HomeMy WebLinkAbout47023-Z �o�OSUf�1 py Town of Southold 12/18/2021
P.O.Box 1179
N 53095 Main Rd
Southold,New York 11971
CERTIFICATE OF OCCUPANCY
No: 42635 Date: 12/18/2021
THIS CERTIFIES that the building ADDITION/ALTERATION
Location of Property: 25500 Route 25, Orient
SCTM#: 473889 Sec/Block/Lot: 18.-6-10
Subdivision: Filed Map No. Lot No.
conforms substantially to the Application for Building Permit heretofore filed in this office dated
5/13/2021 pursuant to which Building Permit No. 47023 dated 10/25/2021
was issued, and conforms to all of the requirements of the applicable provisions of the law. The occupancy for
which this certificate is issued is:
"as-built"pergola addition to existing single family dwelling as applied for.
The certificate is issued to Sutton,Alexander&Tracy
of the aforesaid building.
SUFFOLK COUNTY DEPARTMENT OF HEALTH APPROVAL
ELECTRICAL CERTIFICATE NO.
PLUMBERS CERTIFICATION DATED
tho ize gnature
�o�SUFFQI�.co TOWN OF SOUTHOLD
Gy BUILDING DEPARTMENT
C. x TOWN CLERK'S OFFICE
"oy • �� SOUTHOLD, NY
BUILDING PERMIT
(THIS PERMIT MUST BE KEPT ON THE PREMISES
WITH ONE SET OF APPROVED PLANS AND SPECIFICATIONS
UNTIL FULL COMPLETION OF THE WORK AUTHORIZED)
Permit#: 47023 Date: 10/25/2021
Permission is hereby granted to:
Turturro, Joan
25500 Main Rd
Orient, NY 11957
To: Legalize as-built fence pergola at existing single family dwelling as applied for.
At premises located at:
25500 Route 25, Orient
SCTM # 473889
Sec/Block/Lot# 18.-6-10
Pursuant to application dated 5/13/2021 and approved by the Building Inspector.
To expire on 4/26/2023.
Fees:
AS BUILT- SINGLE FAMILY ADDITION/ALTERATION $400.00
CO-RESIDENTIAL $50.00
Total: $450.00
Building Inspector
pf SOUTyo�
` # # TOWN OF SOUTHOLD-BUILDING DEPT.
765-1802
INSPECTION '
[ ] FOUNDATION 1ST [ ] ROUGH PL13G.
[ ] .FOUNDATION 2ND [ ] NSULATION/CAU KING
[ ] FRAMING/STRAPPING [ ] FINAL iq- f
[ ] FIREPLACE &CHIMNEY [ ] FIRE SAFM INSPECTION'
[ ] FIRE-RESISTANT CONSTRUCTION [ ] FIRE RESISTANT PENETRATION
[ ] ELECTRICAL (ROUGH) [ ] ELECTRICAL (FINAL)
[ ] CODE VIOLATION [ ] PRE C/O
REMARKS:
DATE 1 1 lyb
FIELD.INSPECTION REPORT. 'DATE COIVIMENTS
FOUNDATION(IST) y
.. C
FOUNDATION'(2ND)
ROUGH FRAMING& 1
PLUMBING --4
1
� Q
d
INSULATION.PER.N.Y.
STATE ENERGY CODE
FINAL
ADDITIONAL CO
0
• � z
rn
z
ro
gUFFO�,�-
o�° TOWN OF SOUTHOLD-BUILDING DEPARTMENT
y Town Hall Annex 54375 Main Road P. O. Box 1179 Southold,NY 11971-0959
oy�o aol�9" Telephone(631) 765-1802 Fax(631) 765-9502 httys://www.southoldtom=.gov
Date Received -
APPLICATION FOR BUILDING PERMIT -,
L5C �IN
For Office Use Only
eN
-�^r
PERMIT NO. U MAY 3 2021
Building Inspector:
Applications and forms must be filled out in their entirety.Incomplete
applications will not be accepted. Where the Applicant is not the owner,an71
Owner's Authorization form(Page 2)shall be completed.
