,c..
~;"
--:'.
Page 9 of 9
.
COUNTY OF SUFFOLK
STEVE LEVY
SUFFOLK COUNTY EXECUTIVE
DEPARTMENT OF PUBLIC WORKS
RICHARD J. LA VALLE, P .E.
CHIEF DEPUTY COMMISSIONER
CHARLES J. BARTHA. P.E.
COMMISSIONER
LESLIE A. MITCHEL
DEPUTY COMMISSIONER
June 20, 2006
Town of South old
Planning Board Office
P.O. Box 1179
Southold, N. Y. 11971 -0957
Attn: Bruno Semon
Re: CR 48, Middle Rd.
M & R Developing
SCTM#1000-96-1-1.8
Dear Mr. Semon:
A pennit from this Department will not be required. We have reviewed this development and find that no
additional improvements within the County right-of-way in the vicinity of this site will be required.
If you have any questions, kindly contact this office at 852-4100.
v cry truly yours,
WH:MPC:ln
cc: Joseph A. Ingegno
William Hillman, P.E.
Chief Engineer
.>-:f:.f@VC
Director of Highway Planning & Permits
SUFFOLK COUNTY IS AN EQUAL OPPORTUNITY/AFFIRMATIVE ACTION EMPLOYER
335 YAPHANK AVENUE
.
Y APHANK. N.Y. 1 1 980
.
(63f)B52~4010
FAX (631)852-4150
t-AATE\... ~Oot=
\"".....~E"t.s. T"t'~.
LTHIZ..E.lii HOv~ FileS: -~^""E.t:>
TENANT SJ::P'A~AT\ON WI>..I-\.
"""'('P.
/'
I
-<
E,><rE.~loR..
N\"',~ I-
5>101"'''''
PANJ;\...S
r,<p.
~
/
,/
Ii
':::o..."'lts;r-~
8t..o~ 0:; WALt...
TYP.
.,,_?1QJ~ TO 5 \ \) E SEe.. T \0 I-..J
'5oC-A..'-~: '/8'-;;'-;'-" ~''::;'-;;--'---
..- t-A......T" \... ;;;:oO~INc..
'PANEI- 'T'<P.
srI-. \=7URI-IN,:> ,...-;'p
. srI-. vvALL C,.coL-U........M...
ANt:> s.L... IZ=~
~Al='rE:'. ~ T"1"P
-,..." -~_.;- DEVELOPI"'''' t
315 coM.r--'HrIZCe:. ~.
'500 TH01-!:>) N.Y.
Ilqi.
..12Rf.,.\NN. e,Y:
. ..J AN\E50 V. De: L.uu;.A
R.A....
il
II
I'
I
I
I
~_._-
< ~\ I-A'(E\Z.'So Of: T'(PE 5/a'l
x c,,"t'P. 80. ""0 .
u..... o!i(.t SIC> S' c:>... ~C>c:> P
17....'" e:: 1-... I S/{>G ""II '- 1-
PA"E~~ ,/J1o.ND 1='\..00 c:;;e.
.
v ,
.
~~..~----
~ .<. -..~,- ~.
-u" srJ.., srvCi>$ <::Z-
/(;,"o,c... fYP~
\' "S
Dt.\' \
1.-
----"-'C.ONc.~E~-..O;'\...,...,~
. Sc:c.,\O N t:"H~Y_.T~.~.~~.r. SePA'R",\O}J
SCAL E ~ \''' :: \ ' - 0 ..
'^' "LL-
,
COMcheck Software Version 3.3.1
Envelope Compliance Certificate
New York State Energy Conservation Construction Code
Report Date: 12106/06 DEe 6'
Data filename: Untitled.cck
Section 1: Project Information
Project Title: M & R Developing
Construction Site:
SCTM# 96-1-1.8
Soulhold, NY 11971
Owner/Agent:
Designer/Contractor:
Section 2: General Information
Building Location (for weather data):
Climate Zone:
Heating Degree Days (base 65 degrees F):
Cooling Degree Days (base 65 degrees F):
Project Type:
Vertical Glazing I Wall Area Pet.:
Suffolk, New York
llb
5750
715
New Construction
1%
Bulldlna TVDe
Storage, Industrial and Commercial
Floor Area
903
Section 3: Requirements Checklist
Envelope PASSES Design 5"'0 beller ttlan code
Climate-Specific Requirements:
Component Name/Description
Gross Area
or Perimeter
903
-..:.?39
15
Roof 1: Metal Roof with Thermal Blocks
Exterior Wall 1 ; Metal Wall without Thermal Blocks
Window 1: Wood Frame:Double Pane with Low-E, Clear, SHGC
0.33
Door 1: Solid
Floor 1: Slab-On-Grade:Unheated, Vertical 4 ft.
21
124
(a) Budget U-factors are used for software baseline calculations ONLY, and are not code requirements.
Air Leakage, Component Certification, and Vapor Retarder Requirements:
o 1. All joints and penetrations are caulked, gasketed, weather-stripped, or otherwise sealed.
o 2. Windows, doors, and skylights certified as meeting leakage requirements.
o 3. Component R-values & U-factors labeled as certified.
o 4. Insulation installed according to manufacturer's instructions. in substantial contact with the surface being insulated, and in a
manner that achieves the rated R-value without compressing the insulation.
o 5. Fireplaces installed with tight fitting non-combustible fireplace doors.
o 6. Stair, elevator shaft vents, and other dampers integral to the building envelope are equipped with motorized dampers.
o 7. Cargo doors and loading dock doors are weather sealed.
o 8. Recessed lighting fixtures are: (1) Type IC rated and sealed or gasketed; or (ii) installed inside an appropriate air-tight assembly
with a 0.5 inch clearance from combustible materials and with 3 inches clearance from insulation material.
o 9. Vapor retarder installed.
