Loading...
HomeMy WebLinkAboutAcoustic Report Red-lined ACOUSTIC REPORT Survey of Existing Acoustic Conditions and Expected Acoustic Impacts at: Strong’s Yacht Center – 5780 West Mill Road – Mattituck, NY Prepared for: Mr. Jeffrey Strong Strong’s Yacht Center Engineers: Sean Harkin Margot Criscitiello Sarah Babione Dr. Bonnie Schnitta December 1, 2022 TABLE OF CONTENTS: Section 3.6.1 – Executive Summary 3 Section 3.6.2 – Equipment Utilized 4 Section 3.6.3 – Acoustic Criteria and Definitions 4 Acoustic Criteria 4 Definitions 56 Section 3.6.4 – Analysis of Existing Conditions 78 Ambient Noise Monitoring Results at Project Site 78 Twenty Minute Ambient Reading Results Around Project Site 9 Existing Conditions for Evaluation with Traffic 1011 Section 3.6.5 – Methodology for Analyses 1418 Development of SoundPlan 3D Model 1418 Development of Traffic Noise Model 1519 In-Situ Data Collected for Dump Trucks 1620 Development of Construction Noise Model 1721 Development of Build Condition Noise Model 2125 Section 3.6.6 – Potential Impacts Analysis 2125 Construction Noise Impacts 2125 Build Condition Impacts 4448 Section 3.6.7 – Proposed Mitigation 4953 Section 3.6.8 – Review of Alternate SiteTruck Routing Plan 5054 Construction Noise Impacts 5054 Section 3.6.9 – Review of Alternate Site Plan 61 Construction Noise Impacts 61 Build Condition Impacts 5970 Section 3.6.910 – Reference Data Used for Analyses 6374 Section 3.6.1011 – Existing Traffic Distributions Used for Analyses 75 Section 3.6.12 – Daily Summary Graphs from Noise Monitoring 6479 3.6.1 EXECUTIVE SUMMARY: This document serves to summarize the evaluation of the existing acoustic conditions at Strong’s Yacht Center located at 5780 West Mill Road in Mattituck, NY (“Project Site”), as well as the analysis of the expected acoustic impacts to be incorporated into the SEQRA review of the potential environmental impacts of the proposed development of the Project Site inclusive of the as-of-right development of the property. This acoustic report has incorporated all items requested by the Town of Southold Planning Board during the DEIS scoping meetings and as issued in the Final Scope on April 5th, 2021. SoundSense collected existing sound level readings at the Project Site through noise monitoring performed from April 14th, 2021, through May 3rd, 2021, and May 13th through May 23rd, 2021, as well as the 20-minute readings collected in nearby areas around the Project Site on April 20th, 2021. These existing sound levels serve as the background sound levels for the area to be incorporated into all noise predictions completed for the project. The measured sound levels were used in conjunction with the traffic study provided by Dunn Engineering Services (“Traffic Study”), to assess any increases in traffic noise both during construction and after development of the project (“Build Condition”), as well as the equipment types and utilization factors provided by Red Rock Industries to develop a construction noise model. Any potential increases in sound levels at the receiving locations evaluated due to increased vehicle/truck passbys, construction activities, and final sound levels with the new development have been considered for the Project Site. Calculations were completed using SoundPLAN Version 8.2 (“SoundPLAN”) acoustic modelling software. Traffic calculations were completed using the Federal Highway Administration’s TNM 2.5 noise model inside SoundPLAN, and construction noise sources used standardized acoustic data available from the Federal Transportation Authority’s Transit Noise and Vibration Impact Assessment Manual published in 2018 (“FTA Guidelines”). A more detailed description of the methodologies used for the project can be found below in Section 3.6.5. Using the computer-generated model, an existing noise model for traffic was also developed for existing peak traffic generation. Along with the background sound levels collected, these baseline noise levels serve as the existing condition sound levels including the existing ambient and traffic levels (“Existing Condition”)”), to which the Build Condition predicted sound levels can be compared. This comparison allows for evaluation against the New York State Department of Environmental Conservation’s definitions regarding noise impact as well as the Town of Southold’s Noise Ordinance in Chapter 180 of the Town Code (“Noise Code”). While construction noise levels are predicted to have an impact at the nearby Residences, the Town of Southold specifically exempts construction noise from the requirements in the Noise Code. Nearby residences are predicted to be impacted by the construction for its duration, however impact from construction is common for any construction project to occur, whether it be commercial or residential, which is why it is commonly exempted from municipal noise codes. Traffic increases during construction and in the Build Condition, are not predicted to impact nearby residents through evaluation using TNM calculations. Furthermore, the Build Condition is not expected to increase existing sound levels by more than 4 dBA, which would constitute “No Impact” under the NYSDEC criteria. In addition to the proposed plan,construction and development (“Proposed Plan”), an as of right development plan (“Alternate Site Plan”), was modeled based on the revised location and size of the development. Analysis showed sound levels are predicted to increase significantly during construction and that in the Build Condition there is no significant difference acoustically between the two plans. 3.6.1 EXECUTIVE SUMMARY (Continued): A proposed alternate truck route plan was also reviewed which diverts some of the trucks used during the excavation phases down Bergen Avenue on the return trip from the Project Site. Analysis showed that this reduced the impact of increased traffic noise levels at receivers along Cox Neck Road south of the intersection of Cox Neck Road and Bergen Avenue and was below NYSDOT recommendations at all receptors considered along Bergen Avenue and along Cox Neck Road south of the intersection of Cox Neck Road and Bergen Avenue. SECTION 3.6.2 -– EQUIPMENT: Frequency Analyzer: Bruel & Kjaer Model 2250L, Serial No. 3009718 Type 1 Microphone: Bruel & Kjaer Model 4952, Serial No. 3080415 Sound Calibrator: Bruel & Kjaer Model 4231, Serial No. 3017454 Frequency Analyzer: Bruel & Kjaer Model 2250, Serial No. 2739677 Type 1 Microphone: Bruel & Kjaer Model 4190, Serial No. 2731530 Sound Calibrator: Bruel & Kjaer Model 4231, Serial No. 2730164 NOTE: The microphones are Type 1 per ASTM Standards and was calibrated before and after the readings. SECTION 3.6.3 – ACOUSTIC CRITERIA AND DEFINITIONS: Acoustic Criteria Town of Southold Noise Ordinance – Chapter 180 § 180-5 General prohibition. No person or persons owning, leasing or controlling the operation of any source of noise on any lot or structure within the Town shall permit the establishment of a condition of noise pollution. Except as provided in §180-6, the use of amplifiers, speakers or other machines or devices capable of reproducing amplified or airborne sound from the premises, dwelling or building within the Town shall be considered noise pollution and shall be prohibited at all times. § 180-6 Standards. No person shall create or cause to be emitted any noise pollution which when measured on a sound-level meter from the property line of a complaining property owner exceeds the following standards: Sunday through Thursday: From 7:00 a.m. to 7:00 p.m., airborne or amplified sound in excess of 65 dB(A); and From 7:00 p.m. to 7:00 a.m., airborne or amplified sound in excess of 50 dB(A). Friday and Saturday: From 7:00 a.m. to 11:00 p.m., airborne or amplified sound in excess of 65 dB(A); and From 11:00 p.m. to 7:00 a.m., airborne or amplified sound in excess of 50 dB(A). § 180-8 Exceptions. The provisions of §180-5 and 180-6 shall not apply to the following: (2) Construction activities between 7:00 a.m. through 7:00 p.m. and the associated use of construction devices or the noise produced thereby, provided that such activities and such equipment and their use comply with the other provisions hereof. (11) Emergency construction or repair work. (14) Emergency stationary and mobile signal devices. SECTION 3.6.3 – ACOUSTIC CRITERIA AND DEFINITIONS (Continued): Acoustic Criteria (Continued) New York State Department of Environmental Conservation, “Assessing and Mitigating Noise Impacts” The NYSDEC provides guidance for environmental noise impacts in its technical report ‘Assessing and Mitigating Noise Impacts released October 6, 2000, and revised February 2, 2001. Table 1 below summarizes the NYSDEC’s guidance provided in Section V, Subsection B, Item c. Table 1: NYSDEC Thresholds for Significant Sound Pressure Level (SPL) Increase Sound Level Increase (dB) Impact Need for Mitigation  0 – 3 No appreciable effect on receptors No need  3 – 6 Potential for adverse noise impact in cases where the most sensitive of receptors are present Mitigation may be needed for some sensitive receptors such as churches and theaters  6 – 10 Potential for adverse noise impact depending on existing SPL and character of surround land use and