Date:
OWNER(S)OF PROPERTY:
Name: 4
_ - - #1000-
-- ' - I C)
Project Address:
Phone#: ��(p_��v�tU2 � Email:
Mailing Address:
CONTACT PERSON:
Name: cdYi C t C. KM l 00 M
Mailing Address: L�� G�G� � ( ( Cf
-7
Phone#: (+✓3�S -1 3-:�>o Email: C M(q0 C M DOrC'cc 5- car
DESIGN PROFESSIONAL INFORMATION:
Name:
Mailing Address:
Phone#: Email:
CONTRACTOR INFORMATION:
Name:
Mailing Address:
Phone#: Email:
DESCRIPTION OF PROPOSED CONSTRUCTION -
❑New Structure ❑Addition ❑Alteration []Repair ❑Demolition Estimated Cost of Project:
❑Other,hup,P� P�9f�4 , $
Will the lot be re-graded? ❑Yes o Will excess fill be removed from premises? ❑Yes ❑No
1
PROPERTY INFORMATION
Existing use of property: Fis' new 6 d (3) Intended use of property:
Zone or use district in which premises is situated: Are there any covena;No
nd restrictions with respect to
�,- 90 this property? Dyes IF YES, PROVIDE A COPY.
❑ Check Box After Reading: The owner/contractor/design professional is responsible for all drainage and storm water issues as provided by
Chapter 236 of the Town Code. APPLICATIONIS HEREBY MADE to the Building Department for the issuance of a Building Permit pursuant to the Building Zone
Ordinance of the Town of Southold,Suffolk,County,New York and other applicable Laws,Ordinances or Regulations,for the construction of buildings,
additions,alterations or for removal or demolition as herein described.The applicant agrees to comply-with all applicable laws,ordinances,building code,
housing code and regulations and to admit authorized'inspectors on premises and in building(s)for necessary inspections.False statements made herein are
punishable as a Class Amisdemeanor pursuant to Section 210.45 of the New York State Penal Law.
Application Submitted By(print name):—p f(Qcti CMAuthorized Agent Downer
Signature of Applicant Date:
STATE OF NEW YORK)
COUNTY OF 5 4*—
being
duly sworn, deposes and says that(s)he is the applicant
(Name of individual signing contract)above named,
(S)he is the /
(Contr ,ctor,Agent,Corporate Officer,etc.)
of said owner or owners, and is duly authorized to perform or have performed the said work and to make and file this
application;that all statements contained in this application are true to the best of his/her knowledge and belief; and
that the work will be performed in the manner set forth in the application file therewith.
Sworn before me this
day of MIAL4 20�/
yl PERKINS
oublic,State of New York
No.01PE6130636
uafled uffolk Cou
PROPERTY OWNER AUTHORIZATIQ�iklmi sion Expires.luly I n �
(Where the applicant is not the owner)
l'- Ta- CV 51/7116/I residing at Z5�5�0 0 /�r���� ZDl a(
.e 6 hereby authorize Pal�-a'q G��CJ��"t� to apply on
my ehalf to th T' wn of So Id Building Department for approval as described herein.
