HomeMy WebLinkAboutL.I. Without Shoreham Power Plant. 1983 - Summary of findings - Planning Conseq.83-14/S
LONG ISLAND WITHOUT THE SHOREHAM POWER PLANT:
ELECTRICITY COST A~D SYSTEM PLANNING CONSEQUENCES
S-wnary of Findings
Prepared for the
County of Suffolk
L~uw OF souT~oL.o i
by
ENERGY SYSTEMS RESEARCH GROUP, INC.
120 Milk Street
Boston, Massachusetts 02109
($17) 426-5844
Principal Investigator
Paul D. Raskin
Project Team
Thomas Austin
Stephen Bernow
Bruce Biewald
David McAnulty
David Nichols
Richard Rosen
Jonathan Wallach
July, 1983
E S R 0
TABLE OF CONTENTS
LIST OF TABLES AND FIGURES.
2.
3.
4.
5.
6.
7.
8.
SUMMARY OF FINDINGS
LOAD FORECAST .
SUPPLY PLANNING
SHOREHAM OPERATIONS AND COSTS
COST IMPACTS OF NOT OPERATING SHOREHAM
THE POTENTIAL ROLE OF CONSERVATION
SENSITIVITY ANALYSIS
REVIEW OF LILCO'S COST IMPACT ESTIMATES AND "CRITIQUE".
TECHNICAL REPORTS
A. Long Range Forecast of Electricity Requirements in the
LILCO Service Area
B. Shoreham Operations and Cost
C. The Conservation Investment Option
D. Sumary of Computer Outputs
Page
ii
1
19
30
40
6O
67
72
76
- i -
E S R G
Table No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Figure No.
1
2
3
4
5
$
7
8
9
LIST OF TABLES
RATE IMPACTS OF ABANDONMENT UNDER ALTERNATIVE
SCENARIOS
FORECAST OF ENERGY AND PEAK DEMAND
FORECAST SU~%RY
DISAGGREGATED FORECAST BY SUBSECTOR COMPONENTS
ANNUAL SHOREHAM REPLACEMENT POWER COSTS
OPERATIONS AND MAINTENANCE COSTS FOR NUCLEAR
STATIONS IN THE U.S.
SHOREHAM PLANT OPERATIONS AND MAINTENANCE
COSTS
NET CAPITAL ADDITIONS FOR NUCLEAR STATIONS
IN THE U.S.
COSTS AND REVENUE REQUIREMENTS FOR SHOREHAM
NET CAPITAL ADDITIONS
SHOREHAM NUCLEAR POWER PLANT OPERATIONS AND
COSTS SUMMARY .
REVENUE REQUIREMENTS.COMPARISON: RATE WASH
CASE
SUMMARY REVENUE REQUIREMENTS COMPARISON: RATE
WASH CASE
RECONCILIATION OF LILCO COST IMPACT ESTIMATES
WITH RATE WASH SCENARIO
LIST OF FIGURES
RATE IMPACTS OF ABANDONMENT - ALTERNATIVE
SCENARIOS
REVENUE REQUIREMENTS AND RATES''--'1983-2013.
SHOREHAM COSTS VERSUS ABANDONMENT COSTS -
SELECTED YEARS AND 20 YEAR AVERAGE
COMPARISON OF HISTORIC CHANGES IN 1990 PEAK
FORECAST
FOPU T ON - l s -i9 2'
COMPARISON OF 1983 LI O AND RSRG PEAK FORE-
CASTS AND GROWTH TREND IN PEAK
REQUIRED CAPACITY AND TOTAL CAPACITY,
SHOREHAM-OUT
SHOREHAM CAPACITY FACTORS - ESRG AND LILCO
ASSUMPTIONS
RECONCILIATION OF LILCO ESTIMATE OF ABANDON-
MENT COSTS WITH THE RATE WASH CASE
Page
4-5
25
26
27
36
46
49
52
54
59
64
66
78
Page
6
9
10
20
21
23
33
44
79
- ii -
E S R G
1. SUMMARY OF FINDINGS
The County of Suffolk has determined that no emergency
plan "could protect the health, welfare and safety of Suffolk
County's residents if there were a serious'accident at the
Shoreham facility." The County goes on to conclude that the
nearly completed nuclear power plant "shall not operate and
must be abandoned."*
The question that naturally arises is: what are the economic
repercussions of not operating Shoreham? This report sum-
marizes the results of a detailed analysis of the likely cost
impacts on' Long Island Lighting Company (LILCO) ratepayers.**
Will ratepayers' bills be higher or lower if Shorehem does not
operate (compared to if it does operate)? What is the
magnitude of such rate impacts?
These questions are addressed by simulating the flow of
revenues LILCO will derive from its ratepayers ("required
revenues") under a variety of Shoreham-Out cases and comparing
these to required revenues should Shoreham operate. The
difference in required revenue streams is the "bottom line"
* County Resolution No. 111, February, 1983.
** Parallel studies sponsored by the County of Suffolk will
explore issues other than direct rate impacts such as LILCO's
financial stability under alternative scenarios and property
valuation and tax consequences.
- 1 -
E $ R G
cost impact measure.* To compute these effects it is necessary
to examine such issues as electrical energy and peak demand
forecasts in the LILCO service area, power supply planning with
and without Shoreham, and the likely performance
characteristics and costs of operating Shoreham. The results
of this investigation are summarized in the remainder of this
section and expanded on in the sections to follow.**
First, however, it is important to state one overall con-
clusion: abandoning Shoreham will not result in an economic
disaster for ratepayers as posited by LILCO in its recent
analyses. Rather, under most scenarios considered in this
report, it actually costs the ratepayers less if Shoreham is
abandoned. Indeed, in the most favorable abandonment scenario
to LILCO -- one where the plant never operates but LILCO gets
full return on its entire Shoreham investment -- the rates
incurred by LILCO ratepayers will be only a small fraction
above the rates to be charged if the plant is operated.
Accordingly, as this report documents, utility rates will
likely increase in the future in both the Shoreham-~n and
Shoreham-Out scenarios. However, the rates may in fact
increase somewhat less if Shoreham never operates but, at
worst, the rate impacts in the Shoreham-In and Shoreham-Out
cases are largely comparable.
-"*Formally stated, the cumulative present value of required
revenues under alternative scenarios have been computed and
compared. Present value calculations are a commonly used
approach in comparing costs and benefits which occur at
different points in time. The procedure discounts future
costs and benefits to reflect the time value of money and
underlying inflation.
**Technical documentation is presented in the four companion
volumes listed in the Table of Contents.
E S R O
Cost Impacts
The average percent impact on rates and cumulative cost
differentials of abandoning Shoreham are presented in Table 1.
The results in terms of percent rate impacts are illustrated
graphically in Figure 1. A benchmark cost comparison in which
the ratepayers are on average no worse off with Shoreham out
than with Shoreham in ("Rate Wash" scenario) is listed first.
This case embodies the basic forecast, system planning, and
power cost parameters developed in the course of this
investigation (see Sections 2-5 and Technical Reports A, B,
and D).
- 3 -
E S R G
TABLE 1
RATE IMPACTS OF ABANDONMENT UNDER ALTERNATIVE SCENARIOS
Scenario
Rate Wash
Load Forecast - High
- Low
Fuel Price
Escalation
- High
- Low
Energy From
Power Pool
- High
Low
Nuclear O&M
Costs - High
- Low
Future Shoreham
Investment
- High
- Low
Shoreham Capi-
tal Recovery
- Full
Low
Description
Rates unaffected by
abandonment*
Cost Impact of Abandonment
Cumulative Change Average
in Required Revenues Percent
(1983 present value Change in
dollars in millions) Rates
0 0.0%
1.6%/year peak growth
(from base case of 0.8%) 230
0.0%/year peak growth -310
1.1
-1.6
oil at 3% real, after
1987 (from 2%)
Coal at 2% (from 1%) 120
Oil at 1% real, after
1987. Coal at 0% real -100
0.6
-0.5
Double energy assumed
available (Sec. 3) -50
No energy available
from pool 60
-0 · 2
0.3
Double real increase in
projected costs (Sec. 4) -210
No real increase in costs 210
-1.1
1.1
Double real increase in
projected investments
(Sec. 4) -290
No real increase in
investments 290
-1 · 4
1.4
100% of Shoreham in
rate base (vs. 91%) 430
65% of Shoreham in
rate base -1340
2.2
-6.7
- 4 -
F~ S R G
TABLE 1
(Continued)
RATE IMPACTS OF ABANDONMENT UNDER ALTERNATIVE SCENARIOS
Scenario
Time Period
of Analysis
- Long
Description
Cost Impact of Abandonment
Cumulative Change
in Required Revenues
(1983 present value
dollars in millions)
30 years, 1984-2013
(from 20 years) - 60
- Short 10 years, 1984-1993 -160
Pursue conservation
to replace Shoreham
generation
Effects of having
started the Shoreham
Project in the first
place
Conservation
Investment
Option
Shoreham
Never Built**
Average
Percent
Change in
Rates
-0.3
-1.2
-580 -2.9
-3405 -17.0
*The base data used in the Rate Wash case is described at length
in the text of this report. In the sensitivity tests reported
here, individual data items of the base set were modified one
at a time.
**This is equivalent to a case in which ratepayers are fully
protected from the costs of the Shoreham investment.
- 5 -
£ S R G
Percent
Impact on
Rates
4%
0
-4%
-12%
-16%
Pate I~k%d Fuel Price
Wash Forecast Escalation
High
High
Power
High
Future Shoreham
Nuclear Shoreham Capital
O&M Investment Be~over~
Full
Hi~ High
Low
Period
vation
Shoreham
Never
Built
10 YR
The treatment of Shoreham investment costs under abandonment
is an issue that would be determined by the Public Service
Commission through the regulatory process. The Rate Wash
scenario is based on the assumption that 91 percent of the
Shoreham investment enters the rate base. Re-stated, if LILCO
were allowed full return on debt service and capital costs and
amortization of 91 percent of the abandoned investment,
ratepayers would be no worse off than if Shoreham operated.
The Rate Wash scenario is presented in this report for
comparison purposes. It does not ~onstitute a recommended amount
of return for LILCO on its Shoreham investment, such a decision
belongs to the New York State Public Service Commission and will
involve complex policy and factual questions. It is important to
note, however, that the Rate wash scenario is a realistic option
if Shoreham is abandoned. Many persons would argue that investors
should share even more of the Shoreham costs if the plant never
operates.* At any rate, the experience in other cases indicates,
at a minimum, that where a major power plant investment is
abandoned, a less than 100 percent return is the norm. Thus, we
have chosen the 91 percent return "Rate Wash" scenario as our
benchmark case.
The revenue requirements over time in the Shoreham-In versus
Shoreham-0ut (Rate Wash) scenario are graphed in Figure 2, along
with a plot of the cost differences. The jump in costs in 1984
will be noted in both scenarios. After that the revenue
*On the other hand, LILCO would have the ratepayers pay more on
the Shoreham investment if it is abandoned (see Section 8).
- 7 -
E S R G
trajectories track closely with minor ratepayer advantages to
Shoreham-0ut in the earlier years, crossing over in the 1990s to
favor Shoreham-In but, by design, averaging to zero effect.
The breakdown by cost component is shown in Figure 3. Here,
the various costs incurred by ratepayers to support Shoreham
operations are compared to those incurred under abandonment. The
comparisons are shown for selected years and for the 20-year
average annual costs. Details are presented in Section 5.
The other scenarios in Table 1 compute the impacts of
adjusting various baseline assumptions. For example, it is found
that if 65 percent*, rather than 91 percent, of the Shoreham
investment enters the rate base, ratepayers would pay 6.7 percent
less with Shoreham abandoned than with Shoreham operating and
fully in the rate base. On the other hand, if Sh0reham were
abandoned bat 100 percent of the investment and return were
allowed, we see that rates would increase by 2.2 percent more in
the abandoned scenario than in the operation scenario. This is
the case most favorable to LILCO and shows that the cost impact
of abandoning Shoreham is likely to be small at worst.
Examining Table 1 further, we see the variation in cost
impact with respect to a range of inputs -- load forecasts,
Shoreham operations and maintenance cost estimates, capital
expenditure projections, make-up power availability and fuel
prices. In no instance, with the exception of the 65 percent
recovery scenario alluded to above, are the impacts substantial.
*This "Low Return" scenario is designed to maintain dividend yields,
achieves a coverage ratio on debt of at least 2.4, and maintains
internal generation of cash at at least 40 percent of construction
requirements. Georgetown Consulting Group (report forthcoming).
- 8 -
FIGURE 2
REVENUE REQUIREMENTS AND .RATES - 1983-2013
Total Revenue
Requirements
(Million 1983
PV $)
2000
1500-
500.
Shoreham operates
...................... Shoreham Abandonm~n~
1983 1995 2003 2013
Cost Impact of
(Million 1983 5
50'
25
25
1983
1995
2C
2013
FIGURE 3
SHOREHAM COSTS VERSUS ABANDONMENT COSTS
SELECTED YEARS AND 20 YEAR AVERAGE
Revenue
Requirements
(Millions 1983 PV
$300
1 9 9 3 2 0 0 3
Spent Fuel and
Decommissioning
20 YEAR AVERAGE
Capital
Makeup
Energy
$200
$100
Invest-
m~nt
Invest-
~_nt
Recovery
Capital
New
Plant
Prop. Tax
Shoreham
Costs
Abandonment
Costs
Inv.
Shoreham
Costs
Inv. Bec.
