HomeMy WebLinkAboutAppendix F - SYC Construction Schedule and DetailsRed Rock Industries, Inc. PO Box 1037 Plainview, NY 11803 (T)516.833.6942
Page 1 of 3
STRONG’S YACHT CENTER
1)Tree Removal / Grubbing and Haul Road Construction
(approximately 2 weeks)
a.1 excavator with operator - 1 vehicle
b.1 feller buncher (tree handling equipment) with operator - 1 vehicle
c.1 woodchipper with operator - 1 vehicle
d.1 tub grinder with operator - 1 vehicle
e.1 payloader with operator - 1 vehicle
f.1 trailer with driver - 1 vehicle
g.4 Laborers - 2 vehicles for 4 laborers
o 8 vehicles total
ALL EQUIPMENT EXCEPT FOR TRAILER STAYS ON SITE DURING THIS PHASE
2)Excavation Phase 1 (5-6 months)
a.40 trailers with operator
(1 vehicle for operator)
b.2 loaders with operator - 2 vehicles
c.2 excavators with operator - 2 vehicles
d.1 fuel truck / water truck with operator - 1 vehicle
e.2 dozers with operator - 1 vehicle
f.1 Project Manager - 1 vehicle
g.1 Site Safety Super - 1 vehicle
h.2 Flagmen - 1 vehicle
i.4 Laborers - 2 vehicles
o 12 vehicles total
EQUIPMENT IN B, C, AND E STAYS ON SITE DURING THIS PHASE
3)Excavation Phase 2 (2-4 weeks)
a.40 trailers with operator - 1 vehicle
b.2 loaders with operator - 2 vehicles
c.2 excavators with operator - 2 vehicles
d.1 fuel truck / water truck with operator - 1 vehicle
e.2 dozers with operator - 2 vehicles
f.1 Project Manager - 1 vehicle
g.1 Site Safety Super - 1 vehicle
h.2 Flagmen - 1 vehicle
i.4 Laborers - 2 vehicles
o 13 vehicles total
EQUIPMENT IN B, C, AND E STAYS ON SITE DURING THIS PHASE
4)Retaining Wall (3 weeks)
a.1 excavator with operator
Red Rock Industries, Inc. PO Box 1037 Plainview, NY 11803 (T) 516.833.6942
Page 2 of 3
b. 1 loader with operator
c. 1 skid steer with operator
d. 1 mini excavator with operator
e. 4 Laborers
*Note* Wall to be installed while construction of building is in progress
*Vehicles duplicated - see Excavation Phase 1
EQUIPMENT IN A, B, C AND D STAYS ON SITE DURING THIS PHASE
MATERIAL DELIVERY FOR RETAINING WALL: APPROXIMATELY 60 TRUCKS
5) Excavation Drainage (8 weeks)
a. 1 loader with operator
b. 2 excavators with operator
c. 1 mini excavator with operator
d. 1 skid steer with operator
e. 1 trailer with operator - material delivery precast / pipe, etc.
*Note* Work to be installed while construction of building is in progress
*Vehicles duplicated - see Excavation Phase 2
EQUIPMENT A, B, C AND D STAYS ON SITE DURING THIS PHASE
6) Construction Phase 3 (6 months, inclusive of wall and drainage above)
a. 2 loaders with operator
b. 1 excavator with operator
c. 1 fuel truck with operator
d. 2 skid steers with operator
e. 1 mini with operator
f. 1 dozer with operator
g. 1 telescopic fork lift
h. 1 Project Manager
i. 1 Site Safety Super
j. Scissor & telescopic lifts
*Note* Labor will vary from 20 employees to 60 as job progresses
*Company vehicles are mostly used (4 persons per vehicle)
15 - 20 vehicles total
EQUIPMENT IN A, B, D, E, F, AND G STAYS ON SITE DURING THIS PHASE
MATERIAL DELIVERY: APPROXIMATELY 12 TRUCKS
CONCRETE FOUNDATION: APPROXIMATELY 89 TRUCKS
TOTAL TRUCKS FOR MATERIAL DELIVERY AND FOUNDATIONS: 101 TRUCKS
Red Rock Industries, Inc. PO Box 1037 Plainview, NY 11803 (T)516.833.6942
Page 3 of 3
NOTES
1)Security booth / gate - duration of project –(5’X5’ Kiosk at entrance & exit)
2)Dust control - 6’ fence with filter fabric around North & west corner
3)Day light savings - hours of operator to be reduced
4)Fall Festival - no weekend construction work – (September 15 - October 31)
5)Asphalt binder to be installed on shoulder of road prior at exit to prevent damage from tag axles
6)Sweeper required daily for roadway maintenance
7)Signage - truck enter & exiting
8)Job trailer locations
9)Temporary water / electric / bathroom locations
10)Employee parking - enter & exiting
11)Jobsite dumpster location
12)First aid / fire extinguisher locations around site
*Staging areas shown on construction plan
*Signage & Booth shown on Haul Road Plan - at entrance & exit
13)Equipment Utilization: 50% OF WORK DAY
14)Overall workweek of M to Saturday 7 am to 7 pm.
-Excavation Phase: Trucking of materials will be M to Friday 7 am to 5 pm - Estimated 40 truck trips per
day (4 trucks/hour). On Saturdays and from 5 pm – 7 pm on weekdays, the on-site activity will be mostly
vehicle & machinery maintenance and planning for the following Monday at 7 am start.
-Construction Phase: Mon-Sat 7 am - 7 pm. On Saturdays, light duty crews expected with minimal truck
activity expected.