Ow er' nature'Qj Date
Print Owner's Name
2
51020 MAIN ROAD
SOUTHO1LD NY 11971
631076504330
PATRICIA C.MOORE(BY )
77a-Cel -7- 7��1'7
COMMENT
Tra t &ex ® 67SS`Oo
DOo C--
Q� ✓a� /S D�1 raj S(de
is G d f0 Ake -0 a4ld Ca/
r
w f
51020 MA? 2
SOUT41OLD NY 11971 D L� C E # U LS
SEP 2 9 2021
BUILDING DEPT
TOWN OF SOUTHOLD
r
PAIMCIA C.NIOOP F(B Y�
r
9 z 2i
0
d moo/
d % 1
zmo
MAK11�1 POAD
lmm
SO'O"1 HOLD NY 119711
63.1.765.4330
r'
i
-- r 1ATRiC1A C.MOORE(BY �
CT 1 ?107,
TpW�O ISO p�pT
Area_ Note: ALL SUBSURFACE STRUCTURES; UNAUTHORIZED ALTERATION OR ADF)HION
WATER SUPPLY, SANITARY SYSTEMS, TO THIS SURVEY IS A VIOLATION OF
v�.vm JM namoar JM DRAINAGE, DRYWELLS AND UTILITIES, SECTION 7209 OF THE NEW YORK STATE
SHOWN ARE FROM FIELD OBSERVATIONS EDUCATION LAW.
40,314 sq.ft. �,�Gti MARCH 1021 AND OR DATA OBTAINED FROM OTHERS. COPIES OF THIS SURVEY MAP NOT [31 ARINC
THE LAND SURVEYOR'S INKED SEAT. OR
0.93 acres oP)x'w K' 21\MAN ROAM 25500 THE EXISTENCE OF RIGHTS OF WAY
EMBOSS
SE
SHALT_ NOT BE CONS IL7CR(U
AND/OR EASEMENTS OF RECORD IF TO BE A VALID TRUE COPY.
ANY, NOT SHOWN ARE NOT GUARANTEED. GUARANTEES INDICATED HEREON SHALT RUN
ONLY TO THE PERSON FOR WHOM PIE SURVFY
IS PREPARED, AND ON HIS BEHAII IO ILII
Premises known r.s. TITLECOMPANY. GOVF12NM1:�NTAI ACLNCY AND
# 25500 Moia Read, Oricnt LFNDINO INSTITUTION LISTED HEREON. AND
TO THE ASSIGNEES OF THE LENDING INSN-
LUTEON. GUARANTEES ARE NOT IRANSf FRANLI.
C
em
i
es
25 u
1'�1� ,� ,p2• `TE
1 �
�65opOpp ,11t 101
L—�` 066 Ott N• weta` .,�Ie n 7d
`a 1 A45 0 as O
\ X9 0 ''••. / : ot, -e's
1\\\TVI ',.F, "t "�s•.`\_3�M�g Il9lN0 ,.. �,t<
/ "`` ° Fr1 4 NIINN tso
w" E
2 bo ORS n
�9,�1 06 Vol
6Vl Q,
o�
00 Sq Mss �C
p
1
C�
Lop" 4L o p3pW N
� ib°7 566 5 0
8913 55�'�
N
O
to
L/ O
-roPmF
l9yD yo[y
f1AY,p0��fD0URRLY OF
Crrlificd lo:
/Ibondcr I. Sullon
Irncy M. Sulion
I idclily NoNbml Idle Insurance Services, 0 C
Survey of Property
Sltuatc at
Orient
1.A/vn SURVCYING Town of Soufhold
C � Mintoville@aol.com Suffolk County, New York
Su1volVISO-* Tax Map #10.00-18-06-10
HILI k.MORIGAGI. SURVEYS
IOP(),R;IAWG SURVEYS Scale 1"= 30' March 10 2021
LAND I'I.ANNFRS )
SI,I I•IAWi GRAPHIC SCALL
JOHN MIN')'(). PI{DNF: (G.31) %JA-AA3Z 3n a IS 30 6a t)O
I Y:�I I)I•ai l'ti!ilt)Nnl.IANn ilVl.vaa
FAX: (631) 72A-5,155
01f SMITHTOWN BOULEVARD SA41%'11TOWN1 A\ Y. 11787 ( IN FEET )
I inch = 30 it.