Abandonment
Costs
Shoreham Abandonment
Costs Costs
The. scenarios in Table 1 entitled "Time Period of Analysis"
require some explanation. In the baseline runs discussed in this
report, rate impact effects are computed over the twenty-year
timeframe 1984-2003. The decision to base the analysis on twenty
years was made because impacts beyond that time must be
considered highly speculative.* In addition to the usual
difficulties of performing economic and financial assessments
that go beyond a fifteen to twenty year period, there is no
experience at this time with commercial nuclear power plants of
that age on which to base analytic judgments. Projections based
on the aging patterns of currently existing facilities show
severe deterioration in performance and escalating repair and
upkeep costs.
In an effort to assess the sensitivity of the results to a
different time range, ESRG has also performed analyses of
Shoreham-In vs. Shoreham-Out for a thirty-year period (1984-2013)
and for a ten-year period (1984-1993). Extending the analysis
over the thirty-year period 1984-2013 shows that costs in the
last ten years are higher if the plant is operating rather than
abandoned, thus improving the economics of abandonment (see
Table 1). The same is true if one selects ten years. However,
twenty years is recommended as a more reasonable period on which
to focus and to base policy decisions.
*LILCO's analyses have extended to forty years (see Section 8).
They are presented without caveats underscoring the high degree
of unreliability involved. This seems astonishing when the
Company's performance on load forecasting, system requirements,
and construction costs have been so strikingly inaccurate over
the past ten years.
- 11 -
E S R G
The next scenario shown in Table 1 -- Conservation
Investment -- assumes that a decision to abandon Shoreham
triggers an extra emphasis on promoting and financing measures to
improve the efficiency of the delivery and consumption of
electrical energy. There remains cost-effective conservation
potential beyond the substantial efficiency improvements already
incorporated in our LILCO load forecast. If vigorous
conservation measures were promoted, the impacts of not operating
Shoreham would be mitigated further. Later in this report
(Section 6 and Technical Report C), the outlines of such a
conservation program are described. The effect of adding a
conservation program are seen to decrease costs to the ratepayers
of abandoning Shoreham by about 2.9 percent.
Finally, Table 1 presents the "Shoreham Never Built"
scenario, which estimates the average impacts over time of having
begun the Shoreham project in the first place -- rates will be
about 17 percent higher with Shoreham than if it never were
built.* The combination of decreasing forecasts of power needs
and escalating nuclear costs combined to make the Shoreham
project both unnecessary and extremely costly.
*Equivalently, if ratepayers were fully protected from the
Shoreham investment costs if the plant does not operate (e.g.,
none of the Shoreham costs recuperated by LILCO), rates would
be 17 percent lower than with Shoreham operating with investment
costs fully recovered. However, this would likely lead to the
financial collapse of the Company, with difficult-to-quantify
indirect consequences.
- 12 -
E S R G
Load Forecast
Summer peak demand in the LILCO service area is likely to
grow at an average rate of 0.8 percent per year over the
1982-2000 period. This forecast was developed by using a detailed
end-use model analysis that has been validated in LILCO service
area forecasts since 1977. Our forecast is above the 0.2
percent per year annual growth rate that would result from
simple time extrapolation of recently experienced summer peaks
(suitably adjusted for weather and time-of-peak fluctuations),
and above the current official New York State 0.3 percent per
year population growth projection. The Company's forecast (1.6
percent growth per year in summer peak load) continues to reflect
remnants of the combination of overly optimistic growth judgments
and model formulation problems that have over the years led LILCO
to seriously overestimate load growth prospects for Long Island.
Power Supply Planning Issues and Costs
If Shoreham does not operate there will be a need, beginning
in 1998, for additional generating capacity. This finding
reasonable assumes that the other elements of the Company's
supply plans remain unchanged -- the power plant additions, the
retirement schedule for existing facilities, and the enhancement
of transmission interconnections with other power systems. It
also assumes that no additional conservation effort would occur
with Shoreham not operating. In Section 8, the sensitivity of
rate impacts to both earlier and later in-service dates for
substitute power are examined and shown to have only minor
impacts (less than one percent on rates).
- 13 -
£ S R G
In comparing a scenario with Shoreham not operating to one
with Shoreham operating, the Shoreham-Out case will require
that the energy that would have been produced by Shoreham be
provided by other facilities (assuming again no extra conserva-
tion beyond Base Case levels). Furthermore, as indicated above,
additional capacity will be required beginning in 1998. During
the 1984-1997 period the make-up energy will come from two
sources: LILCO's existing oil-fired power plants and, especially
after the planned new transmission line comes into service in
1990, from imports from the New York Power Pool.
In the primary cost comparisons discussed here, the capacity
shortfalls in the late 1990s are assumed to be met by
construction of two 400 MW coal plants, one in 1998 and one in
2000. LILCO also assumes such coal plants in the event Shoreham
does not operate, but in 1994 and 1996, based on the Company'.s
higher forecast.* From 1998, therefore, the make-up energy is
coal-based. (Indeed, two such coal plants would produce more
energy than Shoreham would have, leading to some oil-displacement
benefit after 2000 in the Shoreham-Out case.)
Additional construction is required in both the Shorehem-In
and the Shoreham-Out cases, beginning in the year 2004. This
fact does not affect our impact assessment, which is concerned
with the differences between the two scenarios.
*Section 2 discusses why this forecast is too high. The implica-
tions of the higher forecast are to exaggerate the costs of
abandonment by about $310 (1.1 percent rate impact) as shown
in Table 1.
- 14 -
E S R G
Before the end of the century, when additional capacity will
be required in the absence of Shoreham, a number of alternatives
to conventional coal may be available. The alternatives may
include combinations of greater conservation, wind generated
power, solar power, and modular power systems (e.g., fuel cells
or fluidized bed combustion). Additionally, there is the
possibility that refurbishing and extending the lifetime of aging
oil-fired units may prove cost-effective. Ail these
possibilities are currently under active investigation. However,
because of present uncertainties concerning availability,
engineering, and costs, they have not been included in this
analysis. Should the uncertainties concerning these alternatives
to coal be resolved favorably over the fifteen-year period before
makeup capacity for Shoreham is required, then the costs of
substitute power may well be less than those calculated here.
Costs of Operating Shoreham
If Shoreham does operate, the costs of both substitute
energy and new generating capacity in the late 1990s, discussed
above, can be-avoided. However, substantial other costs will be
incurred to operate the plant. These include the costs of nuclear
fuel, operations and maintenance costs, additional capital ex-
penditures over the life of the plant, costs of decommissioning
at the time of plant retirement, and costs for disposal of
radioactive fuel. Additionally, the electric revenues required
from customers will include Shoreham property taxes, though this
is partially offset by property tax charges for the additional
construction eventually required in the Shoreham-Out case.
- 15 -
E S R G
Critique of LILCO
In Section 8 of this report, LILCO's findings on the costs
of not operating Shoreham are discussed. LILCO's analysis
contains serious shortcomings in method (for example, the
findings are expressed in inflated dollars extrapolated over a
forty-year period) and flaws in judgement (costs that would be
incurred whether or not Shoreham operates are charged to abandon-
ment (such as the Bokum write-off and currently-planned system
upgrade expenses). Furthermore, undocumented "engineering"
estimates of nuclear plant performance and costs are relied on
that are much more optimistic than indicated by analysis of the
actual experience. There is simply no valid technical basis for
LILCO's hysterical tone concerning the economic consequences of
Shoreham. Indeed, of the $25 billion difference between LILCO's
estimates and, say, the Rate Wash scenario, over 90 percent
disappears simply by employing a common time frame and
consistently discounting to common dollars (Table 13). The bulk
of the remainder is related to extra costs that LILCO incorrectly
charges to abandonment and the combination of high forecasts of
load growth and low projections of Shoreham costs of operation.
Finally, a small fraction (less than 2 percent) of the difference
is related to the cost sharing scheme (91 percent of Shoreham in
Rate Base) employed in the rate base. LILCO not only fails to
consider a scenario where Shoreham cost recovery is shared
between ratepayers and stockholders, but actually assumes that
ratepayers would pay more for the Shoreham investment when the
plant is abandoned than if it ran.
- 16 -
E S R G
Finally, LILCO's critique of a preliminary version of the
present document is briefly reviewed. In its critique, the
Company "adjusts" the County's findings by reinserting its own
assumptions and not surprisingly rederives its own estimates. A
number of miscellaneous criticisms are shown to be unfounded in
Section 8.
LILCO's presentation, in its methods, scenario definition,
and assumptions, consistently biases the estimate of cost impacts
to favor Shoreham operation. The range of scenarios developed
here show, contra-LILCO, that under reasonable variation of key
parameters, the cost impacts of not operating Shoreham are not
likely to be far from zero, one way or the other.
Other Issues
Certain other issues beyond the electric cost impacts
focussed on in this analysis should also be considered to fully
assess the Shoreham question. First, since in the scenario
emphasized here LILCO customers are not assessed the full
capital-related costs of the Shoreham plant, the impact of such
partial recovery of investment on LILCO's financial health
deserves consideration. Georgetown Consulting Group is
developing recommendations for treating the abandoned Shoreham
investment consistent with equity, sound regulatory principles,
and the continued financial and operational viability of LILCO.
At this time, it may be stated with confidence that in the
benchmark 91 percent recovery Rate Wash scenario, the C~pany's
financial health can be readily maintained. The County's final
recommendation regarding the appropriate regulatory treatment of
the Shoreham abandonment will be made to the PSC at a later date.
- 17 -
£ S R G
Second, the reduced property taxes resulting from not
opening Shoreham are a credit to required revenue for
electricity. But at the same time they are a loss to government
revenues and would have to be made up. Here, it is worth noting
that the individuals most affected by the loss of Shoreham
property tax revenues, those in the vicinity of the plant,
benefit the most from avoiding both nuclear risk and depressed
property values.*
Third, we note that health and safety tradeoffs are not
quantified here. Any negative impacts or costs of Shoreham
abandonment would have to be weighed against the desirability
of avoiding, for example, public safety risks.
Fourth, for the longer term, there is a benefit to the
Shoreham-Out case not included here. When Shoreham would be
retired at the end of its useful life, additional construction
would then be required while, on the other hand, the additional
plants required toward the end of the century if Shoreham does
not operate will have many operational years remaining.
Finally, this analysis does not take account of the
likelihood that Shoreham's in-service date will be delayed
beyond January 1, 1984, nor does it consider the costs
associated with such delay. The impact of one year's delay is
approximately a $300 million increase in the cost of plant,
which would lead to even higher base revenue requirements in
the future. In this case, the economics of Shoreham
abandonment on January 1, 1984 would be improved.
*These matters will be discussed in forthcoming studies prepared
for Suffolk County.
- 18 -
E S R G
' 2. LOAD FORECAST
An independent forecast of the annual electrical energy
requirements and peak load (mmximum demand for power during the
year) has been performed.* The forecasting model used -- a detailed
end-use/engineering computer system -- has been applied to
forecast the demand for electricity in the LILCO service area
since 1977.
The forecasting model has in the past produced stable and
high-confidence forecasts. It anticipated the necessity for
LILCO to radically revise its long-range forecasts during the
late 1970s and early 1980s. The historic pattern is illus-
trated in Figure 4, which shows the precipitous drop in the
LILCO forecast of the 1990 summer peak after 1974. Earlier
ESRG forecasts are also shown.
The dramatic decrease in LILCO's load growth forecasts
(and corresponding adjustments in plans for new power plant
construction) can be traced to several factors. First, the
slowdown in population and economic growth prospects for Long
Island from the post-World War II boom levels were gradually
incorporated into the forecasts. The pattern of levelling off
in population growth during the 1950-1982 period is shown in
Figure 5.
* Full documentation on the mathematical structure of the ESRG
model, data base, assumptions, and literature references are
contained in Technical Report A.
- 19 -
~ S R G
Figure 4
COMPARISON OF HISTORIC CHANGES IN 1990 PEAK FORECAST
SO00
7000
6000
5000
4000
3000
2000
1000
0
ESRG
YEAR OF FORECAST
- 20 -
E S R G
GROWTH
1.5
1.0
POPULATION
.5
OF NASSAU AND SUFFOLK COUNTIES
FROM 1950 TO 1987_
1960 1970 1980 1990
YEAR
: (millions)
0
1950
Second, the changes in energy consumption patterns,
conservation initiatives, and the regulatory and policy
context that were ushered in by the 1973 oil embargo and energy
price jolts were eventually recognized as permanent alterations
to the long-term energy planning context, rather than as
temporary aberrations.
Third, serious methodological and conceptual pitfalls in
LILCO's forecasting apparatus were identified. These were
largely corrected.
Despite the corrective alterations in their earlier
forecast procedures, the Company retains to this day a tendency
to forecast with unwarranted optimism. Figure 6 shows the
Company summer peak forecast to the end of the century.* The
average annual growth rate is 1.6 percent per year. For
contrast, the actually experienced summer peak over the
1973-1982 period is also shown (the growth rate was 0.5 percent
per year) along with a time trend on that historic experience.
Finally, the forecast developed for the current invesigation
(0.8 percent per year) is also shown on Figure 6.
Analysis of the assumptions in LILCO's latest forecast
reveals that the higher LILCO forecast is traceable to certain
* The Company current long-range forecast is contained in the
1983 Report of Member Systems of the New York Power Pool
(Vol. 1) submitted to the New York State Energy Office.
22 -
E S R G
Figure 6
COMPARISON OF 1983 LILCO AND ESRG PEAK FORECASTS
AND GROWTH TREND IN PEAK
4000
3500
3000
2500
LILCO
ESRG
TREND
NORMALIZED SUMMER PEAK EXPERIENCED (MW)
- 23 -
judgemental rapid-growth inputs and some continuing problems
with self-consistency in their methods.*
The summary independent forecasts used in the Shoreham
impact analysis are presented in Table 2. These are labelled
Base Case forecasts since they capture evolving trends in
prices, regulatory policy, technology, consumer behavior, and
conservation effort. They are employed in the basic cost
comparisons of Shoreham-In versus Shoreham-Out. The results
are recast as growth rates in Table 3. Below we shall
introduce an alternative scenario -- the Conservation Policy
Case -- which shows how through a more vigorous promotional
effort by LILCO, the forecast could be reduced substantially.