receptors Mitigation may be needed for most receptors, depending on existing conditions  10 or more Adverse impact Deserves consideration of avoidance and mitigation measures in most cases   New York State Department of Transportation Noise Analysis Procedures and Project Environmental Guidelines The New York State Department of Transportation provides recommended criteria for road noise levels at various receptors in its technical report ‘NYSDOT Environmental Procedures Manual, Chapter 3.1’ released in August of 1998. It should be noted that the report notes that the sound levels outlined in this document are a criterion, and not a standard. It should also be noted that the criteria outlined in the document are guided towards future traffic after project completion. Recommended noise levels from Table 1 in the technical report can be found in Table 2. For the nearest receptors to the roads evaluated for additional traffic for this project, Category B is appropriate for evaluation. SECTION 3.6.3 – ACOUSTIC CRITERIA AND DEFINITIONS (Continued): Acoustic Criteria (Continued) New York State Department of Transportation Noise Analysis Procedures and Project Environmental Guidelines Table 2: Recommended NYSDOT Criteria for Road Noise Levels Activity Category Leq(h) (dBA) L10(h) (dBA) Description of Activity Category  A 57 (Exterior) 60 (Exterior) Lands on which serenity and quiet are of extraordinary significance and serve an important public need and where the preservation of those qualities is essential if the area is to continue to serve its intended purpose  B 67 (Exterior) 70 (Exterior) Picnic areas, recreation areas, playgrounds, active sports areas, parks, residences, motels, hotels, schools, churches, libraries, and hospitals.  C 72 (Exterior) 75 (Exterior) Developed lands, properties, or activities not included in Categories A or B above (e.g., commercial, industrial, other)  D   Undeve loped Lands  E 52 (Interior) 55 (Interior) Residences, motels, hotels, public meeting rooms, schools, churches, libraries, hospitals, auditoriums, offices, etc.   Definitions Ambient In this document ambient refers to the existing sound levels as collected during the noise monitoring performed at the Project Site from April 14th, 2021, through May 3rd, 2021, and May 13th through May 23rd, 2021, as well as the 20-minute readings at areas around the site collected on April 20th, 2021. Decibel (dB) Definition: The term used to identify ten times the common logarithm of the ratio of two like quantities proportional to power or energy. Thus, one decibel corresponds to a power ratio (10 to the 0.1 power) to the n power. Since the decibel expresses the ratio of two like quantities, it has no units. In this document, all decibels are presented using industry standard 20 µPa as the reference quantity. A-Weighting dBA – This weighting metric is commonly applied to sound pressure levels as it is an approximation ofapproximates the hearing response of the human ear which is more responsive to higher frequencies than lower frequencies. SECTION 3.6.3 – ACOUSTIC CRITERIA AND DEFINITIONS (Continued): Definitions (Continued) Equivalent-Continuous Sound Level (Leq) Definition: Equivalent-continuous, frequency-weighted sound pressure level over a specified averaging time is the equivalent steady level, in that time interval, of the time-mean-square, frequency-weighted sound pressure produced by the sources of steady, fluctuating, intermittent, irregular, or impulsive sounds. The equivalent-continuous sound level of a time-varying sound is equal to the level of an equivalent steady sound at a measurement location for the same measurement duration. Specifically, Leq is 10 times the common logarithm of the ratio of the time-mean-square sound pressure 𝑝 2 (𝑡) over time period 𝑇= 𝑇 2 − 𝑇 1 to the square of the standard reference sound pressure. Measured in dB the Leq is: 𝐿 𝑒𝑞 =10⋅ 𝑙𝑜𝑔 10 1 𝑇 2 − 𝑇 1 𝑇 1 𝑇 2 𝑝 2 (𝑡)⋅𝑑𝑡 𝑝 𝑜 2 Standards The information within this findings document is based on the ASTM Standards. Any variation to the ASTM criteria is based on additional research by such groups as the Acoustic Society of America and INCE that focuses on the well-being of humans in the presence of noise. Statistical Sound Levels (L10, L50, L90, etc.) The sound level that is exceeded for the percentage of time of that level during a period of time. Example: During a 1-hour measurement, an L10 of 60 dBA means the sound level was at or above 60 dBA for a total of 6 minutes, whereas an L90 of 60 dBA means the sound level was at or above 60 dBA for a total of 54 minutes. This is often used to demonstrate ambient sound levels. In addition to these sound levels, minimum and maximum sound levels measured are typically provided and denoted as Lmin and Lmax. SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS: Ambient Noise Monitoring Results at the Project Site To establish the existing sound levels over longer periods of time, noise monitoring was performed at two locations at the Project Site. A marked copy of a satellite view indicating these locations can be found in Figure 1. Monitoring at Location 1 occurred from April 14th, 2021, to April 28th, 2021, and at Location 2 from April 28th, 2021, to May 3rd, 2021, and then from May 13th, 2021 until May 23rd, 2021 for a total of four full weeks of data collection. The disruption between May 3rd, 2021, and May 13th, 2021, was due to a disruption in data transmission from the noise monitoring unit. Therefore, additional days were completed after May 13th, to complete the four full weeks of data collection. Figure 1: Noise Monitoring Locations at the Project Site / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Ambient Noise Monitoring Results at the Project Site (Continued) In addition to the collection of data, inclement weather can unnecessarily impact the data collected. To mitigate the impact of inclement weather, the data collected was compared to historical weather data from the nearest weather station at East Hampton Airport, since they maintain historical weather information. Any hour where precipitation was reported was eliminated from calculation of the metrics provided in Table 23, which serve as a summary of the acoustic data collected at each location for the daytime hours between 7 AM and 7 PM. This time range was selected because it is the same time range as the exemption for construction noise in the Noise Code. The median hourly Leq of 44 dBA was selected to use as the background sound level near the Project Site. This was the lowest median sound level collected during the measurements completed as seen in Table 23. This table summarizes the minimum, first quartile (statistic which 25% of the data is lower and 75% of the data is higher), the median (statistic which 50% of the data collected and 50% is higher), the third quartile (statistic which 75% of the data is lower and 25% of the data is higher), and the maximum. The individual graphs which summarize the sound levels by hour for each day of data collection can be found in Section 3.6.1012. Dominant sounds at the Project Site include wildlife, nearby construction, and a couple examples of boat washing. Table 23: Summary of Acoustic Data Collected During Noise Monitoring at the Project Site Metric Measurement Location Leq (dBA) Lmax (dBA) L10 (dBA) L50 (dBA) L90 (dBA) Lmin (dBA)  Minimum Location 1 39.4 57.6 48.5 44.1 40.0 29.6   Location 2 36.3 55.3 38.2 31.6 28.5 24.7  Fir st Quartile Location 1 42.7 65.1 53.2 47.5 44.1 35.7   Location 2 42.0 64.0 43.6 36.2 31.7 28.5  Median Location 1 44.5 67.4 55.6 48.8 46.1 37.8   Location 2 44.0 67.9 45.8 37.8 33.4 30.2  Third Quartile Location 1 46.9 70.7 58.0 51.1 47.9 41.4   Location 2 46.3 72.0 48.4 41.5 36.1 32.3  Maximum Location 1 58.4 85.4 69.3 63.8 63.2 48.0   Location 2 65.3 83.3 70.6 54.9 46.6 42.3   Twenty Minute Ambient Reading Results Around Project Site In addition to the above-described noise monitoring data taken at the Project Site, acoustic readings were collected at four locations near the Project Site and along the route which will be taken by trucks during the excavation phase. Acoustic readings were collected on April 20th, 2021, in the morning between 7:39 AM and 9:21 AM, and in the afternoon from 3:16 PM to 4:59 PM and were collected for a duration of 20 minutes each. Historical weather data from the nearest weather station on Long Island at East Hampton Airport reported winds between 3-8mph from the SSW during the morning readings with minimal cloud cover. The winds during this period can be described as a light or gentle breeze. The afternoon reading period had 16-18mph from the SW with minimal cloud cover. Air pressure was between 29.84-29.88 in. with 0 in. of precipitation. The winds during this period can be classified as a moderate breeze. SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Twenty Minute Ambient Reading Results Around Project Site (Continued) The locations of acoustic readings collected can be found in Figure 2, while the results of the readings can be found in Table 34. Since the sound levels of vehicles passing were louder at the reading locations than they would be at the nearest residences, the L90 values