1 }
APPROVED AS NOTED Parking for guests 2
DATE: 0-g'r - B.P. Oaf 3
FEE: BY: 4
NOTIFY BUILDING DEPARTMENT AT 5
765-1802 8 AM TO 4 PM FOR THE
FOLLOWING INSPECTIONS:
1. FOUNDATION - TWO REQUIRED
FOR POURED CONCRETE
2. ROUGH - FRAMING & PLUMBING 1
F
3. INSULATION Owner parking
4. FINAL - CONSTRUCTION MUST
BE COMPLETE FOR C'O. . 12:
ALL CONSTRUCTION SHALL MEET THE Z
DN
IM
REQUIREMENTS OF THE CODES OF NEW N Pergolattrellis
YORK STATE. NOT RESPONSIBLE FOR
UL
DESIGN OR CONSTRUCTION ERRORS.
DN
OCCUPANCY OR
USE IS UNLAWFUL
WITHOUT CERTIFICATE I ��
OF OCCUPANCY
Shea M AY 1 3 2021
COMPLY WITH ALL CODES OF
NEW YORK STATE & TOWN CODES Owner parking
AS REQUIRED AND CONDITIONS OF
SOUTHOLD TOWN ZBA
SOUTHOLD TOWN PLANNING BOARD HES►y0
SOUTHOLD TOWN TRUSTEESSite
1 1
N.Y.S.DEC = 3ol-o-
�
Additional y
v
Certification
May Be Required. pQ� ssto��'
25500 Main Road Site plan for parking
Tracy & Alex Sutton Orient, NY 11957 Project number: 101
April 28, 2021
A101
Drawn by: Tracy Sutton N
P
Screened Porch
Porch
Owner parking
Exit
1
12"concrete footing 12"X 30"concrete footing A106
Living Room Foyer' Dming Rom.
2 Fire Places
�. Pergola/trellis
D
- Exit
P
Parlour
DN zo7 sF _ 1
i IWbm A105
I
ramp' i
----- 207 SF
O7f
Private
Iltllll. 11tl L� ���
Private Bedrown-Owners use
' =SF �
Z
p 1684+
Exit
25500 Main RoadLo
Floor Plan Level 1 a.
Trac & Alex Sutton orient, NY 11957 Projectnumber: 101 v
Y April 28, 2021 Al 02
---
- Drawn by: Tracy-Sutton- - -- - o
D
Room 5 Room 4 Room 3
252 SF 141 SF 265 SF
12
5
Cerkral H&UW
2%SF
Rom.6
267 SF
Exit :
N
® SbmRoom 2
41 SF
1111111 Jill 11
r
Owners private apace
164 SF
F
fl51
�i�ESS10��'
25500 Main Road Floor Plan Level 2
` Tracy & Alex Sutton Orient, NY 11957 Project number: 101
April 28,2021 Al 03
Drawn by: Tracy Sutton
--- __ Checked by Scale
1
A106
12"X 30"concrete footing
17'concrete footing 7 x 8"cedar column wrapped with smooth cedar s ' gles 4"x 4"MCQ posts wrapped with 1"x N'&1"x 5"cedar
3'- 1/8" 8'-0" 3'-11 1/8"
1'-6"
i IM
Sk
I I
1
—- — — — 7'x2"cedar lattice
M
3'-11 3/8"
My
7'X 8"cedar
A105
Pergola/trellisi a F 2021
GUILD!P,IG GF T. +
Town OF SOLM-,OLD 51 r$;
4
Trac � Alex Sutton 25500 Main Road Pergola/fence Plan
YOrient, NY 11957 Project number: 101
October 4,2021
Al 04
- - Drawn by: Tracy Sutton
Checked by Scale 1/2"= 1'-9'
PROODUCED BY AN AU ESK STUDEN 'VERSION
Table 3.1 Nailing Schedule(Wood Framed Construction Manual 2018,Pages 149 and 193)
Notes: Number of Number of
Joint Description Common Nails Box Nails Nail Sparing
*Concrete used for footings is to be 3,500 psi ROOF NAILING
after 28 days minimum. Rafter to Top Plate(Toe-nailed) 3-8d 3-8d per rafter
Ceiling Joist to Top Plate(Toe-nailed) 3-8d 3-8d per joist
Ceiling Joist to Parallel Rafter(Face-nailed) 5-16d 5-16d each lap
*All pressure treated lumber is to be MCQ No. Ceiling Joist Laps Over Partitions(Fac:-nailed) 5-16d 6-16d each lap
2 or better Southern Yellow Pine. Collar re to Rafter(Toe-nailed) 2-10d 2-10d per tie
Blocking to Rafter(Toe nailed) 2-8d 2-10d each end
*All nails, baits, nuts and washers are to be Rim Board to Rafter End Nailed WALL FRAMING 2-16d 3-116d each end
hot dipped galvanized.