The breakdown of Base Case energy requirements for
subcategories within the residential, commercial, and
industrial sectors is displayed in Table 4. As seen there,
consumption increases are anticipated for most of the
* The critique of LILCO's methods is spelled out in
Technical Report A. The main problems are: (1) there are
discontinuities in its short-range (to 1986) and long-range
methods leading to inexplicable and unreasonable jumps in
demand; (2) there is overestimation of residential
appliance ownership levels by the year 2000 (e.g., 3.4
television sets per houshold in a period of shrinking
household size); (3) there is extreme growth in electric
water heat and electric space heat usage (virtually all new
customers plus substantial switching by existing oil and gas
users); and (4) there are no price and conservation impacts
assumed in certain commercial subsectors (despite the large
price increases anticipated during the 1980s) even though
the time series used to generate forecasts dates back to
the rapid-growth period of the 1960s.
- 24 -
£ S R G
TABLE 2
FORECAST OF ENERGY AND PEAK DF24AND
ENERGY EH GUH PEAK POUER LOAD IN
LILC083 RESZ~ENT. COHHER, INDUGTR. OTHER TOTAL GUHHER WIHTER
1982 5574, 5340, 1205. 1637, 13757, 3070. 2471,
1983 5640. 5360° 1240, 1650. 13900, 3100. 2500.
1984 5700. 53G0, 1280, 1670, 14040, 3120o 2530°
1985 5760, 5410, 1320. 1680o 14170, 3140, 2560,
1986 5800, 5480. 1350, 1700, 14330, 3160, 2600.
1987 5840, 5550, 1380. 1720, 14500. 3190. 2640.
1988 5880, 5620. 1420o 1740o 14660, 3220. 2680,
1989 5920, 5690, 1450, 1760, 14820, 3240, 2710,
1990 5960, 5760, 14G0, 1770, 14980, 3270, 2750,
1991 5990, 5830, 1510, 1790. 15:30, 3300, 2790.
1992 6010, 5910, 1540, 1810, 15280, 3320, 2820,
1993 6040, 5980, 1580, 1830, 15430, 3350, 2860,
1994 6060, 6060, 1610, 1850. 15570, 3380, 2890.
1995 6080, 6130, 1640, 1870, 15720, 3410, 2930,
1996 6100, 6210, 1670, 1890, 15870, 3430, 2960,
1997 6130, 6280, 1700, 1910. 16030, 3460, 3000,
1998 6160, 6360, 1740, 1930, 16190, 3490, 3030,
1999 6200, 6440, 1770, 1960, 16360, 3520, 3070,
2000 6230. 6520, 1800, 1980. 16530, 3~60, 3110.
25 -
E S R G
TABLE 3
FORECAST SUMMARY
Energy Requirements (million KWH)
Total (includes misc. and losses)
Residential
Commercial
Industrial
Peak Power (Thousand KW)
Sum~er
Winter
1982
Growth
Rate
2000 (%)
13,757 16,530 1.0
5,574 6,230 0.6
5,340 6,520 1.1
1,205 1,800 2.3
3,070 3,560 0.8
2,471 3,110 1.3
- 26 -
E S R G
TABLE 4
DISAGGREGATED FORECAST BY SUBSECTOR COMPONENTS
LILCO
LILCG83
BAS~' CASE - ~ESIDENTIAL SECIOR - ENER(~Y IN OWH
1991 1994 1997
1982 ~985 1988
1339, 1.348, 1332,
268, 276, 283,
822. 841. 858,
366, 369. 375,
424, 441,
62, 64, 65,
290, 303, 307,
342, 342, 337,
291. 3~8, 337,
254, 30~, 351,
i REFRIGERATORS
2 FREEZERS
RANGES
4 LIGHI'ING
TELEVISIONS
61 CLOTHES D~YERS
71 CLOTHES WASHERS
DISH WASHERS
WATER HEATERS
10: ROOM A/C
CENTRAL. A/C
SPACE H~AI*ERS
HFATINGAUXII. IARY
14t HISCELLANE~US
1295, ]236,
3¢)6, 300,
289, 2¥5,
87%~. 882,
~85, 396,
67. 6~,
311. 315,
359 381.
396 436,
345 342,
418 452~
1175,
291 ·
301 .
889.
409,
?0,
140,
321,
404 ·
472,
487 ·
LILI;08~
BASE CASE - COHMERCIAL
1982 1985
It OFFICES
HEATING
COOl. INS
L. IGHIING
AOX ~ POWER
21 ~ETAIL
HEATING
COOLING
LIGHTING
AUX ~ P~WER
HOSPITALS
1 HEATING
2 COOL[NS
LIGHTING
AUX ~ POWER
SCHOOLS
1: HEATING
2: COOLING
3: LIGHTING
4: AUX ~ POWER
OTHER
HEATING
COOLING
LIGHTING
4: AIJX i POWER
49. 61.
337, 341,
466, 461.
387, 399,
23. 28.
330. 337,
1237. 1260,
445, 46l,
146. 145.
29, 79,
16, 17.
76, 66,
317, 277,
187. 164,
22. 27,
249, 255.
553. 581.
364. 389.
SECTOR - ENERI~Y 1N I~WH
1988 1991 1.994 1~97
2000
i151,
280,
306.
894,
423,
518,
142~
328,
329.
427.
507~
335.
524.
2000
73, 85, ?8. 11:~. 124,
352, 362, 373. 383, ~93.
476, 491, 507, 523, 538,
421, 444, 468. 493. 520.
33, 39, 44, 50, 56,
348, 360, 371, 383, 395,
1294, 1328, 1362, 1396, 1431,
488, 517, 547, 578, 6ll,
7, 8, 9, 10. li.
51, 51, 51, 51, 51,
146. 147, 148, 148, 149,
82, 85, . 88. 90, 93,
LIt. C083
BASE CASE - INDUSTRIAl.
1982 1985
20: FOOD 58. 65.
22: TEXTILES 21. 22,
231 APPAREL 16. 18.
24: LUMBER 7,
25: FURNITURE 15. 16,
261 PAPER PROI)UCTS 47. 53,
27: PRINTING & PUBL. 90° 116.
28: CHEHICALG 58. 59.
29~ PETROLEUM ~ COAL 5.
33t PRIMARY METALS 40. 43.
34: FABRICAT. HETALS 73. 76.
35t MACHINERY 122. 13l.
36: ELECTRIC EQUIP. 255. 280.
37t TRANSPGRTAYION 176. 184.
30: RUBBER & PLASTIC
3ti LEATHER ~. 4.
32~ STONE,CLAY,GLASS 11. 12o
38: INSTRUMENTS 118. 129.
39: DTHER 33. 34.
21, 24. 28. ~1. 35.
67. 68, 69, 70. 71.
278. 278. 279. 279, 280.
169, 173, 177, 18/, 185.
32, 38, 4~, 49,
262, 268, 27~, 282, 289,
604, 627, 649, 672, 695,
415, 44~, 471. 502. :534.
SE[:IOR kN~R~Y IN GWH
1988 1991 1994 1997
7~. 77 82. 88.
21. 21 2l, 20,
20, 22 24, 26,
11, 13 15, 17,
16o 17 17o 18.
57. 62 66, 70,
142, 169 196. 224.
59. 59 58, 58,
6. 7 8. 9.
45. 48 50~ 52°
78. 80. 82. 84.
1~8o 145. 152.
300, 321. 342, 365,
189, t91, 192, 192,
75, 84, 94, 105.
4. 4. 5.
12, 13. 13.
1~7. 147, 156, 166.
34, 34, 34, 34.
2000
?3,
19.
28,
19,
18.
252,
57,
10,
54,
86.
167,
388,
190,
116,
6,
~4,
177,
- 27 -
E $ R G
residential end-uses. This results from folding together the
anticipated increases in appliance ownership, the number of
households*, and usage of electric space and water heat, on the
one hand, and improvements in the efficiency of new residential
equipment and structure, on the other hand.
The commercial sector growth is driven primarily by rapid
employment growth rates in certain sectors (2.2 percent per year in
finance, insurance, and real estate, and 1.6 percent per year in
service industries), and increasing use of electric space
and water heat. Demand growth is moderated by slow employment
growth projections in government sectors (0.5 percent per year),
and in those which directly service local populations (e.g.,
schools and hospitals).
At 2.3 percent per year,
fastest growing demand. This
industry is the sector with the
is due to a small degree to
increasing employment (about 0.1 percent per year), but due primarily
to projected increases'in the electrification and automation of
the production process. For example, the amount of electricity
consumed per employee in 1990 versus 1982 is projected to
increase by 70 percent in the printing and publications
subsector, and 20 percent in the electrical equipment sector
and the transportation sector.
* Households are projected to grow at an average rate of 0.7
percent per year to the year 2000 on Long Island, with multi-
family units growing somewhat faster (1.3 percent per year) than
single-family units (0.5 percent per year). The reason that the
number of households grows faster than population (0.3
percent per yearl is that the size of households -- the average
number of persons per household -- is projected to decrease.
- 28 -
£ S R G
The summer peak, the most critical forecast in determining
the need for additional generating capacity, is seen from Table
2 to have a forecast growth of 0.8 percent per year. This is
somewhat less than the 1.0 percent per year forecast for total
energy requirements for energy as a whole, for several reasons.
First, the various end-uses of demand contribute differentially
to peak load (for example, on average a KWH consumed for
cooking contributes much more than one used for lighting). But
the most rapidly increasing end-use, electric space heating,
does not contribute at all to summer peak. Second, there is an
intersectoral effect: the industrial sector which has the most
rapidly growing energy use also has the most evenly spread
demand due to its relatively regularized operations over both
daily and annual cycles. The above factors contribute to a
more rapid increase in total energy consumption (1.0
percent per year) and winter peak demand (1.3 percent per
year), than in summer peak demand (0.8 percent per year).
29 -
E $ R
3. SUPPLY PLANNING
In this section, the current and planned supply situation
in the LILCO service area are summarized. It is found that if
Shoreham is abandoned and no additional conservation is
achieved, LILCO, in addition to capacity additions already
planned, will need to add capacity beginning in 1998. For
purposes of this study, two extra coal plants are assumed, one
in 1998 and one in 2000.
Currently, the supply of electricity to LILCO's customers
derives from three sources. The main share (about 64 percent)
of this energy is generated by LILCO's own residual oil-fired
power plants. Another 20 percent of LILCO's energy requirement
is purchased from the New York Power Pool (NYPP) and is
transmitted to Long Island over LILCO's existing tie-line to
Con Edison.* The remaining generation is from LILCO's
gas-fired stations.
Installed capacity currently consists of a total of 3,767
MW: consisting of oil-fired units (2,672 MW), combustion
turbines (1,037 MW), diesel units (12 MW), and several hundred
megawatts of interties to other power systems (46 MW of which
is currently considered as available for meeting peak demand).
Apart from bringing Shoreham on-line in 1984, LILCO's
current supply plans include some oil-to-coal conversions, a
small refuse burning plant at Mitchell Gardens, a share of the
*Currently, LILCO's share is about 300 MW. There is a plan to
upgrade this 345 KV transmission line by 1986 so that LILCO's
share would becomes600 MW. There is, in addition, curently an
an interconnect to the New England Power Pool of about 75 MW
sustainable with upgrade to about 300 MW planned for the
late 1980s.
- 30 -
E $ R
upstate Nine Mile Point 2 nuclear facility, upgraded
transmission interties to the New York Power Pool (NYPP), and a
sequence of oil plant retirements. In this study two basic
scenarios have been developed to meet LILCO's capacity
requirements, one with and one without Shoreham operating.
Thus two different power plant investment programs were
developed for LILCO to fit the needs of these two scenarios.
The aim of these programs is to keep the cost of the
electricity supply as low as possible for ratepayers in either
scenario. In addition, the transmission system links between
LILCO and the rest of the NYPP were reviewed in light of
their potential for transporting additional electric power to
Long Island to replace the power that would have come from
Shoreham.
In performing this supply assessment, all recent LILCO
studies that attempt to quantify the economic impact of not
allowing Shoreham to operate have been reviewed along with the
most recent NYPP generation planning and power flow computer
simulations. The two scenarios embody the following findings
and assumptions.
Capacity Requirements
The New York Power Pool (NYPP) required reserve margin of
18 percent is a reasonable basis on which to phase in new power
plants to LILCO's supply mix. On the basis of the ESRG demand
forecast, and utilizing LILCO's "extended retirement" dates
- 31 -
E S R G
for its existing generation units, LILCO's capacity for meeting
summer peak demand will fall below its capacity requirements,
without Shoreham operating, by 1998. With Shoreham
operational, this will not happen until 2004. Figure 7
illustrates the summer capacity requirements against total
capacity for the scenario with Shoreham not operating.
Additional 400 MW coal plants, one in 1998 and one in 2000, are
thus included beyond what would be needed in the Shoreham-In
cas e.
Planned Generation and Transmission System Upgrade
Given the significant level of oil consumption by LILCO
generating plants expected during the period from 1985-1997,
LILCO is assumed to invest in the coal conversion of Port
Jefferson units #3 and #4, and in a new 600 MW transmission
line in 1990 to the Con Edison service territory in all
scenarios. Both of these major upgrades are currently
part of LILCO's official power supply plans as submitted this
year to the New York State Energy Master Planning Board.