M & R Developing
Page 1 of 7
Section 4: Compliance Statement
Compliance Statement: The proposed envelope design represented in this document is consistent with the building plans, specifications
and other calculations submitted with this permit application. The proposed envelope system has been designed to meet the New York
Stale Energy Conservation Construction Code requirements in CQMcheck Version 3.3.1 and to comply with the mandatory requirements
in the Requirements Checklist.
When a Registered Design Professional has stamped and signed t . page, they are attesting that to the best of hisfher knowledge,
belief, and professional judgment, such plans or specification i pliance with this Code.
----
~ Ayy)~->
Name - Ille
~~1l.Y\,Q'S V\2i.
/2.}~ J<0~
Dale' I
\
."....
M & R Developing
Page 2 of 7
COMcheck Software Version 3.3.1
Lighting and Power Compliance
Certificate
New York State Energy Conservation Construction Code
Report Date: 12/06/06
Data filename: Untitled.cck
Section 1: Project Information
Project Title: M & R Developing
Construction Site:
SCTM# 96-1-1.8
Southold, NY 11971
Owner/Agent:
Designer/Contractor:
Section 2: General Information
Building Use Description by:
Project Type: New Construction
Bulldina TVDe
Storage, Industrial and Commercial
Floor Area
903
Section 3: Requirements Checklist
Interior Lighting:
o 1. Total actual watts must be les5 than or equal to total allowed watts.
Allowed Watts Actual Watts Complies
542 0 YES
o 2. Exit signs 5 Watts or less per side.
Exterior Lighting:
o 3. Efficacy greater than 45 lumensIW.
Exceptions:
Specialized lighting highlighting features of historic buildings; signage; safety or security lighting; low-voltage landscape
lighting.
Controls, Switching, and Wiring:
o 4. Independent controls for each space (switch/occupancy sensor).
Exceptions:
Areas designated as security or emergency areas that must be continuously illuminated.
Lighting In stairways or corridors that are elements of the means of egress.
o 5. Master switch at entry to hotel/motel guest room.
o 6. Individual dwelling units separately metered.
o 7. Each space provided with a manual control to provide uniform light reduction capability.
Exceptions:
Only one lumlnaire in space;
An occupantwsensing device controls the area;
The area is a corridor, storeroom, restroom, public lobby or guest room;
Areas greater than 250 sq.ft.
o 8. Automatic lighting shutoff control in spaces greater than 250 sq.ft in buildings larger than 5,000 sq,ft,
o 9. PhotocelVastronomical time switch on exterior lights.
M & R Developing
Page 3 of 7
Exceptions:
Lighting intended for 24 hour use.
D 10.Tandem wired one-lamp and three-lamp ballasted luminaires (No single-lamp ballasts).
Exceptions:
Electronic high-frequency ballasts; Luminaires not on same switch.
D 11, Transformers meet minimum efficiencies listed in Table 805.6.1 or 805.6.2.
M & R Developing
Page 4 of 7
COMcheck Software Version 3.3.1
Lighting Application Worksheet
New York State Energy Conservation Construction Code
Report Dale:
Dala filename: Untitled.cck
Section 1: Allowed Lighting Power Calculation
A
BCD
Floor Area Allowed Allowed Watts
Watts I ft2
903 0.6 542
Total Allowed Watts = 542
Storage, Industrial and Commercial
Section 2: Actual Lighting Power Calculation
A
Fixture 10 : Description I Lamp I Wattage Per Lamp I Ballast
B
Lampsl
Fixture
C D
# of Fixture
Fixtures Watt.
T alai Actual Watts =
E
(CXD)
o
Section 3: Compliance Calculation
If the Total Allowed Watts minus the Total Actual Watts is greater than or equal to zero, the building complies.
Total Allowed Watts = 542
Total Actual Watts = 0
Project Compliance = 542
Llghtmg FAILS Deslgll 100") worst' tildll code
M & R Developing Page 5 of 7
"
COMcheck Software Version 3.3.1
Mechanical Compliance Certificate
New York State Energy Conservation Construction Code
Report Date: 12/06/06
Data filename: Untitled.cck
Section 1: Project Information
Project Title: M & R Developing
Construction Site:
SCTM# 96-1-1.8
Scuthold, NY 11971
Owner/Agent
Designer/Contractor:
Section 2: General Information
Building Location (for weather data):
Climate Zone:
Heating Degree Days (base 65 degrees F):
Cooling Degree Days (bese 65 degrees F):
Project Type:
Suffolk, New York
11b
5750
715
New Construction
Section 3: Mechanical Systems List
.Q..u.ant.Ib: System Tyee & DescrlDtlon
Section 4: Requirements Checklist
M & R Developing
Page 6 of 7
COMcheck Software Version 3.3.1
Mechanical Requirements
Description
New York State Energy Conservation Construction Code
Report Date:
Data filename: Untitled.cck
M & R Developing
Page 7 of 7
M, & R Southold Properties Lie.
P.o. Box 890
Southold, NY 11971
Town Of Southold
PO Box 1179
Southold. NY 11971
(631) 765-1800
RECEIPT
#3649
11/21/2006
Received $ 25.00 for Septic Permit - Construct. Non-resid., on 11/21/2006. Thank you for stopping by
the Town Clerk's office.
As always, it is our pleasure to serve you.
Neville
Clerk
Elizabeth A.
Southold Town