Tap Plate to Top Plate(Face wiled) 2-16d(1) 2-16d(1) per foot
Top Plates at Intersections(Face-nailed) 4-16d 5-16d joists-each side
Stud to Stud(Face-nailed) 2-16d 2-16d 24'o.c.
Header to Header(Face-nailed) 16d 116d 16'o.c.along edges
CLIMATIC AND GEOGRAPHIC DESIGN CRITERIA Top or Bottom Plate to Stud(End Nailed) 3-16d 2-40d per stud
Ground Snow Wind Seismic Weathering Frost Line Termite Decay Winter Design Ice Barrer Flood Hazards ,D
Load Speed Depth Temp. Undedayment Bottom Plate to Floor Joist,Band Joist,End joist or Blocking(Faa;Nailed) 2-16d(1,2) 2-16d(1,2) per foot
Re wired FLOOR FRAMING 0
20 psf 130 mph B Severe 36 in. Moderate to Slight to 10'F Yes �
Heavy Moderate Joist to Sill,Top Plate or Girder(roe wiled) 4-8d 4-10d per joist C
Bridging to Joist(Toe-nailed) 2-8d 2-10d each end n
Blocking to Joist(roe-nailed) 2-8d 2-10d each end m
Blocking to Sill or Top Plate(Toe-nailed) 3-16d 4-16d each block M
Ledger Stip to Beam(Face-nailed) 3-16d 4-16d each joist
Joist on Ledger to Beam(roe-nailed) 3-8d 3-10d perjoist
Band Joist to Joist(End-nailed) 3-16d 4-16d per joist
r.�� .�.��. �.���.�...,-,a a,•,r� Band Joist to Sill or Top Plate(roe-nailed) 2-16d(1) 3-16d (1) per foot D
ROOF SHEATHING Z
T-23(4- 4314' Structural Panels(See Notes 4,5 and 6) n
Interior Zone 8d 10d 6'edge/12'field C
_ Perimeter Edge Zone 8d 10d 6'edge/6'field O
r Gable End Rake with up to 1'Rake Overhang 8d 10d 6'edge/6'field
CEILING SHEATHING 111
Gypsum Wallboard I 5d coolers 5d coolers 7'edge/10'field N
WALL SHEATHING
cc
m Structural Panels(See Notes 1,2,and 3) 8d 10d 6edge/12'field
< > C
5d coolers 5d coolers 7'edge/10'field 0
Gypsum Wallboard M
Gtade FLOOR SHEATHING Z
Structural Panels I
V or less 8d 10d 6'edge!12'field C
,•.rma. m
zt•,mocm ar,rme. ��
(1)Nailing requirements are based on wall sheathing nailed 6'on-center at the panel edge. Alternate nailing schedules shall cc
be used where wall sheathing nailing is reduced. For example,if wall sheathing is nailed 3 inches on-Genter at the panel edge '> .•:•;•'"'?
T� to obtain higher shear capacities,nailing requirements for structural members shall be doubled,or alternate connectors shall ® NEW '. .
be used to maintain load path.