Additional coal conversions are not judged to be cost effective
or necessary in either scenario.
In this study it is not assumed that the converted
coal plants at Port Jefferson will be used to make up
the power that would have come from Shoreham. In the years
from 1984 through 1997 most of the power required to replace
the output of Shoreham will derive from LILCO's own residual
- 32 -
E S R G
Dk~4A/~D
(~,~)
Figure 7
REQUIRED CAPACITY AND TOTAL CAPACITY~
SHORENAM-OUT
4750 IN THE YEARS 1998, 2000, and 20
400 MW COAL ~ITS ADDED
TOTAL
4500 CAPACITY
REQUIRED
CAPAC I TY
4250
4000
3750 SUMMER
PEAK
D~4AND
3500
3250
3000
YEAR
*FOR THE YEARS 2004 AND BEYOND, CONSTRUCTION PROGRAMS
WOULD BE COMPARABLE WITH, OR WITHOUT, SHOREHAM
- 33-
oil-fired units, though some is projected to come from other
NYPP member utilities. However, with the completion of the new
transmission link to Con Edison by 1991, the portion from each
will change significantly. After the new transmission line is
completed, the transmission capacity from the New York Power
Pool to LILCO will at least double. During the 1990s, at
least one-third of the power needed to replace the output of
Shoreham, if it does not operate, is projected to be available
from the power pool at a price of about 85 percent of the cost
of power from LILCO's oil-fired units which otherwise would be
needed. This replacement power for Shoreham will be available
in addition to the significant amount of power that LILCO
currently purchases from the Power Pool (about 20 percent of
total energy requirements in 1981 and 1982). These estimates
result from a review of the outputs of LILCO's own dispatch
model (a model which simulates the generation system) and the
output of runs on the new and more sophisticated MAPS
multi-area dispatch model used by NYPP. The MAPS outputs show
considerably more power available than does LILCO, but more
conservative assumptions, consistent with LILco'S findings, are
utilized in the basic runs here. In Section 7, the effects of
assuming no NYPP power to replace Shoreham are quantified and
found to be small (see Table 1).
- 34 -
£ S R G
New Power Plant Construction
Given uncertainties as to the costs of less conventional
sources of power in the next 15 years, it has been assumed that
without Shoreham, LILCO builds a 400 megawatt (MW) coal unit
with scrubbers in 1998 and 2000 for a total of 800 MW, to
replace the 809 MW of capacity lost from Shoreham. The output
of these units will replace the lost output from Shoreham after
1997, when the additional power is needed. Interestingly, with
both coal plants in place there is more oil displacement than
would have been provided by Shoreham. The construction costs
projected for these coal units using statistical techniques are
$2040 million in 1998 and $2399 million in 2000, comparable to
those LILCO has assumed recently for new coal units. The
annual required revenues for these units were calculated using
a financial model. They appear in the column "Coal Plant Cost"
in Table 5 below.
Assumptions on the operating characteristics of these new coal
units were taken from the 1982 version of the Electric Power Research
Institute (EPRI) Technical Assessment Guide. These include operations
and maintenance (O&M) costs of 7.72 mills per KWH in 1983 (escalated
at 1 percent above inflation), a capacity factor of 70 percent*, and
an annual average heat rate of 10,060 BTU's of coal per KWH generated.
After the year 2000, when the second 400 MW coal plant will be
required, the LILCO construction program is assumed to be the same
whether or not Shoreham operates.
*The EPRI availability of 74.3 percent was reduced to a 70 percent
capacity factor to allow for some degree of load following. Since
Shoreham's capacity factor is projected to be somewhat lower
this, these two coal units will more than replace the energy
from Shoreham after 2000.
35 -
E S R G
TABLE 5
ANNUAL SHOREHAM REPLACEMENT POWER COSTS*
Plant, Fuel and O&M Cost
(in millions of current $)
Coal Plant Fuel and Total
Year Cost O&M Cost Cost
(1) (2) (3) (4)
1984 0 177 177
1985 0 199 199
1986 0 224 224
1987 0 251 251
1988 0 283 283
1989 0 321 321
1990 0 347 347
1991 0 359 359
1992 0 388 388
1993 0 419 419
1994 0 453 453
1995 0 489 489
1996 0 529 529
1997 0 571 571
1998 418 505 923
1999 397 544 941
2000 865 451 1,316
2001 820 469 1,289
2002 773 502 1,275
2003 730 521 lr251
Total 4,003 8,002 12,005
* Costs include a 2.4 percent allowance for working capital
and a 4 percent revenue tax.
- 36 -
E S R G
Fuel Prices
In the absence of Shoreham, LILCO's existing oil-fired steam
plants will generate additional power (at least until the substitute
coal plants come in-service).* The fuel prices for this make up
power vary with sulfur content. In i983, the average prices
will be about $25.2/barrel for relatively high sulfur oil and
$27.4/barrel for medium sulfur oil (burned primarily at the
Barrett and Glenwood facilities). The make-up oil generation is
comprised of a mixture of plants using the higher (about 30
percent) and lower (about 70 percent) price oil at an average heat
rate of 10,400 BTU's per KWH. This translates into a fuel cost
per KWH of 42.3 mills. To this, 3.8 mills per KWH have been added
for oil plant operations and maintenance costs, as well as 1.0
mill per KWH as an allowance for working capital related to fuel
storage and 2.0 mills per KWH for revenue taxes. This yields
a total of 49.1 mills per kilowatt-hour for additional oil power
in 1983.
It is further estimated that the price of oil will escalate
at the rate of inflation through 1987, and then at 2 percent above
the rate of inflation for the long term. This yields
significantly higher oil prices in the future than LILCO has
recently projected, and is based on a tightening of the oil market
with international economic recovery.
*A very small increase in combustion turbines output
150 GWH) would also occur.
- 37 -
(approximately
E S R G
With respect to coal prices, it is estimated, along with
the 1983 NYPP report, that a mid-range price of coal in 1983 to
LILCO will be $2.24 per million BTUs. Coal prices are projected
to escalate at 1 percent above inflation.
In computing revenue requirements for each scenario, an
allowance is made for working capital on fuel inventories at a
rate of 2.4 percent of annual fuel costs, and a revenue tax of
percent is also included. Thus, for example, the total cost of
oil replacement power for Shoreham is assumed to be 52.2 mills
per KWH in 1984.
Results
Using the preceding findings and estimates concerning
LILCO capacity requirements and new power plant construction,
coal conversions, transmission line upgrading, and fuel prices,
the quantity and cost of replacement power required in the
absence of Shoreham were computed. Table 5 presents the annual
replacement power costs for the basic scenarios when Shoreham
is not operating. The electric energy generation which would
have been produced by Shoreham and must be replaced rises from
3.4 billion kwh in 1984 to 4.47 billion kwh in 1989 and
subsequent years (see Section 4). The annual fixed costs of
the new coal plants beginning in 1998 appear in column 2.
Column 3 provides the annual fuel and operations and
maintenance costs of the replacement power, which when added to
the fixed costs in column 2, yields the total annual cost of
- 38 -
£ S R G
the replacement power, shown in column 4. These costs begin at
$177 million in 1984, and reach $1,251 million in 2003. Note
the reduction in fuel and O&M costs in 1998 and 2000 when the
operation of the new coal units displaces oil-fired generation.
Alternative Power Sources
Before the end of the century, when additional capacity
will be required, a number of alternatives to conventional coal
plants may be available. The alternatives may include greater
conservation, wind generated power, prefabricated modular units
(fuel cells, batteries, integrated gasification-combined cycle
coal units, pressurized fluidized bed combustion), and solar
power. Additionally, there is the possibility that
refurbishing and extending the lifetime of aging oil-fired
units may prove cost-effective. These non-conventional
approaches to planning are at various stages in the research,
development, and demonstration process. Because uncertainties
concerning availability, engineering, and costs remain at this
time, these alternatives have not been included in this
analysis.* Should the remaining uncertainties concerning these
alternatives to coal be resolved favorably over the
fifteen-year period before makeup capacity for Shoreham is
required, then the costs of substitute power may well be less
than calculated here.
*An exception is utility based conservation investment programs
which are being actively pursued in a number of states. A
conservation-oriented scenario for LILCO has been developed
in Technical Report C and summarized in Section 6 below.
- 39 -
E S R G
4. SHOREHAM OPERATIONS AND COSTS
In this section, a summary of the analysis and assumptions
employed in estimating the costs and characteristics associated
with Shoreham operations is presented.* Included are annual
capacity factors, operations and maintenance costs, net capital
additions, fuel costs, spent fuel disposal costs, and
decommissioning costs. The results provided here are input
assumptions to the complete required revenues impact analysis
presented in Section 5.
Capacity Factors
The capacity factor of a power plant is defined as the net
annual generation divided by the maximum potential annual
generation. Maximum potential generation is the rated capacity
of the plant times 8,760 (hours in a year). Thus, the annual
capacity factor can be thought of as the fraction of the year
that the plant will operate at the equivalent of the full rated
capacity.
For nuclear power plants there are several factors which
lead to experienced capacity factors well below 100 percent.
These include both forced and scheduled outages for maintenance
and equipment repair, refuelling outages, and outages mandated
by the U.S. Nuclear Regulatory Commission (NRC) for safety,
training and licensing. According to data published
*Full documentation for the results summarized in this section
is presented in Technical Report B: Shoreham Operations and
Costs.
- 40 -
E S R G
by the U.S. Department of Energy, average capacity factors for
operating nuclear power plants in the U.S. during the 1973-1982
period have ranged from a low of 43.5 percent (1974) to a high
of 63.9 percent (1978). The industry-wide average over this
period was 56.7 percent, and the average for the last four
years was 56.1 percent.
There has been, however, a wide variation around these
averages depending on the particular plant and year considered.
In order to understand the basis for this variation, we divided
outages into two sets. One set consists of outages for re-
fueling, regulatory restriction (i.e.~ NRC mandated), and
operator training and licensing (hereafter referred to as
"refuelling and NRC" outages). The other set consists of all
other outages, including those associated with equipment
failure and maintenance (hereafter referred to as "maintenance
and repair" outages). To explain the maintenance and repair
outages~ statistical procedures were employed in the present
study. The result of these procedures -- multivariate
regression analysis -- provides the magnitude of contributions
to observed capacity factors (adjusted to exclude refueling and
NRC outages) from each of several explanatory variables
associated with the characteristics of the nuclear power plants
in the data base. Once these magnitudes are established they
can be applied to any specific nuclear plant (such as Shoreham)
whose characteristics are known, as one tool to predict future
maintenance and repair outages.
- 41 -
E S R G
The data base used in the statistical analysis consists of
annual capacity factors and outage information for 68 nuclear
power plants, essentially all commercially operating units in
the U.S., over the years 1975-1981. Detailed data for those
years were available from the Nuclear Regulatory Commission
(NRC) in its published "Grey Books" and computer tapes. Data
on plant characteristics were also obtained from the NRC.
A comprehensive series of multivariate regression analyses
were carried out. Among the explanatory variables which were
explored for statistical significance were plant size (in
Megawatts), reactor type (PWR or BWR*), age or year of
operation, presence of cooling towers, saltwater cooling,
reactor manufacturer, multiple unit siting, and whether the
observation was in the years immediately following the Three
Mile Island (TMI) accident. Some anomalously low adjusted
capacity factors were excluded, e.g.r those of the Diablo
Canyon facility (which received a low power license but never
has operated) and of TMI after its accident.
No statistical significance in explaining adjusted
(maintenance and repair based) capacity factors was found for
multiple unit siting and the TMI years. Significant aging
effects were found, however, including both capacity factor
increases during the early years of "maturation," and long-term
capacity factor decreases for saltwater-cooled plants.
The refueling and NRC-mandated outages, being less clearly
related to long-term plant performance characteristics, were
analyzed separately. Year-by-year data were collected
*Pressurized water reactor or boiling water reactor.
- 42
E S R G
on such outages for all BWR plants, and a weighted average of
such outages was developed for the years 1975-81. The annual
rate among BWRs was found to be 14 percent, almost all of it
attributable to refueling outages.
The results of the analyses are graphed in Figure 8, where
the regression results, modified to incorporate a 14 percent
annual refueling and NRC outage rate, beginning in the second
year, are shown through the eleventh year of operation. Figure
8 also shows LILCO's assumptions concerning total Shoreham
capacity factors, as well as the assumptions employed by ESRG
in the present study. While there are indications of a rather
rapid decline in Shoreham capacity factors after its tenth year
of operation, the assumption actually used in this study is
that the Shoreham capacity factor will rise to 63 percent by
its sixth year of operation and then remain constant at that
level for the remaining 20 years of its planned operating life.
Operations and Maintenance
The operations and maintenance costs for electric utility
power plants are passed on to ratepayers as expense items. For
nuclear power plants these costs include eight subcategories in
the Operations category, and five sub-categories in the
Maintenance category, as reported in the annual Form 1
submitted to the Federal Energy Regulatory Co~u~ission (FERC).
These costs are also reported by the U.S. Department of Energy.
- 43
Figure 8
SHOREHAM CAPACITY FACTORS
ESRG AND LILCO ASSUMPTIONS
70
60
5O
40
CAPACITY
FACTOR
PERCENT)
30
20
10
~ LILC0 ASSUMPTION~
. .......... -j~-r~-~-r~-- ..... ~ ESRG ASSUMPTIONS
..." ,, REGRESSION RESULTS
1 2 3 4 5 6 7 8 9 10 11 12
YEAR OF OPERATION
- 44
Industry-wide operations and maintenance costs for
commercially operating nuclear power plants in the U.S. have
increased dramatically over the past decade, from about $20
million in 1970 to about $1.4 billion in 1980. Since both
inflation and an increase in installed nuclear generating
capacity have occurred during this period, it is useful to
recast these figures in constant (i.e., inflation-adjusted)
dollars per kilowatt of installed capacity. The increase was
from about $12.50 per KW in 1970 to about $35.90 per KW in 1980,
expressed in 1983 dollars. Thus, over the 1970-1980 period,
average industry-wide nuclear plant operations and maintenance
costs escalated at about 11 percent per year above the general
rate of inflation. In fact, after correcting for economies
associated with increasing plant sizes during this period, one
finds that the per unit costs increased at a rate of about 15
percent per year above inflation.
