1) Tree Removal/Grubbing and Haul Road Construction
(approximately 2 weeks)
a. 1 excavator with operator- 1 vehicle
b. 1 feller buncher(tree handling equipment)with operator- 1 vehicle
c. 1 woodchipper with operator- 1 vehicle
d. 1 tub grinder with operator- 1 vehicle
e. 1 payloader with operator- 1 vehicle
f. 1 trailer with driver- 1 vehicle
g. 4 Laborers- 2 vehicles for 4 laborers
o 8 vehicles total
ALL EQUIPMENT EXCEPT FOR TRAILER.STAYS ON,SITE DURING THIS PHASE
2) Excavation Phase 1(5-6 months)
a. 40 trailers with operator
(1 vehicle for operator)
b. 2 loaders with operator-2 vehicles
c. 2 excavators with operator-2 vehicles
d. 1 fuel truck/water truck with operator- 1 vehicle
e. 2 dozers with operator- 1 vehicle
f. 1 Project Manager- 1 vehicle
g. 1 Site Safety Super- 1 vehicle
h. 2 Flagmen- 1 vehicle
i. 4 Laborers- 2 vehicles
o 12 vehicles total
EQUIPMENT IN 8, E,AND E.STAYS ON,SITE DURING THIS PHASE
3) Excavation Phase 2(2-4 weeks)
a. 40 trailers with operator- 1 vehicle
b. 2 loaders with operator-2 vehicles
c. 2 excavators with operator- 2 vehicles
d. 1 fuel truck/water truck with operator- 1 vehicle
e. 2 dozers with operator-2 vehicles
f. 1 Project Manager- 1 vehicle
g. 1 Site Safety Super- 1 vehicle
h. 2 Flagmen- 1 vehicle
i. 4 Laborers- 2 vehicles
o 13 vehicles total
EQUIPMENT IN B, E,AND E,STAYS ON,SITE DUPING THIS PHASE
4) Retaining Wall (3 weeks)
a. 1 excavator with operator
Page 1 of 3
Red Rock Industries,Inc.
PO Box 1037
®� Plainview,NY 11803
RED ROCK (T)516.833.6942
o U ST �
b. 1 loader with operator
c. 1 skid steer with operator
d. 1 mini excavator with operator
e. 4 Laborers
*Note* Wall to be installed while construction of building is in progress
*Vehicles duplicated-see Excavation Phase 1
EQUIPMENT IN A,R, C"AND D STAYS ON SITE DURING THIS PHASE
MATERIAL DELIVERY FOR RETAINING ALL:APPROXIMATELY 60 TRUCKS
5) Excavation Drainage (8 weeks)
a. 1 loader with operator
b. 2 excavators with operator
c. 1 mini excavator with operator
d. 1 skid steer with operator
e. 1 trailer with operator- material delivery precast/pipe, etc.
*Note*Work to be installed while construction of building is in progress
*Vehicles duplicated-see Excavation Phase 2
PQt1IP ENT A,R, C AND D STAYS ON SITE DURING THIS PHASE
6) Construction Phase 3(6 months, inclusive of wall and drainage above)
a. 2 loaders with operator
b. 1 excavator with operator
c. 1 fuel truck with operator
d. 2 skid steers with operator
e. 1 mini with operator
f. 1 dozer with operator
g. 1 telescopic fork lift
h. 1 Project Manager
i. 1 Site Safety Super
j. Scissor&telescopic lifts
*Note* Labor will vary from 20 employees to 60 as job progresses
*Company vehicles are mostly used (4 persons per vehicle)
15-20 vehicles total
EQUIPMENT IN A,R,D,F, P,AND G STAYS CAN SITE DURING THIS PHASE
MATERIAL LIVERY.APPROXIMATELY 12 TRUCKS
CONCRETE FOUNDATION APPROXIMATELY 89 TRUCKS
TOTAL TRUCKS FOR MATERIAL DELIVERY AND FOUNDATIONS:101 TRUCKS
Page 2 of 3
Red Rock Industries,Inc.
PO Box 1037
®� Plainview,NY 11803
RED ROCK (T)516.833.6942
� N o U ST �
NOTES
1) Security booth/gate-duration of project—(5'X5' Kiosk at entrance&exit)
2) Dust control -6' fence with filter fabric around North &west corner
3) Day light savings-hours of operator to be reduced
4) Fall Festival -no weekend construction work—(September 15-October 31)
5) Asphalt binder to be installed on shoulder of road prior at exit to prevent damage from tag axles
6) Sweeper required daily for roadway maintenance
7) Signage-truck enter&exiting
8) lob trailer locations
9) Temporary water/electric/bathroom locations
10) Employee parking-enter&exiting
11) lobsite dumpster location
12) First aid/fire extinguisher locations around site
*Staging areas shown on construction plan
*Signage& Booth shown on Haul Road Plan -at entrance&exit
13) Equipment Utilization: 50%OF WORK DAY
14) Overall workweek of M to Saturday 7 am to 7 pm.
- Excavation Phase:Trucking of materials will be M to Friday 7 am to 5 pm- Estimated 40 truck trips per
day(4 trucks/hour). On Saturdays and from 5 pm—7 pm on weekdays,the on-site activity will be mostly
vehicle & machinery maintenance and planning for the following Monday at 7 am start.
-Construction Phase: Mon-Sat 7 am-7 pm. On Saturdays, light duty crews expected with minimal truck
activity expected.