(2)For wall sheathing within 4 feet of the comers,the four foot edge zone attachment requirements shall be used. `S�@`� C '
(3)Tabulated 12 inch o.c.nail spacing assumes wall sheathing attached to stud framing members with 0.42<G<0.49. A
(4) For roof sheathing within 4 feet of the perimeter edge of the roof,including 4 feet on each side of the roof peak,the 4 foot tis
perimeter zone attachment requirements shall be used.
(5)Tabulated 12 inch o.c.nail spacing assumes roof sheathing attached to ratter/truss framing members with G>0.49.For
framing members with<0.42<G<0.49,the nail spacing shall be reduced to 6 inches o.c.
6 For winds speeds greater than 130 mph,blocking is required which transfers shear load to two additional rafters 3 rafters in a:
( ) P 9 P , 9� eq (
total). r
(7)For exterior panel siding,galvanized box nails shall be permitted to be substituted for common nails.
Pergola/ Fence North Elevation
TRACY & ALEX SUTTON 25500 MAIN ROAD Project number 101
ORIENT, NY 11957 October 20, 2021 A 105
Drawn by Tracy Sutton
SCALE 3/16"=1'-0"
N0ISN3A 1N3dnis 3IS3d6inV NV As dabh lld
T x 8"cedar column wrapped with smooth cedar shingles
4"x 4"MCQ posts wrapped with 1"x 4"&1"x 5"cedar
r
r -
a0 ti
r � �
L0
r
Grade
i
27 x 2"cedar lattice
Gravel `' .{%� t„{:�•� :ti
� }^]moi� �:'��e- :�v� :'..ar..•/
12"0 Concrete
i^yw... s y�'ti•' a�y'r.. �j t�
Filled Sono Tube IX '_ ti:`;= ,} "�.•_ ;;;`;_ y
Footing
ti ':=j•'�� =``•'-y yfy;c.•S;,tsa
�J'er .05 684 op k"
r"
��FESSIO���
Pergola/ Fence North Elevation
TRACY & ALEX SUTTON 25500 MAIN ROAD Project number 101
ORIENT, NY 11957 October 20, 2021 A 106
Drawn by Tracy Sutton
---• - - --- - - — ————--- - SCALE 11Z'=I'-U'
a
4!'x 4"MCQ posts wrapped with 1"x 4'& 1"x 5"cedar
III III III I I fir:., ,•,`Y.� 1 NEI I 1 I I I I I I—
Gravel
=• "�. `.I 1111 III I ! 1=
_
_III MHEELIIII_
Dig `s •'�� : I I i=. Tl I I. 1111F1 III I II I IrI—
i III 11 I�Yi..sy • •t;-1 I I I IP: III I IJ,_
-7111 III
Concrete footing. 21r=1 I I 1 I I !
I I I I I 1 I I f. w`• L `�a�� l 1 Fir=.I�I I II 1 I �.i�i� ,
�..:;;` �-.: -�" �"�� -•- � .I I III III I I I-
111 NI 11EJ lrr _
III I I 1 111—� , �� � ,"Y"•-: y:-'`_ _ �_
•� _r^III I1I� I I1 I
III 111 III I I �•"�_. _� _.� _ �•� r 'r�':I 1 1 I I III I 11—
I I 111 l 111 ..•-Y F' -�_ . �' ,.`,,is .�Y}:�a -1 11111: III I
I I I III III I I I:�. _ ; �� ``•�• ••r'_•.T( ��I I I 1 I. III I I I—
~:'.�►a:• s Hyl'+'.i. :4,•
I I I III 111= `.'. J` •" • � `-I 1 I III III I I -
1 Pergola/fence footing detail
25500 Main Road Detail drawing of footing a_
Tracy & Alex Sutton Orient, NY 11957
Project number. 101
April 28,2021 Al 07
— - --- . Drawn by: Tracy-Sutton o
Checked by Scale 1"= T-O"