Table 6 below shows industry-wide average operations and
maintenance costs per kilowatt for nuclear stations in the U.S.
for each year in the 1970-1980 period in both nominal and
constant (1983) dollars. The table also shows percentage
changes from year to year and average growth rates over the
period. The real growth rate was 9.3 percent per year from 1970
through 1978 (the last full year before the TMI reactor
accident) and 11.0 percent/year from 1970 through 1980. While
the average operations and maintenance cost in the industry was
- 45 -
£ S R G
$35.9 per KW (1983 dollars), the costs of individual stations ranged
as high as about $75 per KW (1983 dollars).*
For a plant the size of Shoreham, the 1980 industry-wide
experience indicates an annual cost of $29.4 million (1983
dollars). Escalating by the 1970-80 average real rate of 11.0
percent per year, and adding an additional year of 6 percent
inflation, would give a 1984 operations and maintenance cost of
$47.3 million ($57.8 per KW). Continued escalation at these
historical rates would lead to annual costs greater than $400
million ($500 per KW) by 1998. As we shall see below, the
detailed statistical analysis employed here leads to much lower
predicted operations and maintenance costs for Shoreham over
its first fifteen years
trends.
OPERATIONS AND MAINTENANCE COSTS
of operation than these industry-wide
TABLE 6
FOR NUCLEAR STATIONS IN THE U.S.
Cost Cost
Year (S/KW) (19835/KW)+
1970 5.25 12.53
1971 5.02 11.40
1972 6.91 15.08
1973 6.38 13.16
1974 8.73 16.58
1975 9.94 17.27
1976 11.98 19.78
1977 13.65 21.29
1978 16.78 24.39
1979 20.93 28.04
1980 29.21 35.93
Average Growth
Rate (Percent)
1970-78 16.6 9.3
1970-80 18.6 11.0
+ Using GNP deflators.
*Some small old units, excluded from our data base and the above
averages, had costs approaching $150 per KW (1983 dollars) in 1980.
- 46 -
E S R
It is worthy of note that the Pennsylvania Power and Light
Company (PP&L) has forecast about $62 per KW operations and
maintenance costs in 1985 for its Susquehanna nuclear
generating station, also a BWR, which could be expected to have
somewhat lower costs than Shoreham due to its larger size
(1,052 MW) and multiple unit siting. PP&L has also predicted
that these costs would reach about $110 per KW by the early
1990s.
As we indicated above, operations and maintenance costs have
varied widely by plant and operating year. For this reason,
multivariate regression analysis has been used in the present
study to explain these costs and their variation in terms of
independent variables expressing power plant characteristics.
Numerous independent variables were explored. These included
plant size, age, vintage (first year of operation), geographic
location, demonstration unit, multiple unit siting, saltwater
cooling, 1980 operation (post-TMI experience), cooling towers,
reactor manufacturer, reactor type, turbine manufacturer, utility
size, and utility experience with nuclear plant operation. No
statistical significance was found for the last six variables.
Increases in constant dollar costs per KW were found for both
later vintage plants and older plants. Saltwater cooled plants
were found to experience more rapid cost increases with age,
presumably due to corrosion patterns, and larger plants were found
to experience economies of scale. While cost increases above the
- 47 -
E S R G
general rate of inflation were found, these are not nearly so
rapid as the industry-wide 1970-1980 escalation experience
discussed earlier. There are two principal reasons for this.
First, the regression equation expresses the age effects in linear
rather than exponential fashion. And second, the variable for the
year 1980 (post-TMI experience) nets out this large effect from
the general temporal trends, tending to attenuate the underlying
rate of increase found by the regression analysis.
The regression equation for nuclear operations and
haintenance costs was applied to the Shoreham facility, with
the following modifications. The equation was applied only to
the first fifteen years of Shoreham operations. Thereafter,
annual operations and maintenance costs were assumed to
increase only at the general rate of inflation (6 percent). An
additional cost of 4 percent was added to each year's
operations and maintenance costs to account for revenue taxes.
Table 7 below gives the operations and maintenance costs which
result from the foregoing analyses and assumptions, on a per KW
and total cost basis.
During the first fifteen years of service, Shoreham operations
and maintenance costs increase at a rate beginning at 5.6 percent per
year above inflation and declining to 3.3 percent per year by the
fifteenth year. These rates are far below those experienced
in the industry during the 1970s.
- 48
E S R G
TABLE 7
SHOREHAM PLANT OPERATIONS AND MAINTENANCE COSTS
O&M Cost Total O&M* O&M Cost
Year ($ KW) ($ Millions) year (S/KW)
Total O&M*
($ Millions)
1984 63.44 51.954 1999 265.65 217.570
1985 70.83 58.012 2000 281.59 230.625
1986 78.89 64.609 2001 298.49 244.462
1987 87.65 71.789 2002 316.40 259.129
1988 97.19 79.598 2003 335.38 274.677
1989 107.55 88.085 2004 355.50 291.157
1990 118.81 97.305 2005 376.83 308.627
1991 131.03 107.313 2006 399.44 327.144
1992 144.29 118.173 2007 423.41 346.772
1993 158.67 129.949 2008 448.81 367.579
1994 174.25 142.713 2009 475.74 389.633
1995 191.14 156.541 2010 504.29 413.011
1996 209.42 171.514 2011 534.54 437.791
1997 229.21 187.721 2012 566.62 464.058
1998 250.62 205.255 2013 600.61 491.901
*Revenue tax included.
Net Capital Additions
Nuclear power plants have continued to incur capital costs
in the years following the in-service date (initial commercial
operation), when the initial construction and financing costs
enter the rate base. As these new costs -- for land,
structures, reactor, turbogenerator, electrical and
miscellaneous equipment -- are incurred, they too enter the
rate base and the utility earns a return on them. Thus,
required revenues are increased as these capital additions are
made.
- 49 -
S R G
Both capital additions to and retirements from cumulative
nuclear plant capital costs are reported by utilities in the
Form 1 submitted annually to the Federal Energy Regulatory
Commission (FERC). The cumulative capital costs by nuclear station
are also reported by the U.S. Department of Energy. In the
present treatment only net annual capital additions are examined.*
In the present study, each year's net capital addition is
spread over all subsequent years by applying a levelized fixed
charge factor to represent LILCO's return on rate base for the
Shoreham facility%
Data on nuclear power plant annual net capital additions over
the period 1970-1980 have been collected from the FERC Form 1 reports
and the U.S. Department of Energy documents, on a station-specific
and year-by-year basis. Industry-wide totals over this period
increased from about $2.6 million in 1970 to about $840 million in
1980. Expressed in constant 1983 dollars per kilowatt of
installed capacity, these costs increased from about $3.5 per KW to
$24.7 per KW over this decade. Thus, the real per-unit costs of net
capital additions to nuclear stations increased sevenfold during
the 1970s.
*The result of this is to somewhat underestimate the additional
required revenues from capital additions. This is because the
capital removals are reported at original rather than depreci-
ated costs and rate base reductions are thereby overstated.
Futhermore, retired plant can still impact revenue requirements
through continued amortization, or as expensed items after
removal from rate base.
- 50 -
E S R G
Table 8 below shows the average net capital additions costs
per kilowatt for nuclear stations in the U.S. for each year in the
1970-80 period. Also shown are the annual percentage changes, and
average escalation rates over the entire decade. The real
escalation rate was 17.5 percent per year from 1970-1978 (the last
full year before the TMI reactor accident) and 15.9 percent per
year from 1970-1980. While the industry-wide average net capital
additions cost in 1980 was $24.7 per KW (1983 dollars), costs at
individual stations ranged as high as $126 per KW (1983 dollars)
in that year.*
For a plant the size of Shoreham the 1980 industry-wide
average costs for capital additions were $20.2 million (1983
dollars). Escalating this by the 1970-80 industry-wide growth
rate of 15.9 percent per year, and an additional 6 percent
inflation for one year, would give $39 million ($47.2 per KW) in
1984, Shoreham's first year of operation. Continued escalation at
the rates experienced during the 1970s would imply costs reaching
about $135 million ($165 per KW) by 1990 and about $700 million
($850 per KW) by 1998. By contrast, as shall be seen below, a
more detailed analysis gives much lower projected net capital
additions costs for Shoreham.
* During 1980 six nuclear stations incurred net capital additions
costs in excess of $49 per KW (1983 dollars), i.e. more than twice
industry-wide average in that year. These were the Beaver
Valley, Davis Besse, Oyster Creek, Pilgrim, San Onofre, and
and Surrey facilities. Four of these incurred costs of $90 per
KW (1983 dollars) or greater.
the
- 51
E S R G
TABLE 8
NET CAPITAL ADDITIONS
FOR NUCLEAR STATIONS IN THE U.S.
Cost Cost
Year (S/KW) (19835/KW)+
1970 1.46 3.49
1971 1.84 4.18
1972 3.96 8.65
1973 5.30 10.93
1974 4.74 8.99
1975 4.72 8.20
1976 6.51 10.75
1977 10.63 16.58
1978 9.24 13.43
1979 8.65 11.59
1980 20.08 24.70
Average Growth
Rate (Percent)
1970-78 25.3 17.5
1970-80 23.9 15.9
+Using GNP deflators.
The present study has employed multivariate regression
analysis to help explain the net capital additions costs and their
variation over stations and operating years. Among the independent
variables explored for statistical significance were plant size,
vintage, age, multiple unit siting, geographic location, cooling
towers, saltwater cooling, demonstration unit, and reactor
manufacturer.
A simple equation in which each of four independent
variables showed strong statistical significance was selected
from the regression study. These variables were plant vintage,
plant age, multiple unit siting, and saltwater cooling.
- 52
The results of the statistical analysis were applied to
the Shoreham facility with the following modifications. Net
annual additions in each year of operation, obtained from the
regression equation, are applied for only the first fifteen
years of Shoreham operations. Thereafter, the net additions
are assumed to increase only at the general rate of inflation (6
percent) through the twenty-fifth year of operation.
Expenditures are then assumed to decline linearly over the last
five years of operation. A four percent revenue tax was added
to each year's net capital additions cost. Finally, each
year's cost was spread over the life of the Shoreham facility
by applying a 17.87 percent levelized fixed charge rate.
Table 9 below shows both the annual net capital additions
per kilowatt and the annual revenue requirements as forecasted
on the basis of the results and assumptions employed. As the
figures in Table 8 show, the real escalation rate of Shoreham
net capital additions is about 14 percent after its first year
of operation, lower than the average experience of nuclear
plants in the 1970s. By its fifteenth year of operation this
rate falls to about 5 percent.
- 53 -
E S R G
COSTS
TABLE 9
AND REVENUE REQUIREMENTS FOR SHOREHAM NET CAPITAL ADDITIONS
(Current Dollars)
Net Capital Annual Re- Net Capital
Additions quired Revenue Additions
Year (S/KW) ($ Millions) Year (S/KW)
1984 35.3
1985 42 4
1986 50 2
1987 58 7
1988 68 1
1989 78 5
1990 89 9
1991 102 3
1992 116 0
1993 130 8
1994 147 0
1995 164 7
1996 184 0
1997 205.1
1998 228.0
5 4
11 8
19 5
28 4
38 8
50 8
64 5
80 1
97 8
117 7
140 1
165 3
193 3
224 6
259 3
Annual Re-
quired Revenue
($ Millions)
1999 241.6 296.2
2000 256.2 335.2
2001 271.6 376.6
2002 287.8 420.5
2003 305.1 467.0
2004 323.4 '516.3
2005 342.9 568.6
2006 363.4 624.0
2007 385.2 682.7
2008 408.3 745.0
2009 340.3 796.8
2010 272.2 838.3
2011 204.2' 869.5
2012 136.1 890.2
2013 68.0 900.6
Nuclear Fuel Costs
The cost of nuclear fuel for the Shoreham facility was
estimated to begin at a base value of 6.02 mills/KWH in 1983,
and escalate at 1.6 percent per year above the general rate of
inflation (itself 6 percent per year) thereafter. Both the
base value and the escalation rate are derived from LILCO
estimates (Madsen, Exhibit 1, PSC Case No. 28252). The base
value of 6.02 mills/KWH is LILCO's 1983 nuclear fuel cost with
its spent fuel disposal component subtracted. The 1.6
percent/year real escalation rate is the average real rate of
growth assumed by LILCO for nuclear fuel costs from 1983-2000.
- 54 -
E S R G
Disposal of Spent Fuel
At present, spent nuclear fuel is temporarily stored
on-site in storage pools, after a several year stay in nuclear
reactor assemblies. Since the capacity of these pools is
limited, permanent and safe disposal will ultimately be
required. The cost of ultimate disposal has not been reflected
in utility costs and electricity rates, as have other elements
of the nuclear fuel cycle. Indeed, both the costs and
technology of disposal have been subject to continuing
discussion and debate.
The federal government has taken responsibility for the
ultimate disposal of spent nuclear fuel. The current plan is
to make a deep geologic repository available for spent fuel
shipments near the end of the century. The costs for this
service will include construction, operation, research and
development, regulation, and licensing. They are to be
recovered in full from electric utilities. Recent legislation
has provided for utility payment for all electricity generated
by nuclear facilities after April 7, 1983. The fee .of 1 mill
per KWH (0.1C/KWH), is designed to cover all costs expected to
be incurred by the government. This fee, developed from U.S.