have been used to represent the background sound levels at all receiver locations near each reading location. This was chosen because the acoustic readings were collected on the shoulder of West Mill Road and Cox Neck Road, meaning that vehicle passbys were significantly louder than what would be measured at the nearby residential structures. This provides a true definition of the background sound levels at each location without, or with minimal, vehicle passbys. For each location, the lowest L90 measured was used to represent a quieter background noise level and a worst-case scenario for noise impact. Figure 2: Twenty Minute Ambient Reading Locations Around the Project Site SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Twenty Minute Reading Results Around Project Site (Continued) Table 34: Results of Twenty Minute Ambient Readings Near the Project Site Measurement Location Time Period LAeq (dBA) LASmax (dBA) L10 (dBA) L50 (dBA) L90 (dBA) LASmin (dBA)  Location 1 7:39am – 7:59am 60 79 56 45 41 37   3:16pm – 3:37pm 58 81 53 45 41 37  Location 2 8:06am – 8:26am 61 76 65 52 51 49   3:45pm – 4:05pm 69 92 69 52 46 41  Location 3 8:32am – 8:52pm 68 85 71 64 52 46   4:10pm – 4:30pm 65 84 68 50 44 40  Location 4 9:01am – 9:21am 67 84 69 57 48 39   4:39pm – 4:59pm 69 95 70 64 53 46   Existing Condition Sound Levels While the data provided above provides a baseline for the background sound levels without the existing traffic data. Therefore, it does not provide a baseline for the Existing Condition as it does not provide a baseline considering the existing traffic to establish an Leq. To evaluate the Existing Condition, traffic data collected by Dunn Engineering were used to complete a traffic noise model in SoundPLAN using the FHA’s TNM 2.5 methodology. Incorporating traffic data into the calculation was completed so that the same calculation methodology and noise model is consistent when establishing the Existing Condition and future predictions. Additionally, this model allows for consistency in the baseline data for traffic generation so that all calculations are consistentstandardized for total trip generation. Inputs for the model can be found in Table 4 and are the baseline peak traffic levels for analysis. Additionalexisting trips generated as defined inwere based on data provided by the traffic consultant. The traffic in the analysis varies throughout the Traffic Study were day, as shown by the data. This time varying traffic was used for the analysis. The existing trips used for all prediction analyses (“Trip Generation”) during construction as well as in the Build Condition.the analysis can be found in Section 3.6.11. The results of the baseline noise models can be found graphically in Figures 3-5 and overallfor the peak hour sound levels and Figures 6-8 for 8-hour sound levels. Overall sound pressure levels at each receiving location considered can be found in Table 5 for both peak hour and 8-hour levels. Receiving locations were selected by evaluating locations near the Project Site, as well as various receiving locations along West Mill Road and Cox Neck Road. These Existing Condition sound levels are used to evaluate the impacts of construction activities, traffic increases, and the Build Condition for evaluation. Table 4: Inputs for TNM Model to Evaluate the Existing Condition Sound Levels Vehicle Class Existing Measured Trips  Automobiles 14  Medium Trucks 12  Heavy Trucks 0  Buses 0  Motorcycles 0   SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 3: Peak Hour Existing Conditions at the Project Site / / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 4: Peak Hour Existing Conditions at West Mill Road and Cox Neck Road / SECTION 3.6./4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 5: Peak Hour Existing Conditions at Cox Neck Road / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 5:6: Eight Hour Existing Conditions at the Project Site / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 7: Eight Hour Existing Conditions at West Mill Road and Cox Neck Road / / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Figure 8: Eight Hour Existing Conditions at Cox Neck Road / SECTION 3.6.4 – ANALYSIS OF EXISTING CONDITIONS (Continued): Existing Condition Sound Levels (Continued) Table 5: Existing Conditions at Each Receiving Location Evaluated Receiver Number Location Peak Hour Existing Condition (dBA) Eight Hour Existing Condition (dBA)   Receiver Number Location Peak Hour Existing Condition (dBA) Eight Hour Existing Condition (dBA)  R1 5106 West Mill Road 44 44  R2 800 North Drive 44 44  R3 805 North Drive 4644 44  R4 2010 West Mill Road 4744 44  R5 4105 West Mill Road 5149 50  R6 200 East Mill Road 44 44  R7 750 East Mill Road 44 44  R8 3329 Grand Ave 44 44  R9 3001 West Mill Road 4746 46  R10 1525 West Mill Road 6050 50  R11 1480 West Mill Road 6352 52  R12 1065 West Mill Road 6352 52  R13 155 Breakwater Road 6352 52  R14 2100 Cox Neck Road 6557 57  R15 2695 Cox Neck Road 6655 55  R16 1475 Cox Neck Road 6454 54  R17 1020 Cox Neck Road 6256 56  R18 55 Middle Road 6360 60   SECTION 3.6.5 – METHODOLOGY FOR ANALYSES: Development of SoundPlan 3D Model As discussed previously, calculations were completed using SoundPlan Version 8.2. SoundPlan constructs a 3D model for all areas analyzed by importing ground elevation data through Google Earth. Using the elevation data, SoundPlan constructs a 3D Digital Ground Model (“DGM”) of the terrain. Once the DGM is constructed, building height and location information, and roadway information can be imported using Open Street Map and added to the DGM. In addition, surface composition to calculate factors such as soft ground attenuation, reflections from buildings, and propagation over water are also calculated and assigned to the DGM. Depending on the specific situation analyzed, the DGM is updated to indicate changes in the elevation which would occur through the construction process, such as the excavation and retaining wall construction proposed (“Retaining Wall”). This ensures that the calculations are accurately completed for each phase of the project. An example of the DGM can be found in Figure 69, which shows the 3D model of the Retaining Wall construction phase. It should also be noted that all calculations completed for the project include frequency dependent data for accurate calculation of barrier effects/diffraction, although only overall sound pressure levels are presented at each receiving location to simplify the results and compare the results to the Town of Southold Noise Ordinance and, NYSDEC Criteria and NYSDOT Criteria. SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of SoundPlan 3D Model (Continued) Figure 69: DGM of Retaining Wall Construction Phase / / Development of Traffic Noise Model The traffic analysis is completed using TNM 2.5. The TNM noise model was used for evaluation of any traffic increase resulting from the Build Condition during construction, as well as vehicle traffic down the Haul Road. Additional trips for traffic generation as defined in the traffic study were added to the baseline trips presented in Table 4.Section 3.6.11. Per the traffic study, three main traffic scenarios were considered for the project. These scenarios include Excavation Phases 1 and 2, Retaining Wall and Construction Phase Traffic, and Build Condition Traffic. All additional Trip GenerationAdditional trips generated for workers use the same vehicle mixes for vehicle classes asthe construction phases were used from the existing traffic to remain consistent with memo provided from Red Rock Industries, which noted the existing traffic profile.expected vehicles needed for each phase of construction. Additional trip generation in the Build Condition was provided in the traffic study completed. This additional trip generation data by phase and vehicle class used for the truck route can be found in TableTables 6. and 7 for the various phases of the project. As noted in the construction details provided in the Red Rock Memo, the Haul Road will be used through the Retaining Wall Phase, and then is eliminated from the noise model starting at the Excavation Drainage Phase. Traffic data used to model the Haul Road during a peak hour are the peak traffic trips per hour all going down the Haul Road. SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Traffic Noise Model (Continued) Table 6: Peak Hour Additional Trip Generation Data by Project Phase New Trip Generation by Condition  Vehicle Class Tree Grubbing Excavation PhasesPhase Construction PhasesPhase Build Condition  Automobiles 198 7013 20 18  Medium Trucks 0 0 0 0  Heavy Trucks 80 10 2 0  Buses 0 0 0 0  Motorcycles 0 0 0 0  Total 27 72 18   Table 7: Non-Peak Hour Additional Trip Generation Data by Project Phase Vehicle Class Tree Grubbing Excavation Phase Construction Phase Build Condition  Automobiles 0 0 0 0  Medium Trucks 0 0 0 0  Heavy Trucks 0 10 0 0  Buses 0 0 0 0  Motorcycles 0 0 0 0   In-Situ Data Collected for Dump Trucks In addition to traffic noise generation completed with TNM, in situ data of a Peterbilt 389 2020 edition dump truck with a Paccar MX13 engine was collected. The dump truck was loaded with 39 tons of sand/dirt at