Loading...
HomeMy WebLinkAboutAppendix F - SYC Construction Schedule and Details.pdf Red Rock Industries,Inc. PO Box 1037 ®� Plainview,NY 11803 RED ROCK (T)516.833.6942 o U ST � STRONG'S YACHT CENTER 1) Tree Removal/Grubbing and Haul Road Construction (approximately 2 weeks) a. 1 excavator with operator- 1 vehicle b. 1 feller buncher(tree handling equipment)with operator- 1 vehicle c. 1 woodchipper with operator- 1 vehicle d. 1 tub grinder with operator- 1 vehicle e. 1 payloader with operator- 1 vehicle f. 1 trailer with driver- 1 vehicle g. 4 Laborers- 2 vehicles for 4 laborers o 8 vehicles total ALL EQUIPMENT EXCEPT FOR TRAILER.STAYS ON,SITE DURING THIS PHASE 2) Excavation Phase 1(5-6 months) a. 40 trailers with operator (1 vehicle for operator) b. 2 loaders with operator-2 vehicles c. 2 excavators with operator-2 vehicles d. 1 fuel truck/water truck with operator- 1 vehicle e. 2 dozers with operator- 1 vehicle f. 1 Project Manager- 1 vehicle g. 1 Site Safety Super- 1 vehicle h. 2 Flagmen- 1 vehicle i. 4 Laborers- 2 vehicles o 12 vehicles total EQUIPMENT IN 8, E,AND E.STAYS ON,SITE DURING THIS PHASE 3) Excavation Phase 2(2-4 weeks) a. 40 trailers with operator- 1 vehicle b. 2 loaders with operator-2 vehicles c. 2 excavators with operator- 2 vehicles d. 1 fuel truck/water truck with operator- 1 vehicle e. 2 dozers with operator-2 vehicles f. 1 Project Manager- 1 vehicle g. 1 Site Safety Super- 1 vehicle h. 2 Flagmen- 1 vehicle i. 4 Laborers- 2 vehicles o 13 vehicles total EQUIPMENT IN B, E,AND E,STAYS ON,SITE DUPING THIS PHASE 4) Retaining Wall (3 weeks) a. 1 excavator with operator Page 1 of 3 Red Rock Industries,Inc. PO Box 1037 ®� Plainview,NY 11803 RED ROCK (T)516.833.6942 o U ST � b. 1 loader with operator c. 1 skid steer with operator d. 1 mini excavator with operator e. 4 Laborers *Note* Wall to be installed while construction of building is in progress *Vehicles duplicated-see Excavation Phase 1 EQUIPMENT IN A,R, C"AND D STAYS ON SITE DURING THIS PHASE MATERIAL DELIVERY FOR RETAINING ALL:APPROXIMATELY 60 TRUCKS 5) Excavation Drainage (8 weeks) a. 1 loader with operator b. 2 excavators with operator c. 1 mini excavator with operator d. 1 skid steer with operator e. 1 trailer with operator- material delivery precast/pipe, etc. *Note*Work to be installed while construction of building is in progress *Vehicles duplicated-see Excavation Phase 2 PQt1IP ENT A,R, C AND D STAYS ON SITE DURING THIS PHASE 6) Construction Phase 3(6 months, inclusive of wall and drainage above) a. 2 loaders with operator b. 1 excavator with operator c. 1 fuel truck with operator d. 2 skid steers with operator e. 1 mini with operator f. 1 dozer with operator g. 1 telescopic fork lift h. 1 Project Manager i. 1 Site Safety Super j. Scissor&telescopic lifts *Note* Labor will vary from 20 employees to 60 as job progresses *Company vehicles are mostly used (4 persons per vehicle) 15-20 vehicles total EQUIPMENT IN A,R,D,F, P,AND G STAYS CAN SITE DURING THIS PHASE MATERIAL LIVERY.APPROXIMATELY 12 TRUCKS CONCRETE FOUNDATION APPROXIMATELY 89 TRUCKS TOTAL TRUCKS FOR MATERIAL DELIVERY AND FOUNDATIONS:101 TRUCKS Page 2 of 3 Red Rock Industries,Inc. PO Box 1037 ®� Plainview,NY 11803 RED ROCK (T)516.833.6942 � N o U ST � NOTES 1) Security booth/gate-duration of project—(5'X5' Kiosk at entrance&exit) 2) Dust control -6' fence with filter fabric around North &west corner 3) Day light savings-hours of operator to be reduced 4) Fall Festival -no weekend construction work—(September 15-October 31) 5) Asphalt binder to be installed on shoulder of road prior at exit to prevent damage from tag axles 6) Sweeper required daily for roadway maintenance 7) Signage-truck enter&exiting 8) lob trailer locations 9) Temporary water/electric/bathroom locations 10) Employee parking-enter&exiting 11) lobsite dumpster location 12) First aid/fire extinguisher locations around site *Staging areas shown on construction plan *Signage& Booth shown on Haul Road Plan -at entrance&exit 13) Equipment Utilization: 50%OF WORK DAY 14) Overall workweek of M to Saturday 7 am to 7 pm. - Excavation Phase:Trucking of materials will be M to Friday 7 am to 5 pm- Estimated 40 truck trips per day(4 trucks/hour). On Saturdays and from 5 pm—7 pm on weekdays,the on-site activity will be mostly vehicle & machinery maintenance and planning for the following Monday at 7 am start. -Construction Phase: Mon-Sat 7 am-7 pm. On Saturdays, light duty crews expected with minimal truck activity expected. Page 3 of 3