Department of Energy estimates, is consistent with a total
disposal cost of $190 per kilogram
dollars).
However, we estimate the costs
from the Shoreham plant at $350 per kilogram (in
(KgU) of spent fuel (in 1983
for spent fuel disposal
1983 dollars),
- 55 -
E S R G
about 1.8 times the Department of Energy figure. Several
factors enter i~to our estimate. First, the DOE estimate
itself does not account for inflation. Beyond inflation, it
does not account for real escalation from initial engineering
estimates. Indeed, the system of cost collection embodied in
the legislation includes yearly review so that changes in costs
can be reflected in changes in the fee. This is especially
important since the costs of new complex technologies (e.g.,
nuclear power plants themselves) have often ultimately been
many times higher than initial engineering estimates. Other
estimates have put ultimate disposal costs well above the $190
per KgU figure, and as high as $3000 per KgU (see Section 5 of
Technical Report B for a review of the literature). Further
indication of the likelihood that the 1 mill per KWH fee will
prove too low is the fact that at least one utility
(Commonwealth EdiSon) has arranged for disposal funds to be
collected at 2 mills per KWH.
In the analysis of Shoreham required revenues, we assumed
that 1 mill per KWH will be collected initially, but that this
will increase annually until ultimately $350 per KgU (in 1983
dollars) is collected for Shoreham spent fuel. Total funds
collected will be about $283 million (1983 dollars). Thus
payments will escalate from 1 mill per KWH in 1983 to about 27
mills per KWH by 2013, averaging about 8 mills per KWH over the
30-year operating life of the plant. The average in 1983
dollars is about 2.2 mills per KWH.
- 56 -
Decommissioning
Significant costs are associated with all three major
options for nuclear plant decommissioning: entombment,
mothballing, and immediate dismantlement. The immediate
dismantlement method appears, at this time, to be the least
costly approach. It entails cleaning the radioactive
components to the extent that decontamination is practical,
then cutting the radioactive structures into pieces suitable
for transport to a permanent radioactive waste disposal site.
Experience with dismantling nuclear reactors has been
limited to only very small units thus far. Therefore, cost
estimates for large commercial nuclear power plants remain
speculative. With larger units, both economies of scale and
diseconomies associated with much higher levels of radiation
can be expected.
Based upon estimates in the literature, which put the
costs in the $50-500 million (1983 dollars) range, a figure of
$200 million (1983 dollars) has been selected to represent the
decommissioning costs for Shoreham (see discussion in Technical
Report B).
A recent estimate by the Pennsylvania Power and Light
Company for a boiling water reactor was $123 million. By
contrast, LILCO has assumed that decommissioning Shoreham will
cost about $50 million (1983 dollars). In evaluating utility
estimates, it is necessary to consider the likelihood of a real
escalation rate above inflation caused by growing factor input
costs and the increases from initial engineering estimates
which have been typical in the nuclear industry.
- 57 -
E S R G
At the 6 percent inflation rate our $200 million (1983
dollars) decommissioning estimate becomes $1,150 million in
year 2013, the assumed end of Shoreham's operating life.
Revenues were assumed to be collected from ratepayers taking
account of Federal income tax effects and interest credit for
decommissioning funds received. Our computerized simulation
collects funds at a rate beginning at LILCO's assumed initial
rate and increasing over the plant life to achieve full
collection of the $1,150 million estimated decommissioning
cost. The resulting required revenue stream, comprised of
ratepayer contribution to the decommissioning fund (net of
interest accrued on the contribution) and incremental Federal
taxes incurred, is reported in the next section.
Summary of Shoreham Operations and Costs
Table 10 below summarizes the projections of Shoreham
power plant operations and costs in nominal dollars. These
results, properly discounted to common present value dollars,
are included as part of the cost impact analysis of the last
section.
- 58 -
E S R G
the
Year
TABLE 10
SHOREHAM NUCLEAR POWER PLANT OPERATIONS AND COSTS SUMMARY
SHOREHAM OPERATIONS
SHOREHAM COSTS: REQUIRED REVENUES
IMPACTS (Millions of Dollars)
Net Opera-
Capacity Genera- tions & Net De-
Factor tion Mainten- Capital Nuclear Co,mis- Spent
(Percent) (GWH) ance Additions Fuel sionin~ Fuel
1984 48.0 3402 52.0 5.4
1985 51.0 3614 58.0 11.8
1986 54.0 3827 64.6 19.5
1987 57.0 4039 71.8 28.4
1988 60.0 4252 79.6 38.8
1989 63.0 4465 88.1 50.8
1990 63.0 4465 97.3 64.5
1991 63.0 4465 107.3 80.1
1992 63.0 4465 118.2 97.8
1993 63.0 4465 129.9 117.7
1994 63.0 4465 142.7 140.1
1995 63.0 4465 156.5 165.3
1996 63.0 4465 171.5 193.3
1997 63.0 4465 187.7 224.6
1998 63.0 4465 205.3 259.3
1999 63.0 4465 217.6 296.2
2000 63.0 4465 230.6 335.2
2001 63.0 4465 244.5 376.6
2002 63.0 4465 259.1 420.5
2003 63.0 4465 274.7 467.0
2004 63.0 4465 291.2 516.3
2005 63.0 4465 308.6 568.6
2006 63.0 4465 327.1 624.0
2007 63.0 4465 346.8 682.7
2008 63.0 4465 367.6 745.0
2009 63.0 4465 389.6 796.8
2010 63.0 4465 413.0 838.3
2011 63.0 4465 437.8 369.5
2012 63.0 4465 464.6 890.2
2013 63.0 4465 491.9 900.6
23.0
26.3
30.0
34.1
38.6
43.7
47.0
50.7
54.6
58.8
63.3
68.2
73.4
79.0
85.1
91.7
98.7
106.3
114.5
123.3
132.8
143 1
154 1
165 9
178 7
192 4
207 2
223 2
240 4
258.9
1.2 3.8
1.3 4.2
1.4 4.8
1.5 5.4
1.7 6.1
3.3 6.8
3.5 7.7
3.9 8.7
4.2 9.8
4.6 11.0
7.9 12.4
8.6 13.9
9.4 15.7
10.2 17.7
11.2 19.9
18.5 22.5
20.1 25.3
22.0 28.5
24.0 32.1
26.3 36.2
43.6 40.8
47.6 46.0
52.0 51.8
56.9 58.3
62.2 65.7
115.2 74.1
125.7 83.4
137.3 94.0
150.1 105.9
164.2 119.3
- 59 -
£ $ R G
5. COST IMPACTS OF NOT OPERATING SHOREHAM .
A basic aim of this study is to quantify the changes in
the costs to ratepayers resulting from not operating the
Shoreham facility. This was done by considering LILCO's annual
required revenues under various scenarios. Required revenues
consist of the amount utilities need to collect from their
customers to cover operating expenses, taxes, capital
amortization, and return on investment. As an overall measure
of ratepayer expenditures, required revenues are an appropriate
indicator of cost effects.
Cost Components
The required revenues for a given year are composed of many
elements reflecting the operations of the entire electric system
under consideration. However, the ratepayer impact of not
operating Shoreham is the difference of two required revenue
streams: one with the plant operating and the other with it
nonoperational. Consequently, costs common to both cases
cancel out in computing the incremental impacts of a plant
closing, and need not be considered further.
There remain seven significant components of the required
revenues that would be differentially affected by plant
abandonment. These are:
- 60 -
E S R G
Make-up Generation. In the absence of the nuclear plant,
the electricity generation requirements must be provided by the
existing system, by purchased power, by new plant construction,
or by conservation. The costs of these make-up power
alternatives constitute the major penalty of early power plant
retirement. To analyze them, it is necessary to specify the
system responses to the loss of the facility (discussed in
Section 3). Projections of nuclear plant generation (capacity
factors) to determine how much generation must be replaced are
an important ingredient in this analysis (discussed in Section
4).
Direct Capital Related Costs. These include recovery of the
sunk capital, return on investment, taxes and insurance. The
amount and method of recovery is to some extent a regulatory
policy issue. In this investigation, capital related costs
have been computed using a financial model to simulate LILCO
characteristics and practices.
In the Shorehem-In case, it is assumed that the full
investment is recovered with interest. In the Shorehem-Out
case, a range of cost recovery scenarios were evaluated. For
example, in the benchmark "Rate Wash" Shoreham-Out case, the
recovery was reduced by an amount sufficient to make the
present value of revenue requirements the same as in the
Shorehem-In case.
Nuclear Fuel.
running the plant.
dependent on assumptions on
This is an avoided cost (i.e., a benefit) of not
As with make-up generation, its value is
likely future plant capacity factors.
- 61 -
E S R G
Nuclear Operations and Maintenance. This is another avoided
cost. As discussed in Section 4, there is statistical evidence for
projecting escalating nuclear O&M costs related in part to aging-
related equipment problems.
Radioactive Waste Storage and Disposal. In the case where the
plant operates, it is necessary to store and to finally dispose of
highly radioactive spent fuel.
Decommissioning. If the plant operates, expenses will be
incurred in dismantling or encapsulating the radioactive facility
after its useful life has ended.
Capital Additions.
and safety modifications
operated. In Section 4,
Certain costs for major plant repairs
are avoided if the plant is not
statistical estimates of these costs
were developed based on actual experience with nuclear
facilities. These costs are significant and have not been
properly considered in Shoreham cost evaluations to date.
Cost Accounting System
The complexity of these issues -- as well as the desire to have
a flexible capability for developing scenarios, performing
sensitivity analyses, and synthesizing results -- warranted the
development of a computer-based costing model. The result, the Rate
Impact of Shoreham Not Operating (RISNO) System, is designed to
simulate the required revenue impacts in both current and discounted
dollars and over variable time periods. It provides a flexible
framework for testing the effects for various scenarios and parameter
ranges so that uncertainty in both technology variables (e.g., future
plant performances) and policy or economic variables (e.g.~
- 62 -
E S R G
conservation activity) may be adequately explored. In addition, as
described earlier, several ancillary models were used in developing
'inputs on make-up generation, capacity factors, O&M costs, and
capital additions.
Time Period of the Analysis
The focus here will be on the first twenty years of
Shoreham's operations, 1984-2003. In the next section, the effects
of extending the study time period by ten years (the assumed plant
lifetime) will be analyzed. Projections past twenty years must be
considered highly speculative. Beyond the inherent uncertainties in
such a long range prognosis, there is the problem that commercial
nuclear facilities are all twenty years old or younger. There is
thus very little concrete experience on which to base estimates of
nuclear plant performance and cost consequences out to the third
decade of power production. Sensitivity projections over both
thirty years and ten years indicate cost penalties for the
Shoreham-In scenario (see Sections 1 and 8), but twenty years
is suggested as a more reliable period for estimation and
policy deliberations.
Results
The cost streams of the Shoreham-In and Shoreham-Out cases
are shown in present value terms in Table 11. The assumptions
- 63 -
E S R G
TABLE 11
REVENUE REQUIREMENTS COMPARISON: RATE WASH CASE
(Millions of Dollars Present Valued to 1983)
1986 632.6 43.1 46,2 4.8 3.4 1.1 20.4 751.6
1985 534.5 42.2 45.7 9.3 3.3 1.0 20.7 636.7
1986 447.8 41.5 45.2 13.6 3.6 1.0 21.0 573.5
1987 376.2 40.8 44.6 17.6 3.4 0.9 21.2 504.7
1988 316.1 40,1 43.9 21.4 3.4 0.9 21.3 467.1
1989 264.7 39.2 43.1 24.9 3.3 1.6 21.4 ' 398.2
1990 221.2 :38.3 42.3 28.0 3.3 1.9 20.4 355.0
1991 184.6 37.4 41.4 30.9 3.4 1.3 19.6 318.8
1992 153.4 36.5 60.5 33.5 3.4 1.4 18.7 287.4
1993 126.9 34.3 39.5 35.8 3.3 1.4 17.9 259.1
1994 106,7 32.3 38.5 37,8 3.3 2.1 17.1 237.8
1995 91.5 30.4 37.5 39.6 3.3 2.1 16.3 220.7
1996 78.3 28.6 36.5 41.1 3.3 2.0 15.6 205.4
1997 67.0 26,9 35.5 42.4 3.3 1.9 16.9 191.9
1998 57.2 25.3 34.4 43.5 3.3 1.9 14.3 179.9
1999 48.8 23.8 32.4 44.1 3.4 2.8 13.7 169.0
2000 61.5 22.4 30.5 44.3 3.3 2.7 13.0 157.7
2001 35.3 21.1 28.7 44.2 3.3 2.6 12.5 147.7
2002 29.9 19,9 27.0 63.8 3.3 2.5 11.9 138.3
2003 25.3 18.7 25.4 43.2 3.3 2.4 11.4 129.7
TOTALS 3839.5 642.8 758.8 643.8 66.7 35.3 343.3 6330.2
*Excludes
revenues
570.0 0 157.0 727.0
480.4 0 157.2 637.6
601.0 0 156.7 557.7
335.8 0 155.8 491.6 .