the time of the readings, which is equivalent to 28-29 yards of material. This truck is Tier 4 compliant with EPA standards, using the latest technology to reduce environmental emissions. The applicant has mandated that all trucks on the project comply with the Tier 4 criteria. Readings collected during this testing included the truck passing at 35 mph, idle and backup with a white noise backup alarm, and release of the air brake. It should be noted that all contractors will be directed to disengage any Jake Brake system on incoming vehicles once they turn onto Cox Neck Road from County Route 48. These data are used in the analysis to demonstrate and to include sound levels from the backup alarm with engine idle, and air brake release on the construction site. The data collected have been converted into sound power levels and can be found in Table 78. In addition, calculated sound pressure levels 50’ from the source have also been provided as a reference. A more detailed copy of the reference data showing octave band sound power levels can be found in Table 2127 located in Section 3.6.910. Any sound levels provided do not constitute a requirement for equipment used for the project but provide the basis for calculations completed. SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): In-Situ Data Collected for Dump Trucks (Continued) It should also be noted that the FTA Guidelines list a truck at having a sound pressure level of 84 dBA when measured at 50 feet. Table 78 shows that the actual data collected by SoundSense of the dump truck collected would have a sound pressure level at 50 feet ranging from 62-73 dBA depending on the operating condition. This represents a significant reduction compared to the sound level in the FTA guidelines, showing that using the Tier 4 truck would represent a considerable reduction ranging from 11-22 dBA. A 10 dBA reduction in sound level is typically heard as half of the original sound level and would constitute a significant reduction. It must also be noted that these reduced levels could not be used in the TNM calculations, but these reduced levels support that the TNM calculations completed would demonstrate a worst-case scenario for sound level increase due to traffic. SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): In-Situ Data Collected for Dump Trucks (Continued) Table 78: Converted Overall Sound Power and Pressure Levels of Dump Truck Data Collected Description Sound Power Level (dBA) Calculated Sound Pressure Levels at 50’ (dBA)  Engine Idle and White Noise Backup Alarm 93 62  Air Brake Release 89 58  Vehicle Passing at 35 mph 105 73   Development of Construction Noise Model To evaluate the impact of construction noise, a list of equipment used and utilization factors for the equipment throughout the day were requested from Red Rock Industries. No blasting or pile driving is proposed as a portion of the construction. All construction equipment was then cross-referenced with data available from the FTA Guidelines to find standardized sound levels for construction equipment. Where information was not available within the FTA Guidelines, the integrated library within SoundPlan was utilized for equipment sound sources. Since the FTA Guidelines only provide sound data in overall A weighted sound pressure levels and do not provide frequency breakdowns of sound levels, data included for analogous equipment in SoundPlan was adjusted to meet the prescribed sound pressure level at 50’ as noted in the FTA Guidelines. Overall sound power levels for each piece of construction equipment broken down by each phase of construction, their quantities, and utilization factors, can be found in Tables 8-139-14 as provided by Red Rock Industries. A more detailed copy of the reference data noting frequency breakdown can be found in Table 2127 located in Section 3.6.910. Any sound levels provided do not constitute a requirement for equipment used for the project but provide the basis for calculations completed. All predictions compiled for the construction noise analysis include a peak hour analysis with 100% utilization of all equipment to present a worst-case scenario coinciding with peak traffic generation, as well as an 8-hour Leq from 8 AM – 4 PM during the proposed construction hours to present an overall predicted daily average. The only exception to the 100% utilization in the peak hour is for any equipment which has a utilization factor of 10%, where the equipment was included for 48 minutes of that hour, accounting for 10% of an 8-hour day. It should be noted that some of these phases will occur together such as the Retaining Wall Phase to be completed while the Construction Phase is in progress, and the Excavation Drainage Phase while the Construction Phase is in progress. These phases and equipment types, quantities, and utilization factors have been included in the analysis. SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) Sound levels for the Tub Grinder and Woodchipper were developed were developed in conjunction with built-in data within SoundPlan for the Tub Grinder and Woodchipper idling, as well as data provided in a technical report published by the UK Health and Safety Executive titled Noise Emissions and Exposure from Mobile Woodchippers published in 2008. The data provided in the UK Health and Safety Executive report only provides sound levels during wood chipping and is not representative of an hourly average. The highest sound power level identified was 124.5 dBA during wood chipping. To calculate a worst-case, but realistic sound power level over an hour, the 124.5 dBA was energy averaged with sources of 114 dBA for the Tub Grinder and 103 dBA for the Woodchipper based on wood chipping/grinding 50% of the time and idling only 50% of the time. This results in a sound power level of 122 dBA for both sources. Table 89: Construction Equipment Overall Sound Power Levels and Utilization Factors for the Tree Removal/Grubbing Phase Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 1 50% 111 80  Shouting S2 1 50% 74 42  Exc avator S3 1 50% 113 81  Water/Fuel Truck S4 2 50% 115 83  Tub Grinder S7 1 50% 114122 8290  Woodchipper S8 1 50% 103122 7190  Feller Buncher S9 1 50% 114 82  Raised Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   Table 910: Construction Equipment Overall Sound Power Levels and Utilization Factors for Excavation Phase 1 Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 2 50% 111 80  Shouting S2 1 50% 74 42  Excavator S3 2 50% 113 81  Water/Fuel Truck S4 2 50% 115  83  Dozer S6 2 50% 116 85  Raised Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   SECTI ON 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) Table 1011: Construction Equipment Overall Sound Power Levels and Utilization Factors for Excavation Phase 2 Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 2 50% 111 80  Shouting S2 1 50% 74 42  Excavator S3 2 50% 113 81  Water/Fuel Truck S4 2 50% 115 83  Dozer S6 2 50% 116 85  Raised Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   Table 1112: Construction Equipment Overall Sound Power Levels and Utilization Factors for the Retaining Wall Phase Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 3 50% 111 80  Shouting S2 1 50% 74 42  Excavator S3 2 50% 113 81  Water/Fuel Truck S4 2 50% 115  83  Dozer S6 1 50% 116 85  Skid Steer S10 3 50% 108 76  Mini Excavator S11 2 50% 96 64  Telescopic Forklift S12 1 50% 100 68  Scissor Lift S13 1 50% 106 59  Raise d Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Construction Noise Model (Continued) Table 1213: Construction Equipment Overall Sound Power Levels and Utilization Factors for the Excavation Drainage Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 3 50% 111 80  Shouting S2 1 50% 74 42  Excavator S3 3 50% 113 81  Water/Fuel Truck S4 2 50% 115  83  Dozer S6 1 50% 116 85  Skid Steer S10 2 50% 108 76  Mini Excavator S11 2 50% 96 64  Telescopic Forklift S12 1 50% 100 68   Scissor Lift S13 1 50% 106 59  Raised Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   Tab le 1314: Construction Equipment Overall Sound Power Levels and Utilization Factors for Construction Phase Construction Equipment Type Source Label Quantity Utilization Factor Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Loader S1 2 50% 111 80  Shouting S2 1 50% 74 42  Excavator S3 1 50% 113 81  Water/Fuel Truck S4 2 50% 115  83  Dozer S6 1 50% 116 85  Skid Steer S10 2 50% 108 76  Mini Excavator S11 1 50% 96 64  Telescopic Forklift S12 1 50% 100 68  Scissor Lift S13 1 50% 106 59  Raise d Voice S14 1 50% 64 1132  Air Brake Release S16 1 10% 89 3858  Dump Truck Idling with White Noise Backup Alarm S17 1 10% 93 3762   SECTION 3.6.5 – METHODOLOGY FOR ANALYSES (Continued): Development of Build Condition Noise Model Noise impacts from the Build Condition were also considered. Noise sources considered in the Build Condition impact include a boat being washed, one male speaking at a “Loud” vocal effort level as defined by data presented in a technical report by the Environmental Protection Agency in 1977 titled Speech Levels in Various Noise Environments written by Karl S. Pearsons, Ricarda L. Bennett, and Sanford Fidell, two males speaking at a “Raised” vocal effort level, and the average acceleration of one truck, meant to simulate truck acceleration denoting moving boats in and out of storage. For evaluation of the Alternate Site Plan, the same sources were considered, but it should be noted that acceleration will likely need to be greater and occur for a longer period of time to pull one of the boats up the ramp to get to the Alternate Site Plan location at a higher elevation. Overall sound power levels for the sources considered can be found in Table 1415 and additional information including noting frequency breakdown can be found in Table 2127 located in Section 3.6.910. Any sound levels provided do not constitute a requirement for equipment used for the project but provide the basis for calculations completed. Table 1415: Overall Sound Power Levels for Sources Evaluated in the Build Condition Construction Equipment Type Source Label Quantity Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Shouting S2 2 74 42  Truck Acceleration S5 1 115 84  Raised Voice S14 1 64 1132  Boat Washing S15 1 74 3442   SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts Using the methodologies described in Section 3.6.5, construction equipment descriptions, equipment utilizations, sound power levels, and traffic modeling methodologies described above, predictions were compiled for sound levels at each phase of construction. An hourly peak Leq and 8-hour Leq were both calculated for each phase of the construction at the Project Site. These can be found in Figures 7-1810-21 graphically show the results of these calculations at the Project Site. For the additional areas considered at West Mill Road/Cox Neck Road, and Cox Neck Road, the main noise source is traffic. Therefore, figures for these areas presented focus only on the Excavation 2 Phase and the Excavation Drainage Phase, as these were the loudest construction phases for each traffic condition. Figures 19-2622-29 graphically show these results for the 8-hour Leq as well as the peak hour. Sound pressure levels for all evaluation scenarios and receivers can also be found in Tables 1516 and 1617 for the 8-hour and peak hour sound levels. SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 710: Eight Hour Leq Sound Levels from the Tree Removal/Grubbing Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 811: Peak Hour Leq Sound Levels from the Tree Removal/Grubbing Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 912: Eight Hour Leq Sound Levels from Excavation Phase 1 at the Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 1013: Peak Hour Leq Sound Levels from Excavation Phase 1 at the Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 11: Eight Hour Leq Sound Levels from Excavation Phase 2 at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 12: Peak Hour Leq Sound Levels from Excavation Phase 2 at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 13: Eight Hour Leq Sound Levels from the Retaining Wall Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 14: PeakEight Hour Leq Sound Levels from the Retaining WallExcavation Phase 2 at the Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 15: EightPeak Hour Leq Sound Levels from the Excavation Drainage Phase 2 at the Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 16: Eight Hour Leq Sound Levels from the Retaining Wall Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 17: Peak Hour Leq Sound Levels from the Retaining Wall Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 18: Eight Hour Leq Sound Levels from the Excavation Drainage Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 17: Eight Hour Leq Sound Levels from the Construction Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 18: Figure 19: Peak Hour Leq Sound Levels from the Excavation Drainage Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Phase at the Project SiteNoise Impacts (Continued) / Figure 20: Eight Hour Leq Sound Levels from the SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued)Phase at the Project Site / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 19: Eight21: Peak Hour Leq Sound Levels from Excavationthe Construction Phase 2 at West Mill Road and Cox Neck Roadthe Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 22: Eight Hour Leq Sound Levels from Excavation Phase 2 at West Mill Road and Cox Neck Road / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) 20Figure 23: Peak Hour Sound Levels from Excavation Phase 2 at West Mill Road and Cox Neck Road / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2124: Eight Hour Sound Levels from Excavation Phase 2 Phase at Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2225: Peak Hour Sound Levels from Excavation Phase 2 at Cox Neck Road / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2326: Eight Hour Leq Sound Levels from the Excavation Drainage Phase at West Mill Road and Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2427: Peak Hour Sound Levels from the Excavation Drainage Phase at West Mill Road and Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2528: Eight Hour Sound Levels from the Excavation Drainage Phase at Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts (Continued) Figure 2629: Peak Hour Sound Levels from the Excavation Drainage Phase at Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Construction Noise Impacts (Continued) Table 1516: Eight Hour Leq Sound Pressure Levels at All Receivers for Construction Activities and Additional Traffic Receiver Number Location Existing Condition (dBA) Tree Removal/ Grubbing (dBA) Excavation Phase 1 (dBA) Excavation Phase 2 (dBA) Retaining Wall Phase (dBA) Excavation Drainage Phase (dBA) Construction Phase (dBA)  R1 5106 West Mill Road 44 4554 4950 4950 5150 5150 5150  R2 800 North Drive 44 6677 4478 7680 7076 7176 7076  R3 805 North Drive 44 6276 7475 7173 6369 6469 6368  R4 2010 West Mill Road 4544 4967 5758 5960 4957 4957 4857  R5 4105 West Mill Road 50 5165 5759 6061 5157 5157 5157  R6 200 East Mill Road 4544 4864 55 6061 5060 5060 4960  R7 750 East Mill Road 4544 4963 5859 6061 5459 5459 5459  R8 3329 Grand Ave 44 5367 6365 6769 5968 5968 5868  R9 3001 West Mill Road 4746 4860 5457 5558 4852 4852 4852  R10 1525 West Mill Road 6150 6158 6168 6168 6162 6162 6162  R11 1480 West Mill Road 6352 6356 6371 6371 6364 6364 6364  R12 1065 West Mill Road 6352 6358 6471 6471 64 64 64  R13 155 Breakwater Road 6352 6355 6371 6371 6364 6364 6364  R14 2100 Cox Neck Road 6657 6655 6667 6667 66 66 66  R 15 2695 Cox Neck Road 6655 6655 66 66 6665 6665 6665  R16 1475 Cox Neck Road 6454 6455 6465 6465 6462 6462 6462  R17 1020 Cox Neck Road 6256 6259 62 62 6261 6261 6261  R 18 55 Middle Road 6660 6663 6663 6663 6662 6662 6662   SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Construction Noise Impacts (Continued) SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Construction Noise Impacts (Continued) Table 1617: Peak Hour Leq Sound Pressure Levels at All Receivers for Construction Activities and Additional Traffic Receiver Number Location Existing Condition (dBA) Tree Removal/ Grubbing (dBA) Excavation Phase 1 (dBA) Excavation Phase 2 (dBA) Retaining Wall Phase (dBA) Excavation Drainage Phase (dBA) Construction Phase (dBA)  R1 5106 West Mill Road 44 4758 57 57 5957 59 57 57  R2 800 North Drive 44 7274 8657 8789 8084 8084 7984  R3 805 North Drive 44 6972 8454 82 7377 7377 7377  R4 2010 West Mill Road 44 5463 6766 69 5565 5565 5565   R5 4105 West Mill Road 5049 5461 6766 69 5465 5465 5465  R6 200 East Mill Road 44 5260 6563 7069 5768 5768 5768  R7 750 East Mill Road 44 5459 68 7069 6367 6367 6267  R8 3329 Grand Ave 44 5964 74 78 6777 6777 6777  R9 3001 West Mill Road 4746 5157 6463 64 5058 5058 5058  R10 1525 West Mill Road 6050 6056 6169 6269 6064 6064 6064  R11 14 80 West Mill Road 6352 6355 6372 6372 6366 6366 6366  R12 1065 West Mill Road 6352 6356 6472 6472 6366 6366 6366  R13 155 Breakwater Road 6352 6354 6372 6372 6366 6366 6366  R14 2100 Cox Neck Road 6557 6555 6668 6668 6668 6668 6668  R15 2695 Cox Neck Road 6655 6656 6665 6665 6668 6668 6668   R16 1475 Cox Neck Road 6454 6455 64 64 6462 6462 6462  R17 1020 Cox Neck Road 6256 6259 62 62 62 62 62  R18 55 Middle Road 6360 63 63 63 6362 6362 6362   SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Construction Noise Impacts (Continued) SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Construction Noise Impacts (Continued) While receivers near the Project Site are impacted by the construction noise, noise impacts due to construction are specifically exempt from the Noise Code. As can be seen from the figures and Tables 1516 and 1617, there is a significant increase at receivers R1-R16 for at least one phase of construction for either the peak hour or 8-hour Leq. For Receivers R1-R9.R8, the increases are predominantly due to sound created at the Project Site from construction activities. These increases would have a significant and adverse impact as defined by the NYSDEC criteria to the nearby residences during the period of construction and particularly, with the highest levels during excavation, butExcavation Phase 2. However, this noise would be limited to during daytime hours, and would be temporary, since these increases are only during construction. It should alsoFor receivers R9-R18, any increase in the sound levels would be dependent on additional traffic, which is highest during the excavation phases. Sound levels are higher than recommended by the NYSDOT at receivers R10-R14 during the excavation phases, and during all construction at receivers R14 and R15. However, as noted that thein Section 3.6.3, the NYSDOT criteria are not standards, and these increases are temporary only during construction. All results presented are exterior sound levels. This impact is reduced to the interior of a nearby residence. As presented in the NYSDOT Environmental Procedures Manual, Chapter 3.1 published in August 1998, it is expected that a light frame building type with ordinary sash windows is expected to reduce sound levels by 20 dB. Should a storm window be used, this reduction is expected to increase to 25 dB. This 20-25 dB decrease in sound levels is expected to reduce the impact to the interior of residences and would minimize impact to quality of life while indoors. During the late fall/winter/early spring it is expected that most nearby residencesresidents will be primarily indoors during construction at those times, reducing the impact on quality of life. Once the ground has been excavated, the impact is significantly reduced, except for R2 and R3 since the excavated area acts like an acoustic barrier. Due to the elevation and line of sight for R2 and R3, this benefit is not receivedIf the reduction of 20 dB is applied to the traffic data for receivers R10-R14, which exceed the outdoor recommendations from the NYSDOT, the interior recommendations in Category E of Table 2 for interior noise levels are met and would be within the NYSDOT recommended criteria for those receivers. Build Condition Impacts While construction noise would be temporary, build conditionBuild Condition impacts are typically most critical under SEQRA review. The proposed project will be a storage facility. While the buildings will be largely inactive for a significant amount of the year, there will be times when boats are loaded into and out of the building. Due to the grading which will occur at the site, the retaining walls act as a sound barrier, largely containing the noise within the graded area. Figures 27-2930-32 show the graphic presentation of the peak sound levels predicted at the Project Site using the noise sources presented previously in Table 1415, as well as peak future traffic generation along Cox Neck Road and West Mill Road. Table 1718 presents the overall sound pressure levels at each location. SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Build Condition Impacts (Continued) Table 1718: Sound Pressure Levels at All Receivers in the Build Condition Receiver Number Location Existing Condition (dBA) Build Condition (dBA)  R1 5106 West Mill Road 44 44  R2 800 North Drive 44 48  R3 805 North Drive 44 4544  R4 2010 West Mill Road 44 44  R5 4105 West Mill Road 5049 50  R6 200 East Mill Road 44 4544  R7 750 East Mill Road 44 44  R8 3329 Grand Ave 44 4544  R9 3001 West Mill Road 4746 4746  R10 1525 West Mill Road 6050 6050  R11 1480 West Mill Road 6352 6352  R12 1065 West Mill Road 6352 6352   R13 155 Breakwater Road 6352 6352  R14 2100 Cox Neck Road 6557 6557  R15 2695 Cox Neck Road 6655 6655  R16 1475 Cox Neck Road 6454 6454  R17 1020 Cox Neck Road 6256 6256  R18 55 Middle Road 6360 6360   SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Build Condition (Continued) Figure 27:30: Peak Sound Levels in the Build Condition at the Project Site / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Build Condition (Continued) Figure 2831: Peak Sound Levels in the Build Condition at West Mill Road and Cox Neck Road / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS (Continued): Build Condition (Continued) Figure 2932: Peak Hour Sound Levels in the Build Condition at Cox Neck Road / / As seen above, no receiving locations exceed 6 dBA above the Existing Condition sound levels. This is categorized as no impact as classified by the NYSDEC evaluation criteria categorizes this as no impact and would not be expected to impact quality of life for any nearby residence. The greatest predicted increase would be 4 dBA at the Residence at Receiver R2. Furthermore, sound levels predicted also meet the conditions of the Noise Code at all receiving locations. The results of the analysis show that in the Build Condition that mitigation measures would not be required. SECTION 3.6.7 – PROPOSED MITIGATION: As discussed previously, based on the results, there is no mitigation needed for the Build Condition scenario based on the results of the analysis. For the construction phases, a few mitigation measures have been integrated into the requirements for any contractor for the project. These requirements include the following measures: Construction activities would be limited to Monday to Saturday from 7:00 AM to 7:00 PM in accordance with the Noise Code. No work would be completed on Federal or State holidays, or on Sundays. In accordance with the Noise Code. Excavation phases would be limited from Monday to Friday from 7:00 AM to 5:00 PM. No work would be completed on Federal or State holidays, or on Sundays. During construction phases, work on Saturdays and after 5:00 PM Monday to Friday will only include vehicle and machinery maintenance and planning. No work would be completed on Federal or State holidays, or on Sundays. Any vehicle which requires the use of a back-up alarm will use a white noise back-up alarm instead of a single tone beep. All trucks and drivers will be instructed to disengage all Jake Brake mechanisms once turning on to Cox Neck Rod from County Route 48. All dump trucks utilized will be Tier 4 certified by EPA standards. These mitigation measures are critical to minimizing impact to nearby neighbors during the construction phases. It is well documented that tonal sounds are significantly more disturbing than sounds with a more distributed sound spectrum across all frequencies. While both the beeping backup alarm and tonal beep alarm are both OSHA compliant and have similar overall sound levels, the white noise alarm distributes the sound level over a wider range of frequencies so that the sound is less disturbing to nearby residents. Like the backup alarm, the Jake Brake mechanism on trucks causes a significant high frequency disturbance while trucks are moving through residential areas. In communication with Benimax Trucking, the company used to coordinate the in-situ readings of the Tier 4 dump trucks, it is understood that it is standard practice to disengage all Jake Brake mechanisms when driving through residential areas and is a requirement on nearly every project which the company takes on. Finally, while there is no standardized data available for sound levels on Tier 4 truck sound levels, the field testing and calculations in Section 3.6.5 show that a significant reduction in sound levels is predicted compared to standardized data from the FTA Guidelines. SECTION 3.6.78 – REVIEW OF ALTERNATE TRUCK ROUTE: An alternate truck route has been proposed as mitigation of truck traffic. The alternate plan involves trucks during the excavation phases using Cox Neck Road to travel to the site, and then using Bergen Avenue access Sound Avenue when leaving the site. This alternate plan reduces the amount of truck traffic on Cox Neck Road south of the intersection between Cox Neck Road and Bergen Avenue. The revised routing is not proposed for additional traffic due to vehicle bringing in workers which would arrive at the beginning of the day and leave at the end of the day. As sources on Bergen Avenue were not considered in the Potential Impacts Analysis, additional acoustic data was collected along Bergen Avenue to quantify the existing ambient sound levels on August 2nd, 2022. Figure 33 below shows the location of the readings collected, noted as Location 5 and Table 19 provides the results of the acoustic readings collected. The afternoon L90 was used in the analysis as the ambient sound level Figure 33: Location 5 for Data Collection at Bergen Avenue / Table 19: Results of Twenty Minute Acoustic Readings at Bergen Avenue Measurement Location Time Period LAeq (dBA) LASmax (dBA) L10 (dBA) L50 (dBA) L90 (dBA) LASmin (dBA)  Location 5 7:39am – 7:59am 59 78 56 46 43 40   5:39pm – 5:59pm 65 87 54 42 41 40   SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): To evaluate traffic, additional traffic distributions were needed to evaluate traffic down Bergen Avenue for both the Existing Conditions were needed. Reference data was provided from the traffic consultant and can be found from 8 AM – 4PM in Section 3.6.11. For additional trips, the additional trip generation data for Excavation Phases 1 and 2 were used as they represent the highest truck traffic during construction. However, the additional trip generation differs from that found in Tables 20 and 21 for peak hour and non-peak hour trip generation on Cox Neck Road and Bergen Avenue since trucks are not traveling twice down this road after leaving the Project Site and will instead be returning to Sound Avenue via Bergen Avenue. Table 20: Peak Hour Additional Trip Generation for Alternate Excavation Phase Vehicle Class Cox Neck Lane Bergen Avenue  Automobiles 13  13  Medium Trucks 0 0  Heavy Trucks 5 5  Buses 0 0  Motorcycles 0 0   Table 21: Non-Peak Hour Additional Trip Generation for Alternate Excavation Phase Vehicle Class Cox Neck Lane Bergen Avenue  Automobiles 0 0  Medium Trucks 0 0  Heavy Trucks 5 5  Buses 0 0  Motorcycles 0 0   Using the additional trip generation data, the TNM analyses in SoundPlan were completed for R15 – R18 for receivers on Cox Neck Road, and then for new receivers R19 – R24 for new receivers which were inserted into the model for Bergen Avenue. Using the results, the sound levels at R15 – R18 for the alternate truck plan were compared to the sound levels during Excavation Phase 1 to show the reduction in sound level. Table 22 shows the existing and predicted excavation phase peak hour Leq sound levels, while Table 23 shows the existing and predicted excavation phase 8-hour Leq sound levels at each location. Figures 34 and 35 show the graphic representations of the existing peak hour and 8-hour sound levels, respectively. Figures 36 and 37 show the graphic representation of the excavation phase peak hour and 8-hour Leq sound levels, respectively. As seen in the figures, there is a 1-2 dBA reduction in both peak hour and 8-hour sound levels, showing an improvement in sound levels at the locations along Cox Neck Road. Although there would now be an impact to receivers along Bergen Avenue, all predicted sound levels are lower than the NYSDOTs suggested criteria of 67 dBA at the receivers considered in the alternate plan. SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): Table 22: Peak Hour Sound Levels with the Alternate Excavation Truck Route Receiver Number Location Existing Conditions (dBA) Alternate Excavation (dBA) Proposed Excavation  R15 2695 Cox Neck Road 55 65 73  R16 1475 Cox Neck Road 55 62 70  R17 1020 Cox Neck Road 55 62 62  R18 55 Middle Road 60 63 63  R19 5350 Bergen Avenue 51 62 44  R20 4680 Bergen Avenue 48 52 44  R21 4300 Bergen Avenue 50 54 46  R22 3049 Bergen Avenue 48 49 46  R23 1525 Bergen Avenue 52 53 46  R24 1405 Bergen Avenue 52 53 46   Table 23: Eight Hour Sound Levels with the Alternate Excavation Truck Route Receiver Number Location Existing Conditions (dBA) Alternate Excavation (dBA) Proposed Excavation  R15 2695 Cox Neck Road 55 65 73  R16 1475 Cox Neck Road 55 62 70  R17 1020 Cox Neck Road 55 62 62  R18 55 Middle Road 60 63 63  R19 5350 Bergen Avenue 51 62 44  R20 4680 Bergen Avenue 48 52 44  R21 4300 Bergen Avenue 50 54 46  R22 3049 Bergen Avenue 48 49 46  R23 1525 Bergen Avenue 52 53 46  R24 1405 Bergen Avenue 52 53 46   SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): Figure 34: Existing Peak Hour Sound Levels at Bergen Avenue and Cox Neck Road / SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): Figure 35: Existing Eight Hour Sound Levels at Bergen Avenue and Cox Neck Road / SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): Figure 36: Alternate Truck Route Eight Hour Sound Levels at Bergen Avenue and Cox Neck Road / SECTION 3.6.8 – REVIEW OF ALTERNATE TRUCK ROUTE (Continued): Figure 37: Alternate Truck Route Peak Hour Sound Levels at Bergen Avenue and Cox Neck Road / SECTION 3.6.9 – REVIEW OF ALTERNATE SITE PLAN: Construction Noise Impacts To evaluate the difference in construction noise impacts in the proposed planProposed Plan compared to the Alternate Site Plan, the Excavation Drainage phase was selected. This phase is anticipated to have the highest sound levels created once the excavation is complete and the two plans would be sufficiently different to compare. The same equipment utilizations, sound levels, and traffic generation were used for evaluation, with the only changes made being the location and grading to match the Alternate Site Plan. Figures 3038 and 3139 present the graphic representation of the data during construction for the peak hour sound level generation and 8-hour Leq sound levels predicted at the Project Site. Figures 32-3540-43 show the predicted 8-hour Leq and peak hour sound levels at West Mill Road and Cox Neck Road. Tables 1824 and 1925 present the predicted sound levels for all receiving locations for the 8-hour Leq and peak hour Leq, respectively. Tables 1824 and 1925 also present the difference in predicted sound pressure levels for a direct comparison to the proposed plan.Proposed Plan. Results show that there would be a significantan overall increase in sound level because the grade would no longer actfunction as an acoustic barrier and would lose the transmission loss provided by the retaining wall. This is most evident at R1R4, where increases range from 10-164-5 dBA, as well as R2-R7 as well as R9,additional receivers which show increases ranging from a 1-3-10 dBA. These changes are significant and will cause a greater disturbance to increase. It should be noted, that R6 shows a wider range of areas2 dBA reduction in expected sound level with the alternate plan. However, all other receptors show either no difference, or an increase in sound levels during the construction. when the Alternate Site Plan is implemented. SECTION 3.6.79 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Figure 30: Peak38: Eight Hour Leq Sound Levels from the Excavation Drainage Phase at the Project Site with the Alternate Site Plan / / SECTION 3.6.79 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Figure 3139: Peak Hour Leq Sound Levels from the Excavation Drainage Phase at the Project Site with the Alternate Site Plan / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS:9 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Figure 3240: Eight Hour Leq Sound Levels from the Excavation Drainage Phase at West Mill Road and Cox Neck Road with the Alternate Site Plan / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts9 – REVIEW OF ALTERNATE SITE PLAN (Continued)): Construction Noise Impacts (Continued) Figure 3341: Peak Hour Sound Levels from the Excavation Drainage Phase at West Mill Road and Cox Neck Road with the Alternate Site Plan / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS: Construction Noise Impacts9 – REVIEW OF ALTERNATE SITE PLAN (Continued)): Construction Noise Impacts (Continued) Figure 3442: Eight Hour Sound Levels from the Excavation Drainage Phase at Cox Neck Road with the Alternate Site Plan / / SECTION 3.6.6 – POTENTIAL IMPACTS ANALYSIS:9 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Construction Noise Impacts (Continued) Figure 3543: Peak Hour Sound Levels from the Excavation Drainage Phase at Cox Neck Road with the Alternate Site Plan / / SECTION 3.6.89 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Construction Noise Impacts (Continued) Table 1824: 8-Hour Sound Pressure Levels at All Receivers for Construction Activities and Additional Traffic with the Alternate Site Plan and Difference in Sound Pressure Level compared to the Proposed Plan Receiver Number Location Existing Condition (dBA) Proposed Plan Construction (dBA) Alternate Plan Construction (dBA) Difference (dBA)  R1 5106 West Mill Road 44 5150 6851 161  R2 800 North Drive 44 7176 7578 41  R3 805 North Drive 44 6469 6971 52  R4 2010 West Mill Road 4544 4957 5961 104  R5 4105 West Mill Road 50 5157 5860 73  R6 200 East Mill Road 4544 5060 5958 9-2  R7 750 East Mill Road 4544 5459 59 40  R8 3329 Grand Ave 44 5968 6169 20  R9 3001 West Mill Road 4746 4852 5554 72  R10 1525 West Mill Road 6150 6162 6162 0  R11 1480 West Mill Road 6352 6364 6466 02  R12 1065 West Mill Road 6352 64 6466 02  R13 155 Breakwater Road 6352 6364 6366 02  R14 2100 Cox Neck Road 6657 66 66 0  R15 2695 Cox Neck Road 6655 66 66 0  R16 1475 Cox Neck Road 6454 6465 6465 0  R17 1020 Cox Neck Road 6256 6261 6261 0  R18 55 Middle Road 6660 6662 6662 0   SECTION 3.6.89 – REVIEW OF ALTERNATE SITE PLAN (Continued): Construction Noise Impacts (Continued) Construction Noise Impacts (Continued) Table 1925: Peak Hour Sound Pressure Levels at All Receivers for Construction Activities and Additional Traffic with the Alternate Site Plan and Difference in Sound Pressure Level compared to the Proposed Plan Receiver Number Location Exist ing Condition (dBA) Proposed Plan Construction (dBA) Alternate Plan Construction (dBA) Difference (dBA)  R1 5106 West Mill Road 44 5957 7158 122  R2 800 North Drive 44 8084 8487 52  R3 805 North Drive 44 7377 7680 3  R4 2010 West Mill Road 44 5565 6370 85  R5 4105 West Mill Road 5049 5465 6368 93  R6 200 East Mill Road 44 5768 6366 6-2  R7 750 East Mill Road 44 6367 6468 10  R8 3329 Grand Ave 44 6777 6978 1  R9 3001 West Mill Road 4746 5058 5961 93  R10 1525 West Mill Road 6050 6064 6264 10  R11 1480 West Mill Road 6352 6366 6367 1  R12 1065 West Mill Road 6352 6366 6368 01  R13 155 Breakwater Road 6352 6366 6368 02  R14 2100 Cox Neck Road 6557 6668 6668 0  R15 2695 Cox Neck Road 6655 6668 6668 0  R16 1475 Cox Neck Road 6454 6466 6466 0  R17 1020 Cox Neck Road 6256 62 62 0   R18 55 Middle Road 6360 6362 6362 0   SECTION 3.6.89 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition Impacts As discussed previously, the Build Condition for the proposed planProposed Plan has no impact predicted on the nearby