281.1 0 156.2 437.3
234.6 0 157.3 391.9
199.3 0 150.9 346.2
162.3 0 138.6 300.9
13~.2 0 132.9 267.1
110.4 0 127.5 237.9
92.5 0 122.3 214.8
79.3 0 117.3 196.6
'68.0 0 112.5 180.5
58.1 0 107.9 166.0
49.6 12.6 154.8 217.0
'41:9 11,9 140.1 193.9
36.0 22.4 173.9 232.3
30~6 21,1 151.3 203.0
25.9 19.9 132.9 178.7
21.9 18.2 113.7 156.3
3608.9 106.6 2818.8 6334.3
revenues required whether or not Shorehamoperates ( e.g., $1,052.4
are required in both the "In" and "Out" scenarios in 1984.)
million additional
and inputs have been discussed in previous sections.* The
total required.revenues, which include all production,
operating and capital-related costs, reflect the assumptions on
demand forecast, fuel prices, and Shoreham costs developed in
this analysis. If Shoreham operates, cumulative costs of $6.3
billion are incurred This total is composed of carrying
charges on the full Shoreham investment ($3.8 billion),
property taxes ($0.6 billion), Shoreham operations and
maintenance ($0.8 billion), net capital additions ($0.6
billion), spent fuel disposal ($.07 billion), decommissioning
($.04 billion), and nuclear fuel costs ($0.3 billion).
Under abandonment~ the total cost is also $6.3 billion,
here composed of makeup power ($2.8 billion, including fuel,
operations and maintenance, and the cost of coal plants),
property taxes on the new coal plants ($0.1 billion), and
carrying charges on the 91.5 percent of the Shoreham investment
which is charged to LILCO customers ($3.4 billion).
For ease of comparison, we have extracted from Table 11 the
total required revenue streams of the Shoreham-In and Shoreham-
Out cases (see also Figure 2). These are shown in Table 12.
While the required revenues vary between cases in individual
years, the total over twenty years is essentially the same in
both cases.
*The discount rate in computing the present value of future costs
is taken at 12.64 percent to reflect LILCO's assumed cost of
capital, again a conventional procedure. The underlying annual
inflation rate assumed is 6 percent. Shoreham property taxes
are taken from Company estimates (Direct Testimony of A. Madsen,
PSC Case No. 28252, Ex. 1, p. 13). Property taxes for the two
400 MW coal plants (in-service 1998 and 2000) are assumed to be
roughly comparable.
all items.
A four percent revenue tax is applied to
- 65 -
TABLE 12
SUMMARY REVENUE REgUIREMENTS COMPARISON: RATE WASH CASE
(1983 Present Value in Millions of Dollars)
Total Total
Year Shoreham-In* Shoreham-Out*
1984 751.6 727.0
1985 656.7 637.6
1986 573.5 557.7
1987 504.7 491.6
1988 447.1 437.3
1989 398.2 391.9
1990 355.0 346.2
1991 318.8 300.9
1992 287.4 267.1
1993 259.1 237.9
1994 237.8 214.8
1995 220..7 196.7
1996 205.4 180.5
1997 191.9 166.0
1998 179.9 217.0
1999 169.0 193.9
2000 157.7 232.3
2001 147.7 203.0
2002 138.3 178.7
2003 129.7 156.3
Total 6,330.2 6,334.3
*Excludes revenues required whether or not Shoreham operates.
- 66
E S R G
6. THE POTENTIAL ROLE OF CONSERVATION
An acceleration of the rate of customer adoption of energy
conservation measures can contribute to an overall strategy for
abandoning the Shoreham generating station. There are two ways
in which additional conservation can help. First, it will reduce
the growth in demand for power, and can thus make it easier,
technically and economically, for Long Island Lighting Company to
meet its customers' demands for electricity. Second, it can
contribute to reducing the electricity b%lls of households and
businesses by reducing the amount of electricity purchased to
meet the service requirements of customers.
In response to increasing prices and increasing awareness,
the efficiency with which electricity is used has increased over
the past decade. But opportunities for cost-effective conserva-
tion are far from exhausted. The policy problem is how to
encourage the move to a second wave of cost-effective
conservation. Here, LILCO itself can play a productive role.
Through a combination of information, incentives, and practical
assistance, the utility can effectively accelerate the rate of
customer energy conservation.
In addition, governmental agencies, including Suffolk
County, can develop information, regulations, and incentives to
further spur business and household conservation. The County can
also accelerate its program of minimizing fuel and energy costs
- 67
E S R G
in its own buildings, as for example by entering into contracts
with the new "shared savings" companies that install conservation
measures at no cost in return for a share of the energy bill
savings.
For the current study, a specific strategy for accelerated
conservation promotion by LILCO has been developed. This is
consistent not only with the local need to minimize any economic
penalties of Shoreham cancellation, but also with an ongoing
Docket (Case No. 28223) convened by the New York State Public
Service Commission to inquire into ways in which utilities can
bring economic benefits to ratepayers through appropriately
designed conservation incentives. An accelerated LILCO
conservation program can be one component of a set of
conservation promotion actions undertaken privately and by public
agencies in the region.
The goal is to design a practical, economical program by
which LILCO can bring about the benefits of a reduction in the
amount of revenues it would otherwise collect from its customers
through attainment of a target level of additional conservation.*
Because certain utilities in the Northeast and elsewhere have
experimented with accelerated customer conservation and peak-
period demand reduction programs, it has been possible, in
developing this program design,
elsewhere and apply it to Long
circumstances.
to draw upon practical experience
Island in ways that reflect local
*Documented in Technical Report C.
- 68 -
E S R G
A number of specific LILCO program elements have been
included in the Conservation Investment Option which would
contribute to saving electricity at a fraction of the cost of
providing it. These included a significantly stepped-up program
of information and public education for households and business
enterprises in the region; cash incentives to encourage customers
to acquire the most efficient types of lighting, cooling,
refrigeration, and other electrical equipment available on the
market; a program to install low-cost weatherization and
conservation measures directly in the residential dwellin~ stock
in the area; and promotion of controlled, off-peak water heating.
In addition to this conservation program aimed at "the
customer's side of the meter," LILCO can undertake low-cost
engineering steps to reduce the amount of power sent out to the
distribution circuits that serve customers, with no degradation
in effective service to customers. Specifically, efforts to
reduce maximum service voltages (while retaining current minimum
standards) are included.
Initial results indicate that by beginning this program
immediately and continuing it, within a decade LILCO can reduce
overall energy consumption by eight percent, and summer peak
period system demand by six percent. Such a conservation and
"load management" investment program, continued through the year
1999, will reduce the revenues LILCO will need to collect from
customers by $580 million dollars (1983 present value), compared
- 69 -
E S R G
to required revenues without the accelerated conservation
program. Quantitative findings on the cost and planning impacts
of not operating Shoreham and simultaneously achieving such
"deeper" conservation levels are presented in Technical Report C.
Previous ESRG investigations, including a report presented
before The New York Public Service Commission in Case 27774, have
shown that the potential for cost-effective additional customer
energy conservation is greater than that which the program
recommended here for the LILCO area would achieve. However, the
effort here has been to design a specific practical program with
a high likely ratio of benefits to costs and a high level of
administrative feasibility.
It must be remembered that LILCO has a small and narrow
customer conservation effort at the current time, focussed
largely on the state-mandated "Saving Power" home energy audits.
Moreover, LILCO has no plans for significant expansion of efforts
in this direction. In addition, no plans appear to be afoot to
realize the energy conservation benefits of more careful control
of maximum service voltages. Therefore, the several elements
outlined above (and detailed in the technical report on
conservation) constitute a realistic "first generation"
expanded conservation program through which LILCO can play a part
in the effort to bring the economic benefits of improved
efficiency to the region. Policy action, legislative or
regulatory, will probably be necessary for LILCO to assume this
- 70 -
E S R G
role. Experience elsewhere has shown that, once given firm
direction, even utilities that have been reluctant to promote
conservation can develop responsive management plans to effect
the mandated goals.
- 71 -
E S R G
7. SENSITIVITY ANALYSIS
In order to test the sensitivity of the results to
alternative sets of assumptions, a number of cost comparisons
were made based on different assumptions.* The results of these
comparisons are shown earlier in this report in Table 1 and
Figure 1. In performing the sensitivity analysis, individual
assumptions of the Rate Wash case were modified as described
below. In each of these alternative scenarios, all assumptions
except those noted retain their base values from the Rate Wash
case.
Load Forecast
If peak loads grows more quickly than forecast, at 1.6
percent annually rather than 0.8 percent, the revenue
requirements under abandonment are 1.1 percent greater than if
the plant operates. This is equivalent to an increase of $230
million (1983 P.V) over twenty years. The increase occurs
because coal plants will be needed in 1994 and 1996 rather than
1998 and 2000 as in the Rate Wash scenario.
If peak loads do not grow, however, abandonment is less
costly than operations. Under abandonment, rates would decline
by 1.6 percent ($310 million in 1983 P.V.). As in the high
growth case, the revenue impact results from a change in the
on-line dates of new generation plants. With no load growth, new
capacity would not be needed until 2002. No growth in peak loads
*Scenario results are presented in detail in Technical Report D.
- 72 -
E S R G
might occur if demand for electricity is curtailed as a result of
forthcoming rate increases related to recovering the Shoreham
investment, regardless of whether the plant operates. In
developing the base load forecast, "business-as-usual"
projections of important determinants of demand, e.g., industrial
activity, employment, and population, were employed. If large
increases in electric rates reduce growth in these items, demand
growth could also be sharply reduced.
Fuel Price Escalation
In the Rate Wash scenario, oil prices were assumed to
increase at the general inflation rate '(6 percent) until 1987 and
at a 2 percent real (above inflation) rate thereafter. Coal
prices were assumed to grow at a constant 1 percent real rate.
If fuel prices rise more quickly, oil at 3 percent after 1987 and
coal at a constant 2 percent, the abandonment is found to
increase rates by 0.6 percent ($120 million 1983 P.V.). On the
other hand, if there are lower growth rates (oil at 1 percent
real and coal at 0 percent real), electricity costs under
abandonment would decline (0.5 percent or $100 million 1983
P.V.).
New York Power Pool Energy
The assumptions on the availability of pool energy are
described in Section 3. If twice that amount is available, rates
are reduced by 0.2 percent ($50 million 1983 P.V.). Conversely,
if no makeup energy is available from the pool, rates increase by
0.3 percent or $60 million 1983 P.V.
73 -
E S R G
Shoreham Operations and Maintenance Expense
To test the sensitivity of operations and maintenance
expenses, a case was considered in which the real escalation
(after inflation) of these costs was twice as great as predicted
by the model. A second case, with no real growth in these costs,
was considered. The results were symmetric about the Rate Wash
scenario. In the high escalation case, abandonment results in
rates which are 1.1 percent ($290 million 1983 P.V.) lower. In
the low cost case, abandonment raises rates by the same amount.
Future Shoreham Investments
The sensitivity of the results to different future
investment streams was analyzed in a similar manner. When future
capital additions increase at twice the real rate used in the
Rate Wash case, abandonment is found to yield a reduction in
rates of 1.4 percent ($290 million 1983 P.V.). With no real
increase, abandonment results in an increase in revenue
requirements of 1.4 percent, or $290 million.
Shoreham Capital Recovery
The Rate Wash case assumes that under abandonment LILCO will
receive depreciation and return on about 91 percent of its
investment in the Shoreham unit. Of course, the actual level of
recovery is an issue of regulatory policy.* If full recovery is
*The financial computations assume that both depreciation and return
would be reduced uniformly each year. In practice, the PSC would
have to consider two major issues: the amount of the Shoreham
investment to be recovered from LILCO customers and the timing
of that recovery. The decision would presumably be based on an
equitable sharing of the Shoreham investment costs and on
implications for LILCO's financial conditions.
- 74
E S R G
allowed, rates would increase under abandonment by 2.2 percent,
or $430 million 1983 P.V. Conversely, if less than 91 percent is
allowed, abandonment leads to a reduction in required revenues.
The work of another of the County's consultants, Georgetown
Consulting Group, indicates that if LILCO were allowed 55
percent of Shoreham related depreciation and return, it would
maintain reasonable financial health. Fifty-five percent
recovery would lead to rates 9.2 percent lower ($1840 million
1983 P.V.) under abandonment.
Time Period of Analysis
In the analysis, impacts are calculated over the twenty-year
period 1984-2003. When the period under consideration is
increased to thirty years, abandonment is found to reduce rates
by 0.3 percent or $60 million (1983 P.V.). When the period is
shortened to ten years, abandonment also leads to a reduction in
required revenues; in this instance by 1.2 percent, or $120
million 1983 P.V.
What If Shoreham Had Never Been Built?
Finally, a case in which no recovery of Shoreham investment
costs is assigned to rate payers. This is equivalent to asking
the question: ~ow much better off would rate payers be if
Shoreham had never been started? The answer is that rates would
be 17 percent lower on average over twenty years. This is
equivalent to a reduction in revenue requirements of $3400
million in 1983 present value.
- 75 -
E S R G
8. REVIEW OF LILCO'S COST IMPACT ESTIMATES AND "CRITIpUE" ~
The Long Island Lighting Company staff recently developed
its own estimates of the economic consequences of not operating
the Shoreham facility.* LILCO's primary conclusion -- that
electric bills would be some $25 billion higher over the 1984 to
2023 time period -- is in
summarized above that the
worst (see Table 1).
striking contrast to the findings
impacts on ratepayers would be small at
The question naturally arises: why are LILCO's estimates so
much higher than those presented in the current report? The two
reports can be reconciled in several straightforward steps, as
will be demonstrated quantitatively below. The main difference
between the results -- indeed 90 percent of the difference -- is
traceable to differences in method. LILCO's estimates are
inflated ("nominal") dollars over a forty-year period,
imappropriately ignoring the time-value of money. Recasting
their results in common (1983 "present value") dollars reduces
the impact from $25 to $2.8 billion. Focusing on the twenty-year
timeframe advocated in this report reduces LILCO's estimated
impact to $2.3 billion.