receivers. The most considerable difference between the proposed planProposed Plan and the Alternate Site Plan is the ramp which will need to be used to access the storage buildings. Vehicles using this ramp will need to accelerate more significantly to access the area, leading to increased sound generation. Figures 36-3844-46 presents the graphic representation of the data, while Table 2026 presents the predicted sound levels at all receivers. The Build Condition would still comply with the Noise Code and would have the same anticipated sound level except at R2 where the increase due to the Alternate Site Plan is only 1 dBA, which is not perceivable. Figure 36:44: Peak Hour Sound Levels in the Build Condition at the Project Site with the Alternate Site Plan / / SECTION 3.6.8 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition Impacts (Continued) Figure 37: Peak Sound Levels in the Build Condition at West Mill Road and Cox Neck Road with the Alternate Site Plan / 9 SECTION 3.6.8 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition (Continued) Figure 38: Peak Hour Sound Levels in the Build Condition at Cox Neck Road with the Alternate Site Plan / SECTION 3.6.8 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition Impacts (Continued) Figure 45: Peak Sound Levels in the Build Condition at West Mill Road and Cox Neck Road with the Alternate Site Plan / SECTION 3.6.9 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition (Continued) Figure 46: Peak Hour Sound Levels in the Build Condition at Cox Neck Road with the Alternate Site Plan / SECTION 3.6.9 – REVIEW OF ALTERNATE SITE PLAN (Continued): Build Condition Impacts (Continued) Table 2026: Sound Pressure Levels at All Receivers for the Build Condition with the Alternate Site Plan and Difference in Sound Pressure Level compared to the Proposed Plan  Description  Receiver Number Location Existing Condition (dBA) Proposed Plan Construction (dBA) Alternate Plan Construction (dBA) Excavation Phase 2Difference in Sound Level (dBA)  R1 5106 West Mill Road 44 44 44 0  R2 800 North Drive 44 48 49 1  R3 805 North Drive 46 45 45 0  R4 2010 West Mill Road 47 44 44 0  R5 4105 West Mill Road 51 50 50 0  R6 200 East Mill Road 44 45 45 0  R7 750 East Mill Road 44 44 44 0  R8 3329 Grand Ave 44 45 45 0  R9 3001 West Mill Road 47 47 47 0  R10 1525 West Mill Road 60 60 60 0  R11 1480 West Mill Road 63 63 63 0  R12 1065 West Mill Road 63 63 63 0  R13 155 Breakwater Road 63 63 63 0  R14 2100 Cox Neck Road 65 65 65 0  R15 2695 Cox Neck Road 66 66 66 0  R16 1475 Cox Neck Road 64 64 64 0  R17 1020 Cox Neck Road 62 62 62 0  R18 55 Middle Road 63 63 63 0   SECTION 3.6.910 – REFERENCE DATA USED FOR ANALYSIS: Table 2127: Sound Pressure/Power Levels for Sources Evaluated  Sound PressurePower Level (dB) at Identified Frequency (Hz)    Source Description Label 63 125 250 500 1000 2000 4000 8000 Sound Power Level (dBA) Calculated Sound Pressure Level at 50' (dBA)  Payloader S1 116 112 109 112 104 98 96 89 111 80   Shouting S2 0 40 56 69 71 67 61 49 74 42  Excavator S3 110 106 110 109 109 106 100 92 113 81  Water/Fuel Truck S4 107 112 109 112 109 108 103 96 115 83  Truck Accelerating S5 108 108 106 109 108 108 108 109 115 84  Dozer S6 111 112 108 105 107 104 114 103 116 85  Tub Grinder S7 107 107 107 107 107 107 107 107 114 8290  Woodchipper S8 96139 96129 96121 96116 96113 96112 96112 96114 103122 7190  Feller Buncher S9 107139 107129 107121 107116 107113 107112 107112 107114 114122 82  Skid Steer S10 113 111 104 103 103 100 100 89 108 76  Mini Excavator S11 102 94 92 92 91 88 87 78 96 64  Telescopic Forklift S12 108 102 98 96 96 92 88 85 100 68  Sc issor Lift S13 108 105 102 102 102 99 93 91 106 5974  Raised Voices S14 0 53 59 64 59 54 49 43 64 1132  Boat Washing S15 69 60 60 67 69 66 66 66 74 3442  Measur ed Air Brake Release S16 91 83 80 83 87 82 76 70 89 3858  Measured Dump Truck Idling with White Noise Backup Alarm S17 95 91 82 85 91 84 81 69 93 3762   Measured Dump Truck Idling with White Noise Backup Alarm S17 95 91 82 85 91 84 81 69 93 3762   SECTION 3.6.1011 – EXISTING TRAFFIC DISTRIBUTIONS UTILIZED FOR ANALYSES: Table 28: Existing Traffic Distribution at West Mill Road Hour Automobiles Medium Trucks Heavy Trucks Buses Motorcycles  0 1 1 0 0 0  1 1 0 0 0 0  2 1 1 0 0 0  3 1 0 0 0 0  4 1 1 0 0 0  5 1 2 0 0 0  6 6 5 0 1 0  7 14 12 0 0 0  8 17 12 0 0 0  9 18 9 0 0 0  10 21 13 0 0 0  11 25 13 0 0 1  12 28 13 0 0 0  13 26 16 1 1 1  14 25 14 0 0 0  15 19 11 0 0 0  16 35 13 0 0 0  17 25 9 0 0 0  18 16 5 0 0 0  19 16 5 0 0 0  20 10 2 0 0 0  21 8 1 0 0 0  2 2 7 1 0 0 0  23 3 0 0 0 0   SECTION 3.6.11 – EXISTING TRAFFIC DISTRIBUTIONS UTILIZED FOR ANALYSES: Table 29: Existing Traffic Distribution at Cox Neck Road Hour Automobiles Medium Trucks Heavy Trucks Buses Motorcycles  0 11 3 0 0 0  1 6 0 0 0 0  2 2 2 0 0 0  3 4 1 0 0 0  4 5 3 0 0 0  5 18 8 0 1 0  6 31 22 0 2 0  7 73 56 1 1 0  8 93 60 2 0 1  9 108  57 1 1 0  10 114 59 1 0 1  11 140 64 1 0 2  12 153 61 1 2 0  13 134 58 2 0 1  14 132 60 1 0 1  15 136 60 1 0 0  16 140 64 1 0 0  17 155 51 0  0 1  18 134 50 0 0 1  19 107 39 0 0 0  20 98 23 0 0 0  21 73 15 0 0 0  22 46 9 0 0 0  23 20 3 0 0 0   SECTION 3.6.11 – EXISTING TRAFFIC DISTRIBUTIONS UTILIZED FOR ANALYSES: Table 30: Existing Traffic Distribution at Sound Avenue Hour Automobiles Medium Trucks Heavy Trucks Buses Motorcycles  0 44 10 0 0 0  1 19 5 0 0 0  2 10 3 0 0 0  3 13 5 0 1 0  4 35 19 0 1 0  5 147 75 0 4 0  6 407 216 1 8 0  7 659 309 2 7 1  8 735 292 3 12 1  9 756 255 4 13 2  10 777 265 1 12 1  11 867 238 2 12 2  12 985 260 3 11 2  13 916 241 1 10 1  14 1006 278 2 11 2  15 1085 335 2 11 1  16 1308  342 1 9 1  17 1086 264 0 3 1  18 844 197 0 2 1  19 582 124 0 1 0  20 500 93 0 0 0  21 337 62 0 1 0  22 244 34 0 1 0  23 122 22 0 0 0   SECTION 3.6.11 – EXISTING TRAFFIC DISTRIBUTIONS UTILIZED FOR ANALYSES: Table 31: Existing Traffic Distribution at Sound Avenue Hour Automobiles Medium Trucks Heavy Trucks Buses Motorcycles  0 44 10 0 0 0  1 19 5 0 0 0  2 10 3 0 0 0  3 13 5 0 1 0  4 35 19 0 1 0  5 147 75 0 4 0  6 407 216 1 8 0  7 659 309 2 7 1  8 735 292 3 12 1  9 756 255 4 13 2  10 777 265 1 12 1  11 867 238 2 12 2  12 985 260 3 11 2  13 916 241 1 10 1  14 1006 278 2 11 2  15 1085 335 2 11 1  16 1308  342 1 9 1  17 1086 264 0 3 1  18 844 197 0 2 1  19 582 124 0 1 0  20 500 93 0 0 0  21 337 62 0 1 0  22 244 34 0 1 0  23 122 22 0 0 0   SECTION 3.6.12 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING: Figure 3947: Noise Monitoring Data from Wednesday 4/14/21 at Location 1 / Figure 4048: Noise Monitoring Data from Thursday 4/15/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 4149: Noise Monitoring Data from Friday 4/16/21 at Location 1 / Figure 4250: Noise Monitoring Data from Saturday 4/17/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 4351: Noise Monitoring Data from Sunday 4/18/21 at Location 1 / Figure 4452: Noise Monitoring Data from Monday 4/19/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 4553: Noise Monitoring Data from Thursday 4/20/21 at Location 1 / Figure 4654: Noise Monitoring Data from Wednesday 4/21/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 4755: Noise Monitoring Data from Thursday 4/22/21 at Location 1 / Figure 4856: Noise Monitoring Data from Friday 4/23/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 4957: Noise Monitoring Data from Saturday 4/24/21 at Location 1 / Figure 5058: Noise Monitoring Data from Sunday 4/25/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 5159: Noise Monitoring Data from Monday 4/26/21 at Location 1 / Figure 5260: Noise Monitoring Data from Tuesday 4/27/21 at Location 1 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 5361: Noise Monitoring Data from Wednesday 4/28/21 at Location 1 / Figure 5462: Noise Monitoring Data from Wednesday 4/28/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 5563: Noise Monitoring Data from Thursday 4/29/21 at Location 2 / Figure 5664: Noise Monitoring Data from Friday 4/30/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 5765: Noise Monitoring Data from Saturday 5/1/21 at Location 2 / Figure 5866: Noise Monitoring Data from Sunday 5/2/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 5967: Noise Monitoring Data from Monday 5/3/21 at Location 2 / Figure 6068: Noise Monitoring Data from Thursday 5/13/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 6169: Noise Monitoring Data from Friday 5/14/21 at Location 2 / Figure 6270: Noise Monitoring Data from Saturday 5/15/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 6371: Noise Monitoring Data from Sunday 5/16/21 at Location 2 / Figure 6472: Noise Monitoring Data from Monday 5/17/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 6573: Noise Monitoring Data from Tuesday 5/18/21 at Location 2 / Figure 6674: Noise Monitoring Data from Wednesday 5/19/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 6775: Noise Monitoring Data from Thursday 5/20/21 at Location 2 / Figure 6876: Noise Monitoring Data from Friday 5/21/21 at Location 2 / SECTION 3.6.1012 – DAILY SUMMARY GRAPHS FROM NOISE MONITORING (Continued): Figure 6977: Noise Monitoring Data from Saturday 5/22/21 at Location 2 / Figure 7078: Noise Monitoring Data from Sunday 5/23/21 at Location 2 /