The disparity largely vanishes by correcting the Company's
failure to report its results in proper monetary units and its
inclusion of highly speculative effects past the year 2003.** The
*"Shoreham Operation Versus Shoreham Abandonment (An Economic
Analysis)", LILCO Office of Engineering, April, 1983.
**Indeed, it was reported earlier that extrapolating beyond twenty
years had the opposite effect claimed by LILCO. Due primarily
to nuclear aging phenomena and decreasing carrying costs for
substitute power plants, the impact on ratepayers diminishes
in the extended timeframe (see Sections 1 and 7).
- 76 -
E S R G
remaining difference has to do with certain extra costs that
LILCO charges, we believe erroneously, to the Shoreham-Out case
(e.g.~ an unneeded coal conversion, a premature coal plant, extra
capital-related Shoreham costs when the plant does not operate,
the Bokum write-off). Finally, LILCO failed to account properly
for future expenditures that would be incurred to keep Shoreham
operating, particularly downstream capital expenditures on plant
and equipment.
To illustrate, Table 13 presents the reconciliation of
LILCO's estimate to the Rate Wash scenario developed earlier in
this report.* The results are displayed graphically in Figure 9.
The adjustment areas will be discussed in turn.
Methods
As mentioned above, the main reason that the LILCO results
differ from those here is that LILCO chose to report its results
in mixed current dollars. The conventional approach is to
account fOr the time value of money (a dollar in hand is worth
more than a dollar next year, let alone one twenty to forty years
hence) by discounting to common present worth monetary units
(e.g., 1983 present value dollars).
The effects of using inflated nominal dollar estimates of
streams of costs are compounded by the other major differences in
method of analysis. LILCO has employed a forty year timeframe
(1984-2023) as opposed to the twenty years recommended here.
*Other scenarios can be compared using identical procedures.
- 77 -
E S R G
TABLE 13
RECONCILIATION OF LILCO COST IMPACT ESTIMATES WITH RATE WASH SCENARIO
Adjustment
(Billion $)
LILCO'S ORIGINAL ESTIMATE .
1. Methods
· Convert to Present Value
(discount to 1983 dollars)
· Compute Impacts Over 20 Years
2. Shoreham Operations Costs
· Include Capital Additions Projections
· Use Statistical Projections of O&M
3. Make-Up Generation Costs
· Remove Uneconomic Coal Conversion
· Delay Coal Plant In-Service Dates
· Add Back Extra Fuel Costs
4. Recovery of Shoreham Initial Investment
· Remove Extra Costs LILCO Associates
with Shoreham Not Operating
· Reduce Shoreham Fraction in Rate Base
in Rate Wash Scenario
5. Miscellaneous*
RATE WASH SCENARIO
Revised Estimate
of Rate Impacts
(Billion $)
25.0
- 22.2 2.8
- 0.5 2.3
0.3 2.0
0.2 1.8
- 0.7 1.1
- 0.8 0.3
1.0 1.3
0.6 0.7
0.4 0.3
0.3 0.0
*Includes LILCO charge to the Shoreham-Out case of the Bokum
write-off at $97 million.
- 78 -
E S R G
25
20
Cost Impact of
~,andonment
(billions $)15
l0
5
, J~O
F~GURE 9
RECONCILIATION OF LILCO ESTIMATE OF ABANDONMENT COSTS
WITH i'HE RATE WASH CASE
Shoreham Makeup
Methods Operations Generation
Recovery of
Shoreham Rate
Investment Wash
Recast
Present Use
Value 20 Yr. Adjust
Capital Adjust
I .~sis AH~ear
................. Adjusted
Add Back
Remove Additional
Coal COn. Delav Fuel
version Coal= Costs
Estimates
Remove R~du~
Extra Rate-
LILCO payers '
Costs Share
There are strong reasons for basing today's policy decisions on
no more than a twenty-year timeframe as discussed earlier.*
The combined effects of not discounting and extending the
time period for analysis to forty years produce extremely large
contributions to LILCO's estimates (almost $23 billion of the
overall $25 billion estimate). For example, fully $5 billion of
the impact reported by LILCO is in the highly speculative years,
2019-2023. Simple discounting to 1983 dollars reduces this to
about $60 million.
Shoreham Operations Costs
Table 13 shows that of the $2.3 billion variance remaining
after adjusting to consistent methodological approaches, an
additional difference of $0.5 billion between the two analyses is
associated with estimates of Shoreham costs after it comes in-
service. First, the statistically based projections of
operations and maintenance costs are somewhat higher than LILCO's
(about $0.2 billion). As described in Section 5, these projects
are based on an analysis of the actually experienced costs in-
curred at other plants and the significant variables driving those
costs. We know of no sounder basis for long-range projections.
The same can be said for estimates of the continuing
investments once the plant comes in-service which have been
required of all operating nuclear power plants and which will be
required for Shoreham. LILCO appears to be employing in-house
estimates that, relative to the statistical projections, are too
low by about $0.3 billion.
*Analytic results become far to speculative= sensitivity
projections past 2003 showed that the economics of opening
Shoreham actually deteriorate and the lifetime of the
Shoreham plant is uncertain. (Until its April report, LILCO
was assuming 30 not 40 years of operational lifetime.)
E S - 8o -R O
Make-Up Generation Costs
This area as shown in Table 13 accounts for another $0.5
billion of difference between the studies. As indicated in
Section 3 above, the approach taken in the present analysis is to
bring new capacity into service as required to meet reserve
requirement targets. In LILCO's study, however, the Shoreham-Out
case is charged with the cost of converting four existing coal
plants, while admitting that "at present these conversions don't
appear economical," LILCO assumes that they will be undertaken if
Shoreham does not operate, in response to fuel reliability
concerns.* In this analysis, the cost of the unneeded
conversions has not been charged to the abandonment case. Two of
the conversions have, by the way, been included along with
Shoreham in LILCO's plans, up to this point.
Another difference concerns load forecasts. Using its
forecast, LILCO finds it will need new coal capacity in 1994 and
1996. However, with the lower growth forecated here, it is found
that these plants are not needed until 1998 and 2000. On the
other hand, the extra coal units assumed by LILCO have the benefit
of reducing make-up power production costs since coal generation
is substituted for oil generation and power transfers from the
New York Power Pool. These effects are sumarized in Table 13.
*However, LILCO also assumes that new coal plants are built in
1994 and 1996 while the coal conversions are not complete until
1991. In other words, the conversions only allow substitution
of coal for oil in a few years in the early 1990s. As a
sensitivity check, cost impacts were computed, as LILCO would
have it, with four coal conversions in the Shoreham-Out case
and none in the Shoreham-In case. The additional impact on
costs is $170 million, or less than a percent on rates. This
is a fictitious scenario since two of the conversions are
planned with Shoreham operating.
- 81 -
E S R G
Recovery of Shoreham Initial Investment
There are two components here. First of all, LILCO assumes
that paying for the Shoreham plant will cost more if the plant is
abandoned than if it is operated. The Shoreham investment in
this study is, on the other hand, assumed to be identical if it
operates or not. Indeed, it is plausible that the costs would be
less if it does not run insofar as the investments are terminated
prior to the date when the plant otherwise would come in-service.
Secondly, LILCO assumes a ratemaking treatment which not
only has ratepayers paying for 100 percent of the principle and
return on Shoreham, but actually paying more (in present worth
dollars) through rapid depreciation. The Rate Wash scenario
assumes 91 percent recovery in the Shoreham-Out case with
comparable depreciation schedules.*
Miscellaneous Differences in Assumptions
This relatively minor differential (about 0.3 billion)
includes the effects of LILCO assuming that the Bokum Resources
investment (related to an abortive uranium venture) is charged to
ratepayers only if Shoreham does not operate. Whatever the
merits of allowing LILCO to recover its Bokum costs, they are not
the result of abandoning Shoreham and should not be charged to it.
In summary, LILCO's claims concerning the impacts of
Shoreham are greatly overstated. In particular, the abandonment
of Shoreham would not be a catastrophe for the County or for
*Indeed, the Rate W-sh scenario is conservative in that the tax
write-off of the Shoreham investment is not more accelerated in the
abandonment case though the Company would be eligible for such
a treatment. Using a five-year write-off schedule, the fraction
of Shoreham recoverable in the rate base to achieve a "rate wash"
would rise from 91 percent to 96 percent.
- 82 -
LILCO. while the precise cost repercussions depend on variables
which cannot be precisely predicted (especially the regulatory
treatment of the Shoreham investment), over a range of reasonable
scenarios the average rate impacts are plus or minus a few
percentage points.
LILCO's Critique
In June 1983, LILCO released a "critique" of a preliminary
version (May 1983) of the present report.* The Company's comments
were reviewed briefly along with those of other technical experts
in the preparation and revision of this final document. A more de-
tailed treatment of LILC0's critique will be prepared in the future.
The issues raised by LILCO may be segmented into two
categories: (1) a series of numerical adjustments to the Rate
Wash scenario that in essence reinserts the LILCO cost and
planning assumptions described earlier (not surprisingly, the
results ultimately resemble LILCO's cost impact assessment
suitably modified into common "present worth" dollars); and (2) a
number of qualitative complaints offered in passing but not used
in the quantitative adjustments.
The first category -- the substantive issues raised by the
Company -- will be briefly reviewed below where it is
concluded that, in essence, LILCO continues its now decade long
pattern of over-optimism in estimating costs of the Shoreham
project. In the absence of sound independent technical back-up
*Preliminary Critique~ Suffolk County Study of Shoreham Abandon-
ment, prepared by Office of Engineering, Long Island Lighting
Company, June 1983.
- 83 -
E R G
on assumptions and methods, LILCO's case for Shoreham rests on an
appeal to faith in its own in-house engineering estimates --
estimates which have been so dramatically erroneous in the past.
The qualitative side comments which pepper the report are
largely incorrect, obscure or irrelevant.* These will be
addressed in future reports.
What does LILCO~s quantitative critique say? It attempts to
"correct" the Rate Wash scenario from zero average impact on rates
to an impact of about 13 percent on rates ($2.6 billion cumulatively).
The 13 percent adjustment consists of several elements. A significant
portion (6 percent) has to do with Shoreham capital cost recovery in the
event the plant does not open. These LILCO assumptions have been
discussed earlier= return should be 100 percent, amortization should be
accelerated (meaning electric customers pay more when Shoreham
does not operate), and Shoreham will cost more if it is abandoned
than not abandoned due to regulatory delays. This latter point
is illogical~ delays and litigation appear inevitable in all
scenarios. If anything, the costs could be less if further
*For example, the "arithmetic mistake" discovered by LILCO (p.1
ff.) of the "critique" turns out to be that the County used LILCO~s
own assumption on firm interties (Report of Momber Electric
Systems of the NYPP, 1983, Vol. 2, p. 34) while LILCO now wants
to deny any firm capacity from interties (p. 18). The County's
'misunderstanding of complex legal/regulatory matters' (p.1) is
simply that LILCO does not think investors should bear part of
the costs for an abandoned facility~ but such cost-sharing is
in fact the tyDical ratemaking treatment in the U.S. for
abandoned equipment. LILCO claims the County used an "unreal-
istically low~ capacity factor but in fact the values e~ployed
are more favorable than implied by statistical analysis
(Fig. 8 above). Finally, LILCO implies (9.4) that the County's
use of a 20 year timeframe was chosen to bias the results
against Shoreham, but sensitivity analyses for 10 and 30 years
makes the Shoreham option look worse (see, e.g., Fig. 1 above).
- 84 -
£ S R G
Shoreham investments are capped early on and amortization
commences. In the Shoreham-In case there will be a period of
disputation of unknown length that would be required to obtain
approval over the County's objection to the plant operating in
Suffolk County.
Of the remaining 7 percent rate impact LILCO suggests, over
2 percent results from attempting to add to regional revenues
certain "indirect" property tax consequences which have no impact
on electricity costs. These are (the critique itself admits) not
part of required revenue. It is simply erroneous and misleading
to include them, as the purpose of the County's study was to
compute rate impacts. (They were not included in LILCO's own
earlier estimate of required revenue impacts.) In addition to
property tax effects, there are other non-rate impacts of the
Shoreham decision (e.g., property value deterioration, health and
safety risks, employment consequences) which are an ongoing topic
of investigation by the County (to be presented in future
reports).
Thus, of the original 13 percent rate impact in LILCO's
"adjusted" Rate Wash case, 7 percent has been traced to LILCO's
Shoreham capital cost impact treatment which assumes ratepayers
will be substantially penalized if the plant does not operate and
a fictitious property tax adjustment to electric rates. A
further 1 percent consists of a pot pourri of minor miscellaneous
adjustments. The critique presents no documentation on
assumptions, methods and relative impacts of these various
effects. Some of the miscellaneous adjustments are clearly
- 85
E S R
suspect (e.g., charging the Bokum Resources mining venture
to Shoreham-Out, adding capacity charges in a scenario where
adequate reserve margins are maintained, assuming no Power Pool
purchases available for make-up*). Others simply cannot be
evaluated without a better technical description.
Finally, LILCO again asks us to accept its own in-house
engineering judgements as a substitute for the empirically-based,
statistical analysis of power plant performance (especially, O&M,
capacity factors and future capital additions). This will be
difficult for those who have followed LILCO~s track-record in
projecting Shoreham costs -- a decade of revisions with current
estimates 1000 percent greater than original projections. Each
year, LILCO~s optimistic in-house engineering estimates have been
offered, as they are now, as firm planning guidelines.
*Indeed, LILCO~s own production costing runs evaluating make-up
power requirements for Shoreham provided to County consultants
in the ongoing NPhase-in# case before the PSC show availability
of NYPP purchases at levels comparable to those used in this
investigation. At any rate, the scenario with no NYPP purchases
led to only a $60 million penalty (0.3 percent on rates).
- 86
S R G